6/28/22 Lokey Education Fire Sprinkler Install

Begin:  June 28th, 2022 at 7:00 am

End:      June 28th, 2022 at 4:00 pm

Building Affected:  Lokey Education

Scope:  Due to installation of new fire sprinkler heads for the Lokey Education elevator modernization project the associated fire sprinkler system will be temporarily shut down between the hours of 7:00 am and 4:00 pm.

Services Impacted:  The fire alarm and sprinkler system will be shut down during this time.

Details:  Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. The contractor will monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions: If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By: Ryan Thomas Construction

Contact: Damon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285