10/21/22 Huestis Hall Fire Suppression System Shutdown

UPDATE:   This work has been extended and will continue 10/21/22 from 6:00 am – 5:00 pm

BeginTuesday, October 11th, 2022 at 7:00 am Friday, October 21st, 2022 6:00 am

End:     Tuesday, October 11th, 2022 at 12:00 pm Friday, October 21st, 2022 5:00 pm

Building and area Impacted:  Huestis Hall

Scope: The fire suppression system will be down in Huestis Hall to cut and cap the fire riser at level 1 in the south stair FDC room.

Services Impacted:  Fire suppression systems in the basement will be maintained and operational.

Work Performed By:  Lease Crutcher Lewis and Harvey & Price

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

To view current construction and impacts. visit UO Map.

9/27/22 – 9/28/22 Huestis Basement Fire Suppression System Shutdown

DATE REVISED:
The date has been changed to Tuesday, September 27th and will end on Wednesday, September 28th.

 

Begin:  Wednesday, September 21st, 2022 Tuesday, September 27th, 2022 at 5:00 pm

End:      Thursday, September 22nd, 2022 Wednesday, September 28th, 2022 at 5:00 am

Building and Area Affected:  Huestis basement

Scope:  As part of the Huestis Renovation project, the fire suppression system will be shut down overnight in the Huestis Basement. Active fire watch will be conducted by Lease Crutcher Lewis. This work will be completed during night shift.

Details: Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions: If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By:  Lease Crutcher Lewis and Harvey & Price

Contact: Martina Oxoby, CPFM Owner’s Representative, 541-346-5880

To view current construction and impacts. visit UO Map.

9/27/22 Baker Downtown Center Fire Systems Testing – Rescheduled

UPDATE:
The fire system testing has been rescheduled for September 27th  at the same time.

 

Begin:  Friday, September 23rd, 2022 Tuesday, September 27th, 2022 at 6:00 am

End:      Friday, September 23rd, 2022 Tuesday, September 27th, 2022 at 8:00 am

Building and Area Affected:  Baker Downtown Center – Suite 100 and adjoining areas

Scope:  As a part of the Baker Center 100 remodel project, fire systems testing will be performed.

Details: Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions: If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By:  Sunset Electric

Contact: David Mason, CPFM Owner’s Representative, 541-346-5679

To view current construction and impacts. visit UO Map.

9/16/22 Huestis Fire Suppression System Work Advisory

Begin:  September 16th, 2022 at 7:00 am

End:      September 16th, 2022 at 3:30 pm

Building and Area:  Huestis room 034 and 001A for access, but shutdown will affect all spaces

Scope: As part of the Huestis Renovation project, the fire suppression system will be shut down in the Huestis Basement. Active fire watch will be conducted by Lease Crutcher Lewis.

Details:  Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions:  If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By: Lease Crutcher Lewis and Harvey & Price

Contact: Martina Oxoby, CPFM Owner’s Representative, 541-346-5880

9/14/22 Planned Power Outage

UPDATE:
Utilities & Energy has switched from island mode back to the normal power configuration as planned.
Please report any issues caused by the outage, including IT, to the CPFM Work Control Center at 541-346-2319,  workcontrolcenter@uoregon.edu, or by entering a service request on the UO call log https://cgis.uoregon.edu/Calllog.
Thank you.

 

 

We are writing to remind you of the upcoming annual planned power outage on Wednesday, September 14th, 2022.

In the event our campus service from the local EWEB electrical grid is interrupted, the UO Utility and Energy plant is capable of providing the campus with electricity (called Island Mode). To best ensure this system operates as designed when needed, the Utility and Energy plant now exercises this system annually. This year’s Island Mode event will take place on Wednesday, September 14, 2022, at 7:35 am. 

At 7:35 am, the entire campus will shift from the primary EWEB power source to the backup generator system at the Central Power Station, also known as “Island Mode”.

While not anticipated, some buildings may briefly lose power when the switch occurs, if a portion of the system does not perform as expected.

At 7:45 am, Feeder 1 will be de-energized.  Affected buildings will experience a  power outage lasting approximately 1 hour.  During this time Utilities and Energy staff will be disconnecting power in a vault for a switch replacement project and exchanging the feeder breaker. Crews will then ensure systems are successfully coming back online.

At 9:00 am, Feeder 10 will be de-energized.  Affected buildings will experience a power outage lasting 15 minutes. During this time Utilities and Energy staff will be exchanging the feeder breaker.  Crews will then ensure systems are successfully coming back online.

At 10:00 am, Standby feeder 2 will be de-energized. This will have no affect to the campus buildings.

At 12:00 noon, Utilities and Energy will Initiate normal power configuration.

For a detailed schedule of feeders and maps of buildings affected, visit the 2022 Power Outage webpage. Updates about the project will be posted on that page and Around the O.

Individuals who wish to request planning assistance for the outages should contact Campus Planning and Facilities Management Work Control at workcontrolcenter@uoregon.edu or 541-346-2319.

Please remember to shut down all multi-function copier devices as well as any printers. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.

To view current construction and impacts. visit UO Map.

8/25/22 Huestis Hall Fire Sprinkler System Shutdown

Begin:  Thursday, August 25th, 2022 at 7:00 am

End:      Thursday, August 25th, 2022 at 2:00 pm

Building(s) or Area(s) Affected:  Huestis Hall Basement

Scope:  As part of the Huestis Renovation project, the fire sprinkler system will be shut down in the Huestis Basement for demo and rerouting of fire sprinkler lines. Active fire watch will be conducted by Lewis.

Details:  Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions:  If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By:  Lewis and Harvey and Price

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

To view current construction and impacts. visit UO Map.

8/18/22 Allen Hall Transformer Testing Electrical Shutdown

Begin: Thursday, August 18th, 2022 at 8:00 am

End:     Thursday, August 18th, 2022 till 6:00 pm

Building Impacted:  Allen Hall

Scope:

  • Due to Data center required utility transformer testing the power will be shut down

from 8:00 am -12:30 pm. Allen hall will be on Standby power during this time.

  • From 12:30 pm to 6:00 pm Allen hall will be on normal power without Standby backup.

Services Impacted:  The entire building will be affected.

Work Performed By:  Utilities and Energy and Contractor

ContactRick Tabor, CPFM Interim Co-Dir Utilities & Energy, 541-346-7511

To view current construction and impacts, visit UO Map.

8/03/22 Huestis Hall Fire Suppression System Shutdown

Begin:  Wednesday, August 3, 2022 at 7:00 am

End:      Wednesday, August 3, 2022 at 12:00 noon

Building(s) or Area(s) Affected:  Huestis Hall

Scope:  The fire suppression system will be shut down to complete the isolation of the renovation zone from the active basement zone. Fire watch will be in place.

DetailsHorns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special InstructionsIf there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By:  Lease Crutcher Lewis, Harvey & Price

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

To view current construction and impacts. visit UO Map.

8/01/22 PLC Fire Alarm Noise Advisory

Begin:  Monday, August 1st, 2022 at 6:00 AM

End:    Monday, August 1st, 2022 at 8:00 AM

Building(s) or Area(s) Impacted:  PLC

Scope:  A contractor will be performing work on the fire system Monday morning. This may cause fire alarms to sound.

Details:  Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions:  If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By:  UO Safety & Risk Services and a contractor

Contact: Zach Earl, UO Fire Systems Program Manager, 541-521-0351 or 541-346-9295.

6/28/22 Lokey Education Fire Sprinkler Install

Begin:  June 28th, 2022 at 7:00 am

End:      June 28th, 2022 at 4:00 pm

Building Affected:  Lokey Education

Scope:  Due to installation of new fire sprinkler heads for the Lokey Education elevator modernization project the associated fire sprinkler system will be temporarily shut down between the hours of 7:00 am and 4:00 pm.

Services Impacted:  The fire alarm and sprinkler system will be shut down during this time.

Details:  Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. The contractor will monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions: If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By: Ryan Thomas Construction

Contact: Damon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285

6/16/22 Campus Fire Systems Testing and Maintenance Schedule for Summer 2022

Begin:  Tuesday, June 28th, 2022

End:     Friday, October 5th, 2022

Scope:  Summer 2022 Fire Systems Testing and Maintenance has been scheduled for the various campus buildings listed below.

Reminders will be sent to each building prior to testing.

Week of 6/27 – 6/30
Tuesday – 6/28                        6am – 8am Moss Street Children’s Center
Wednesday – 6/29                  6am – 8am Thompson Center
Thursday – 6/30                      6am – 8am Rainier
 

Week of 7/4 – 7/8
Tuesday – 7/5                           6am – 8am MKA / 13th Ave. Parking Garage
Wednesday – 7/6                    6am – 8am Jordan Schnitzer Museum of Art
Thursday – 7/7                         6am – 8am Central Kitchen
 

Week of 7/11 – 7/15
Tuesday – 7/12                         6am – 8am 1715 Franklin
Wednesday – 7/13                   6am – 8am Knight Law Center
Thursday – 7/14                       6am – 8am Beall Hall / Berwick Hall
 

Week of 7/18 – 7/22
Tuesday – 7/19                         6am – 8am Susan Campbell Hall
Wednesday – 7/20                  6am – 8am Hendricks Hall
Thursday – 7/21                        6am – 8am Gerlinger Hall and Gerlinger Annex
                                                  

Week of 7/25 – 7/29
Tuesday – 7/26                        6am – 8am Museum Natural Cultural History
Wednesday – 7/27                  6am – 8am Prince Lucien Campbell (PLC)
Thursday – 7/28                      6am – 8am Student Rec Center / Esslinger/ Tennis courts
 

Week of 8/1 – 8/5
Tuesday – 8/2                          6am – 8am Vivian Olum
Wednesday – 8/3                    6am – 8am Baker Downtown Center
Thursday – 8/4                        6am – 8am Spencer View Family Co-op
 

Week of 8/8 – 8/12
Tuesday – 8/9                          6am – 8am Johnson Hall / Collier House
Wednesday – 8/10                  6am – 8am Agate Hall
Thursday – 8/11                        6am – 8am Chapman Hall / Condon Hall
 

Week of 8/15 – 8/19
Tuesday – 8/16                         6am – 8am 510 Oak / 942 Olive
Wednesday – 8/17                   6am – 8am Deschutes Hall
Thursday – 8/18                       6am – 8am Zebrafish International Resource Center (ZIRC)
 

Week of 8/22 – 8/26
Tuesday – 8/23                        6am – 8am Oregon Hall
Wednesday – 8/24                 6am – 8am CPFM
Thursday – 8/25                      6am – 8am CPS / Chiller building
 

Week of 8/29 – 9/2
Tuesday – 8/30                        6am – 8am Fine Arts A, B, C
Wednesday –8/31                    6am – 8am Millrace 1, 2, 3
Thursday – 9/1                         6am – 8am 1900 Millrace
 

Week of 9/5 – 9/9
Tuesday – 9/6                          6 am – 8am Allen Hall
Wednesday – 9/7                    6 am – 8am Friendly Hall
Thursday – 9/8                        6 am – 8am Lawrence Hall
                                  

Week of 9/12 – 9/16
Tuesday – 9/13                         6 am – 8am Clinical Services
Wednesday – 9/14                  6 am – 8am HEDCO
Thursday – 9/15                       6 am – 8am Lokey Education / Alder
 

Week of 9/19 – 9/23
Tuesday – 9/20                       6 am – 8am University Hall
Wednesday – 9/21                  6 am – 8am McKenzie Hall
Thursday – 9/22                      6 am – 8am Villard Hall
 

Week of 9/26 – 9/30
Tuesday – 9/27                        6 am – 8am Computing Center
Wednesday – 9/28                  6 am – 8am Fenton
Thursday – 9/29                      6 am – 8am Columbia Hall / Volcanology
 

Week of 10/3 – 10/7
Wednesday – 10/5                  6 am – 8am 1600 Millrace

Details: Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions: If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By: UO Safety & Risk Services

Contact: Zach Earl, UO Fire Systems Program Manager, 541-521-0351 or 541-346-9295.

6/14/22 Straub Hall Fire Systems Testing/Maintenance

Begin: Tuesday, June 14th, 2022 at 6:00 am

End:  Tuesday, June 14th, 2022 at 8:00 am

Building: Straub Hall

Scope: Fire systems testing and maintenance will be performed.

Details: Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions: If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By: UO Safety & Risk Services

5/14/22 & 5/21/22 Huestis Hall, Lokey Labs, and Willamette Hall Domestic Water Shutdown – Update

UPDATE:
The fire water line shutdown will still occur 5/14 as scheduled, however the domestic water shutdown has been rescheduled for next Saturday, May 21, due to delays in materials.  Willamette Hall will also be affected by the domestic water shutdown on Saturday, May 21st.

 

 

Fire Water Line:  Saturday, May 14th, 2022 from 7:00 am till 3:00 pm

Domestic Water Line:   Saturday, May 21st, 2022 from 7:00 am till 3:00 pm

Building(s) or Area(s) Impacted:  Huestis Hall and Lokey Labs (and Willamette Hall 5/21)

Scope:  As part of the Huestis Hall Renovation project, the main domestic water line and fire water line will be shut down on Saturday for 8 hours.

Services Impacted:  All services that need water will be unavailable during this time. This could include lab equipment, HVAC building equipment, fire sprinkler systems, and restroom plumbing services.

Details:  Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions:  If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations.

Work Performed By:  Mortenson Construction

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Building 130 Fire Sprinkler Install 4/25

Begin:  Monday, April 25, 2022 at 7:30 AM

End:      Monday, April 25, 2022 at 12:00 PM

Building(s) or Area(s) Impacted:  Building 130 second floor hallway

Scope: Two sprinkler heads need to be installed on second floor of building 130 in D&C offices. The building’s fire system will be shut down during this time.

Services Impacted: The fire alarm and sprinkler system will be shut down during this time.

Details:  Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. The contractor will monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions:  If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By: Preferred Construction/Omlid & Sweeney

Contact: Bruce Budzik, CPFM Small Projects & Cap Imp Manager, 541-346-8834

Huestis Hall Basement Fire Sprinkler System Shutdown 4/18/22

Begin:  Monday, April 18, 2022 at 7:00 am

End: Monday, April 18, 2022 at 12:00 pm

Building:  Huestis Hall

Scope:  As part of the renovation project, the fire sprinkler system will be shut down only in the basement to allow final installation of sprinkler heads.  Fire watch will be in place during this shutdown.

Services Impacted:  This will only affect the sprinkler system in the basement.

Details:  Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions:  If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By:  Mortenson Construction

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

 

Onyx Bridge, LISB, and Streisinger Fire Systems Testing 4/15/22

Begin:  Friday, April 15th, 2022 at 5:00 am

End:     Friday, April 15th, 2022 at 7:00 am

Building(s) or Area(s) Impacted:  Onyx Bridge, LISB, and Streisinger

Scope: Fire systems testing will be performed.

Details: Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions: If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By: UO Safety & Risk Services

Contact: Zach Earl, UO Fire Systems Program Manager, 541-521-0351 or 541-346-9295.

Esslinger Hall & NW Corner of SRC Electrical Shutdown 4/30/22

UPDATE 4/18: The first hour (from 6am to 7am), ALL of Esslinger, and the NW corner of the Student REC Center of will be without power. After 7am, the noted spaces for Esslinger will continue to be offline until 4pm.

Begin:  Saturday, April 23rd 30th, 2022 at 6:00 am

End:      Saturday, April 23rd 30th, 2022 at 4:00 pm

Building(s) or Area(s) Impacted:  Esslinger Hall & NW Corner of SRC

Scope:  Electrical Panel C1 and C2 will be shut down to replace them with new panels. The first hour (from 6am to 7am), ALL of Esslinger, and the NW corner of the Student REC Center of will be without power. After 7am, the noted spaces for Esslinger will continue to be offline until 4pm.

Services Impacted:  Power will be off on Saturday to the NW corner of the SRC and all of Esslinger.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.

Work Performed By:  Mortenson Construction / EC Electric

ContactTim Allenbaugh, CPFM Owner’s Representative, 541-346-8214

Zebrafish International Resource Center Electrical Shutdown 4-07-22

Begin:  Thursday, April 07, 2022 at 5:40 am

End:   Thursday, April 07, 2022 at 6:35 am

Building(s) or Area(s) Impacted: Zebrafish International Resource Center

Scope:  Power will be shut down while circuit breakers are installed in the main distribution panel.

Services Impacted:  HVAC / Air Supply, Fume Hoods, Fire Alarm system and Electrical

Special Instructions:  Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.

Work Performed By: Fortis Construction

Contact: Colin Brennan, CPFM Owner’s Representative, 541-346-8242 or 541-654-2972

Campus Fire Systems Testing/Maintenance Schedule for Spring Break 2022

Begin:  Wednesday, March 23rd, 2022

End:     Friday, March 25th, 2022

Scope: Fire systems testing and maintenance will be performed.

Buildings and Schedules:

  • Wednesday, March 23  6:00 am – 8:00 am   University Health Services
  • Thursday, March 24      6:00 am – 8:00 am   Tykeson
  • Friday, March 25            6:00 am – 8:00 am   Knight Campus

Details: Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions: If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By: UO Safety & Risk Services

Contact: Zach Earl, UO Fire Systems Program Manager, 541-521-0351 or 541-346-9295.

CPFM Warehouse/shops Fire Sprinkler Replacement Project 3/21/22

Begin:  Monday, March 21,  2022 at 7:30 am

End:    Monday, March 21, 2022 at 12:00 pm

Building(s) or Area(s) Impacted:  CPFM Warehouse (Building 130)

Scope: The sprinkler system will be shut down to add a new sprinkler head.  The contractor will provide fire watch during this time.

Details:  Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions:  If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By:  Harvey & Price and Preferred Construction

ContactBruce Budzik, CPFM Small Projects & Cap Imp Manager, 541-346-8834

 

Streisinger Hall 2nd Floor Fire Alarm System Testing 2/23/22

Begin:  Wednesday, February 23rd, 2022 at 7:30 am

End:      Wednesday, February 23rd, 2022 at 3:00 pm

Building(s) or Area(s) Impacted:  Streisinger Hall 2nd Floor

Scope:  Fire alarm system testing will be performed.

Details:  Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions:  If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By:  Mortenson Construction / Harvey & Price

ContactColin Brennan, CPFM Owner’s Representative, 541-346-8242 or 541-654-2972

Onyx Bridge 4th Floor Fire Alarm System Testing 2/25/22

Begin:  Friday, February 25th, 2022 at 7:30 am

End:      Friday, February 25th, 2022 at 4:00 pm

Building(s) or Area(s) Impacted:  Onyx Bridge 4th Floor

Scope:  Fire alarm system testing will be performed.

Details:  Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions:  If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By:  Mortenson Construction / Harvey & Price

ContactColin Brennan, CPFM Owner’s Representative, 541-346-8242 or 541-654-2972

Esslinger Hall Electrical Shutdown 2/26/22

Begin:  Saturday, February 26th, 2022 at 7:00 am

End:      Saturday, February 26th, 2022 at 1:00 pm

Building(s) or Area(s) Impacted:  Esslinger Hall – First Floor and Possibly Basement Level

Scope:  Contractors will shut down power to Panels C1 and C2 to terminate 8 circuits and re-feed additional circuits for rooms 112 and 116.

Services Impacted:  Power will be offline on the first floor and possibly affect some circuits in the basement level.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.

Work Performed By:  Mortenson Construction/ EC Power

ContactTim Allenbaugh, CPFM Owner’s Representative, 541-346-8214

1600 Millrace Fire Systems Test/Maintenance Advisory 2/9/22

Begin:  Wednesday, February 9th, 2022 at 6:30 am

End:      Wednesday, February 9th, 2022 at 7:00 am

Building(s) or Area(s) Impacted:  1600 Millrace

Scope:  A fire systems test/maintenance will be performed.

Details:  Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions:  If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By:  UO Safety & Risk Services

ContactSimon Ditton, UO SRS University Fire Marshal, 541-346-2958

Huestis Hall Basement Fire Sprinkler System Shutdown 2-21-22

Begin: Monday, February 21, 2022 at 7:30 am

End:   Monday, February 21, 2022 at 5:00 pm

Building(s) or Area(s) Impacted:  Huestis Hall

Scope:   Sprinklers lines will be rerouted in the construction zone.

Services Impacted:   Fire Sprinkler system will be shut down basement wide.

Details:  Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions:  If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By:  Mortenson Construction/ Harvey & Price

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880