Onyx East Elevator Closure 12/24 – 12/26 & 12/31 – 1/2

Building Occupants,

To ensure building security over the holiday, the Onyx east elevator will be closed on the following dates/times:

 

  • 12/24 11:00 AM through 12/26 7:00 AM
  • 12/31 at 5:00 PM through 1/2  7:00 AM

The Onyx west elevator and the Willamette Hall elevators are not impacted by this closure.

Thank you for your patience and understanding.

MAP OF ALTERNATE ROUTES

Baker Freight Elevator Shutdown 11/8/19

Update 11/18: All repairs have been completed and the elevator is now operational.

 

Update 11/15: The parts have been installed and new relays are on order. The Otis technician is trouble shooting the water issue and plans to have all repairs completed by November 22nd.

 

The freight elevator is currently being worked on, and parts are expected sometime in the middle of next week.   The other elevator requires a key to operate it.  Please contact the building manager if you need access.

For questions or concerns, please contact Work Control Center at 346-2319 or workcontrolcenter@uoregon.edu.

 

Hendricks Hall Electrical Shutdown 11/5/19

On Tuesday, November 5th, from 6:00 am to 7:00 am, the electrical system will be shut down, affecting most of the building, including the elevator.  This will allow time for technicians to install parts in an electrical panel.

Building occupants need to shut down their computers the night before.

For questions or concerns, please contact Rob Berg at 346-2313 or rberg@uoregon.edu.

 

 

 

Onyx Bridge East Elevator Shutdown 10/22/19

Update 10/23:

The Otis technician received the parts and repaired the elevator. It is now operational.

 

The East elevator has malfunctioned. The Otis technician determined they need to order parts in order to make repairs. While repairs are being made, please use the Onyx West elevator or the elevator in Pacific Hall. We will send out an update as soon as we have a better idea of when the East elevator will be operational again.

For questions or concerns please contact CPFM Work Control Center 541-346-2319.

Oregon Hall Freight Elevator Hallway and Loading Dock Entrance Shutdown 10/7/19-12/31/19

4th Update: Postponement

Construction activities for the elevator project will be complete by December 31st and the entrance/exit from the loading dock, through lobby L140, will reopen then.

3rd Update: Postponement

Due to unforeseen site conditions, the entrance/exit from the loading dock will remain closed for more drilling to occur.

 

2nd Update:  Noise Advisory for Monday, October 7th

The elevator contractor will be cutting concrete and using a jack hammer to remove the item that needs to be replaced. This activity will take the whole day for the purposes of the notice, however, we anticipate it may be closer to 4 hours.

 

1st Update:  Postponement

This work has been postponed until Monday 10/7 through 10/15 11/4

 

On Monday, September 30th October 7th at 7:00 am until Monday, October 8th October 15th November 4th Mid December 31st, the entrance/exit from the loading dock, through lobby L140, will be closed.  This will allow for drilling activities associated with the jack replacement for the freight elevator modernization.  Please use entrances located along 13th Ave on the South side of the building.  We apologize for any inconvenience.

Work will be performed by Preferred Construction.

For questions or concerns, please contact Bruce Budzik at (541) 346-8834, (541) 915-5663 or bbbudzik@uoregon.edu.

 

 

Oregon Hall Freight Elevator Noise Advisory 9/12/19

On Thursday, September 12th, from 7:00 am to approximately 2:00 pm, there will be noise associated with the removal of the shaft on the freight elevator in the NE section of the building.

Work will be performed by Preferred Construction and OTIS Elevator.

For questions or concerns, please contact Tom Shepard at 541-346-6959 or toms@uoregon.edu.

TODAY: Oregon Hall Elevators 1 and 2 Annual Testing 8/28

2ND REVISION:

This morning, August 28, elevator technicians are conducting annual testing on the two Oregon Hall elevators. One elevator will always be available for building users, as the units will be shut down in intervals for assessment.

Please direct any questions to Otis Elevator technician Marc Maxey.

 

REVISED 8/26/19:

The crew doing annual elevator testing has been held up on another job and will not be evaluating the Oregon Hall elevators this morning. The crew will be on campus throughout this week, however, and will test the elevators another day.

Building occupants will always have one elevator available, since the elevators will be shut down for testing one at a time at different intervals.

 

 

Please share with building occupants

Facilities Liaisons,

On Monday, August 26, between 8 a.m. and 12 p.m., elevators #1 and #2 will be shut down at different intervals while an Otis Elevator technician performs annual, scheduled testing.

Please direct any questions to Otis Elevator technician Marc Maxey.

Oregon Hall Service Elevator Shutdown 8/5/19 – 1/17/20

Update 1/7/2020:

The State inspection has been rescheduled and the elevator should be up and running on Friday, January 17th.

 

Update 12/12/19:

We are waiting for the State to inspect the elevator so this project has been extended until January 7th. Construction activities for the elevator project will be complete by December 31st. Before we can turn it over for use the state elevator inspector has to sign off and the soonest we can get that inspection is January 7th.

 

Update 11/4/19:

Due to unforeseen site conditions, more drilling needs to occur, which will cause the project to be extended. It is now expected to be completed by mid-December.

 

Update 10/31/19:

This project has been extended and is now expected to be complete by November 29th.

 

Update 9/30/19:

This project has been extended and is now expected to be complete by November 1st.

 

Update 9/6/19:

This project has been extended due to the manufacturer’s delay in material procurement and is expected to be completed on October 4th.

Begin: Beginning August 5th, at 11:30 am

End: September 6th, at 4:00 pm October 4th November 1st 29th mid-December January 7th January 17th

Building(s) or Area(s) Impacted:  Oregon Hall Freight Elevator, this elevator will not be available for use.

Scope: Otis Elevator will be refurbishing the service elevator on the north side of the building. Intermittent construction noise related to drilling, hammering, and roto-hammering fasteners into the concrete ceiling of the shaft are to be expected. When that is complete, the elevator jack will be replaced.  At that time, another notice will be sent out describing the noise impacts associated with this second phase of work.

Extra Notes:  Work is being performed by Preferred Construction and Otis Elevator Company.

Contact: For questions or concerns, please contact Bruce Budzik at 346-8834 or bbbudzik@uoregon.edu.

Onyx Bridge and Cascade Annex East Brief Power Loss 7/23/19

On Tuesday, July 23, locations in Onyx Bridge and Cascade Annex East experienced a brief loss of power. University electricians actively addressed the situation, and all power is now restored; in addition, the elevator technician has re-set the Onyx Bridge East elevator, which is now functioning normally.

Please direct questions or concerns to CPFM Work Control Support Services at 541-346-2319 or workcontrolcenter@uoregon.edu

 

Clinical Services Elevator Out of Order 6/13/19

6/14/19 UPDATE:

The elevator has been repaired and is operational.

 

UPDATE:

The elevator will be down for the night.  Our OTIS technician will troubleshoot with his tech support tomorrow.  It is unknown at this time as to when it will be back up and running.  We will keep you posted.

 

 

The elevator is temporarily out of service while it is being worked on by an OTIS technician.

No ETA is currently available, but we will update you as we receive further information.

Thank you for your patience during this time.

Oregon Hall Elevator #2 Temporarily Out of Service 6/13/19

6/14/19 UPDATE:

The elevator has been repaired and is operational.

 

UPDATE:

Elevator #2 is down for the night, but our technician hopes to have it operational tomorrow morning.  We will update you when it has been placed back in service.

 

Elevator #2 is temporarily out of service while it is being worked on by an OTIS technician.

No ETA is currently available, but we will update you as we receive further information.

The other two elevators are operational.

Thank you for your patience during this time.

 

Onyx Bridge West Elevator Shutdown 7/1 – 9/30

Update 9/30: This project is complete and the elevator is back in service.

 

Update 9/17:

This project has been extended and is expected to be completed on September 30th.

 

As part of the elevator modernization project,  Onyx West Elevator off the loading dock will be shut down from July 1st through September 15th 30th.  There will be increased contractor activity and noise associated with this work. During this time frame, please use the east elevator for access.

For questions or concerns please contact CPFM Design and Construction Project Manager Bruce Budzik at 346-8834.

Oregon Hall Service Elevator Shutdown 6/18 – 9/20

Facilities Liaisons,

As part of the elevator upgrade project, the service elevator off the loading dock will be shut down from June 18th through September 20th.  There will be increased contractor activity in the building including noise.

For questions or concerns please contact CPFM Design and Construction Project Manager Bruce Budzik at 346-8834.