EWEB Agate Street Water Main Replacement Starts 10/8

Campus Community,

Our utility provider EWEB requested we share information about an upcoming water main replacement along Agate Street. The water main is located in the west southbound parking strip. This will require city parking spots along the work zone to be vacated for the duration of the project. Pedestrian sidewalks and crosswalks will be impacted in this area and signage, and detours will be in place. City crews will be working each day from 7:00 am – 5:00 pm.

For questions or concerns please contact EWEB Chris Irvin, P.E. Senior Engineer, Water Engineering at 541-685-7619 christopher.irvin@eweb.org

University of Oregon Contact CPFM Design and Construction Sarah Follett 541-346-8264

This work is expected to start the week of October 8. The main construction will take 3-4 weeks with final disinfection and tie-ins following for a total project duration of approximately six weeks.

2018 Fall Street Faire Road Closure 13th Ave 10/10 – 10/12

Campus Community,

On October 10 – 12, 2018 the ASUO Fall Street Faire will have 13th Ave closed from University Street to Kincaid Street. Activity will begin in this area on October 9. Bike racks will be removed, and parking will be closed along 13th Ave to accommodate vendors.

For questions or concerns please contact event organizer Kylie MacDonald at 541-346-0622 or 541-346-7865

http://uoregon.orgsync.com/org/associatedstudentsofuo/programs_street_faire

Update! ESPN GameDay 2018 Closures and Detours 9/19 – 9/22

This update has been sent to building occupants in PLC and Condon.

Building Occupants,

Due to ESPN GameDay 2018 entry into the PLC north entrance and the Condon South Entrance entry is restricted.  Please use another exit if possible (emergency egress will be allowed).

For questions or concerns please contact CPFM Work Control Center at 541-346-2319.

 

https://blogs.uoregon.edu/cpfmnotifications/2018/09/18/espn-game-day-2018-closures-and-detours-919-922/

Sent: Tuesday, September 18, 2018 4:37 PM
Subject: ESPN GameDay 2018 Closures and Detours along Kincaid 9/19 – 9/22

Campus Community,

Starting Wednesday, September 19 at 5:30 am through Saturday, September 22 at 5:30 pm Kincaid Street from 13th ave to 15th ave will experience a northbound lane closure, east side parking closures, and bike rack removals to accommodate ESPN GameDay equipment along Kincaid Street.  There will also be fencing staged in the Quad outside of Condon Hall, Prince Lucien Campbell, Jordan Schnitzer Museum of Art, Knight Library, and Chapman Hall.  Please expect increased activity and congestion in this area.

Impacts:

Northbound lane closure on Kincaid from 13th Ave to 14th Ave
East Side parking on Kincaid from 13th Ave to 15th Ave
Several Bike Rack removals along Kincaid
Fencing Staged in Condon Hall, Prince Lucien Campbell, Jordan Schnitzer Museum of Art, Knight Library, and Chapman Hall Quad

Contact:  CPFM Work Control Center

For questions or concerns please contact CPFM Work Control Center at 541-346-2319.

Riverfront Parkway Lane Closure 8/23

Campus Community,

Our Utility Provider EWEB will be pruning trees along Riverfront Pkwy on August 23, 2018, from 9:30 am – 3:00 pm.  The northbound lane of Riverfront Parkway will be closed during this time.  Signage will be in place to direct pedestrian and vehicular traffic.

Select this (link) to view traffic plan.

For questions or concerns, please contact:

UO  Transit and Parking Field Operations Manager James McGladrey at 541-346-2676.

EWEB contact Chris Hoffman Utility Forester EWEB Vegetation Management Program 541-685-7608.

 

Bean Hall Project Road Closures July 19, 2018

Campus Community,

There are two street closures for the Bean Hall Project on July 19th.

The first is a closure of 15th street between Bean and Global Scholars Hall from 6 AM to 8 AM. We will shut down the street with flaggers to detour traffic, set up the crane and lift the rooftop units.

The second closure will be Columbia Street between Hamilton Hall and the Alumni Center. We will be closing the parking spots in lot 37 as part of the closure. This closure will be from 6 AM – 3 PM. Access to the Columbia Garage will not be affected.

For questions or concerns please contact CPFM Design and Construction Project Manager George Bleekman 541-346-2625.

6/16 – 9/15: Hayward Utility Corridor Project Impacts

Campus Community,

From June 19, 2018 – September 15, 2018 all traffic access on the service road between LLC and Walton will be closed as part of the Hayward Utility Corridor project. For the remaining occupants in Walton wing Adams sewer reroute work will impact the buildings at times and will be communicated with Housing Staff directly.  Utilities have mostly been rerouted in advance to limit impacts during the overall construction dates.  Some additional electrical outages will happen during the summer months but will be coordinated in advance and communicated to Housing and Utilities and Energy.

For questions for concerns related to this summer utility project please contact CPFM Design and Construction Jana Gerow at 541-346-8317 or 970-640-0176.

3/26 – 3/28: [15th AVE Between Agate Street West to Onyx] EWEB Roadway Patching

This notice was sent to Housing, SRC, Straub, UOPD, FS Memo and Parking Services

Campus Community,

On Monday, March 26 through March 28, 2018 our Utility Provider EWEB will be patching the road along 15th and the street will be closed from Agate Street west to Onyx.  Access from the west off of University will allow access to SRC, Straub and 15th west of Onyx.  EWEB will provide traffic control.

For questions or concerns please contact CPFM Design and Construction Owners Representative Jana Gerow at 541-346-8317.

 

 

3/14: [15th AVE Between Walton & Hayward Field] EWEB Roadway Patching

This notice was sent to Housing, UOPD, FS Memo and Parking Services

Campus Community,

Our Utility Provider EWEB will be patching the road along 15th Ave between Walton and Hayward Field tomorrow morning, March 14, 2018 from 4:00 am – 5:00 am.  EWEB will provide traffic control.

For questions or concerns please contact CPFM Design and Construction Owners Representative Jana Gerow at 541-346-8317.

 

 

Date Change due to Weather: [SRC, STRAUB, LLC] Sidewalk Closure and Noise 3/1 – 3/2

Due to inclement weather this work has been rescheduled for March 1 – 2, 2018

________________________________________________________________

This notice has been sent to all building users:  SRC, Straub, LLC, Earl, Bowerman and Housing.

Campus Community,

This notice has been extended through February 23, 2018 ending at 12:00 (noon).  The sidewalk will remain closed for the duration of the work.  Please expect noise from the stump grinder between 9:00 am  – 12:00 pm (noon) on the 23rd.   Work will be performed by Long Tom Sawmill.

For questions or concerns please contact CPFM Facilities Services Arborist Becket DeChant at 505-699-7007.

________________________________________________________________________________________________________

 

Campus Users,

On Thursday, February 22nd, from 8:00 am until 2:30 pm, the south side of Straub, SRC, and LLC may be impacted by noise related to the removal of a Norway Maple tree.  Sidewalk access to the Student Rec Center from the east sidewalk on the south side of E. 15th will be closed, and East 15th Avenue will have periodic restrictions by trucks loading debris.

Old injuries to the trunk coupled with irreversible root rot fungus has resulted in the large cavity at the base of this tree. This development, when considered with the weight of the canopy above and the high traffic nature of the site necessitates its removal for pedestrian safety. The site will be re-planted in consultation with campus designers.

Work will be performed by Campus Planning and Facilities Management crews.

For questions or concerns about how this may impact your area, contact Phil Carroll, Campus Planning and Facilities Management (CPFM) Grounds Maintenance Manager at pcarroll@uoregon.edu.

2/12 – 12/15: Lane & Parking Closure 15th Ave

Campus Community,

Starting February 12  through February 15, 2018,15th Ave between Bean Hall and Global Scholars Hall/Museum of Natural and Cultural History will be limited to one lane of traffic to allow for steel deliveries for the Bean Hall Project. The sidewalk and parking spaces on the north side of the street in front of Bean Hall will be closed, along with the north lane of traffic, and traffic will be restricted to the south lane during the deliveries during this time. Flaggers will coordinate the two way traffic in the south lane. Please be aware of the limited access during this time. Pedestrian traffic on the south 15th Ave. sidewalk will not be impeded.

For questions or concerns please contact CPFM Design and Construction Owners Representative George Bleekman at 541-346-2625.

 

12/11 – 1/5: 13th Ave Lane Closure Related to Tykeson Hall Connections

Campus Community,

Due to storm and sewer line connections for the Tykeson Hall project, December 11, 2017 – January 5, 2018, 13th Ave between Chapman and Fenton will be down to one-way access as Fortis Construction will move construction fencing from south to north during the winter break to accommodate the piping project along 13th Ave.

For questions or concerns please contact CPFM Design and Construction Owners Representative Martina Oxoby at 541-346-5880.

 

UPDATE: 12/10 – 1/2: Closure: 15th Ave Between Agate and University Street and Bowerman Parking Lot 31

Building Occupants,

 

Due to the EWEB waterline replacement project on 15th avenue, the water will be shut off to both LLC and Bowerman from 9 a.m. to 5 p.m. on Thursday, 12/21/17 to connect the building water for these two buildings to the new water main in 15th.  Domestic water from the fire line will be shut off in Bowerman ONLY, thus UO Fire Protection will provide fire watch or monitors.

 

Please reference the below updates from Jana Gerow CPFM Design and Construction Owners Representative 541-346-8317.

 

_____________________________________________________________________________________________________________

 

Campus Community,

EWEB will be replacing the main water line under 15 Ave between Agate Ave and University Street from Agate to just east of the Recreation Center starting December 11, 2017, Sunday, December 10, 2017, thru January 2, 2018.  The roadway will be closed during this time to traffic as well as the Bowerman Parking Lot #31. Work will be done from 8:00 am -5:00 pm weekdays, however, the roadway and lot will remain closed during off hours.

 

There will be an additional notice sent regarding a water shutdown for one day (likely between December 25 & Dec 31, 2017 ) that will impact LLC and Walton Bowerman.  EWEB will be providing the standard 48-hour notice and information about the water shutdown will be communicated as it is received.  NOTE: Water will NOT be shut off to Walton during this project.

 

For questions, please contact Jana Gerow CPFM Design and Construction Owners Representative 541-346-8317.

10/16 – 10/20: Emerald Path Closure Related to Stadium Construction Activities

Campus Community,

The “Emerald Path,” the north-south path that runs east of Jane Sanders Stadium, will be closed for construction activities October 16, 2017 – October 20, 2017, related to the addition of permanent bleachers. The extent of the closure is shown on the below site plan.

For questions or concerns related to this outage, please contact CPFM Design and Construction Owners Representative Charlene Lindsay 541-346-5503.

Closure: 18th Street Traffic Control Plan 10/3 – 10/6

Campus Community,

As part of the Jane Sanders Expansion Project, 18th Street and Sidewalk between Agate and Hilyard will experience closures October 3 – 6, 2017.  Detour signage and barricades will be in place to identify closures and detours. Please review the below traffic control plan.

For questions or concerns, please contact CPFM Design and Construction Owners Representative Charlene Lindsay at 541-346- 5503.

9/18 – 9/21: Street and Sidewalk Closure between HEDCO and Education Building

Campus Community,

Due to the installation of a ADA ramp starting September 18, 2017, through September 21, 2017 the sidewalk and street between HEDCO and the Education Building will be temporarily closed. Contractors will have signage in place to direct traffic.

For questions or concerns related to this project, please contact CPFM Design and Construction Project Manager Glen Macdonald at 541-346-2281.

8/11/17: Core Drilling on South Side of East 15th between Villard and Villard Alley

Campus Users,

On Friday, August 11th from 9:00 am to 3:00 pm, GRI plans to do some core drilling in three locations on the south side of 15th between Villard and Villard Alley, the future home of the Black Cultural Center.

Equipment will be at each bore location for 2 hours.

Work will be performed by GRI.

For questions or concerns about how this may impact your area, contact Martina Oxoby, Campus Planning and Facilities Management (CPFM) Campus Planning at 346-5880.

Postponed New Date: 13th Street Closure by Carson Hall 8/19/17

Campus Community,

On August 15, 2017, August 19, 2017 a section of 13th street will be closed from 6:30 am – 1:00 pm to accommodate crane staging associated with the roof mount chiller replacement at Carson Hall.

For questions or concerns, please contact Director of Housing Facilities Services Greg Ottoman at 541-346-6794 or Housing Facilities Manager Judd Mentzer at 541-346-5594.  This is a UHDS project.

5/17/17-5/19/17: Berwick Hall Parking Lot #20 Access Lane Closure

Campus Community,

On Wednesday, May 17th at 7:00 am until Friday, May 19th at 6:00 pm, access to Parking Lot #20 will be closed due to upcoming work on the Berwick Project.  Traffic will be limited to emergency vehicles only.

This will affect School of Music and Dance, Pioneer Cemetery and access through the fire lane off of 18th Ave.

For questions or concerns about how this may impact your area, contact Martina Oxoby, Campus Planning and Facilities Management (CPFM) Campus Planning at 346-5880.

 

5/27/17: Columbia Street and Parking Lot 34C Shutdown for Boulder Placement

Campus Community,

On Saturday, May 27th, from 7:30 am until 4:30 pm, Columbia Street and Parking Lot 34C, from 17th Avenue northward, will be shut down. This will allow the staging of a crane to place large boulders at the New Residence Hall.

The sidewalk on the west side of Columbia Street will remain open but access to Parking Lot 34C (Columbia Street) will be closed, as well as vehicular traffic to the Vivian Olum Child Development Center and the Many Nations Longhouse.

The work will be performed by Walsh Construction.

For questions or concerns about how this may affect your area, contact George Bleekman, Campus Planning and Facilities Management (CPFM) Design and Construction at 346-2625.

 

03/28/2017: Cellular equipment removal from the roof of PLC, Kincaid Street Closure at 14th

Campus Community,

As part of the cellular equipment removal from the roof of Prince Lucien Campbell (PLC), Kincaid Street will be closed to parking between the 14th Alley and 14th Street.  Kincaid Street will only have one-way traffic control between the 14th Alley and 14th Street.  The Sidewalk on the eastside of Kincaid Street will also be closed.  This work is associated with the cellular provider T-Mobile.  The City has approved appropriate permits for this temporary closure.

This work is taking place Tuesday, March 28, 2017, from 6:00 am – 5:00 pm.

For questions regarding this notice, please contact Kirk Johnson at 541-346-9605.

03/11/2017: Notice of Womens Quad Tree Work and Johnson Lane Closure

Campus Community,

On Saturday, March 11, 2017, Sperry Tree Care will be on site performing tree work from 7:30 am – 4:00 pm.  The remaining log in the Women’s Quad will be removed via a crane requiring a closure of all walkways leading to the Women’s’ Quad as well as periodic interference with traffic on Johnson Lane. Due to the nature of the work noise is expected.  Sidewalks and Lane closures will be marked for the safety of the campus community.  Saturday was selected to limit the impact to the campus community.  Below is a map of the impacted area.

If you have any questions, please contact Phil Carroll at 541-346-1823