[1715 FRANKLIN] LANDSCAPE WORK 7/10 – 7/27 IN PREPARATION OF SUMMER PAINTING 8/1 – 8/31

Landscape Activities

Beginning July 10th, 2018 through July 27th, 2018 there will be trimming of shrubs and trees along the exterior of the building, including the bike cage and dumpster areas. There may be additional noise when work is in progress.

Painting & Power Washing Activities

The owners have contracted with Gary Pierce Painting to have the entire exterior of the building power washed and painted. Work is anticipated to begin on August 1, 2018, and be completed on or near August 31, 2018. Starting August 1st, Gary Pierce Painting will power wash the entire exterior building. Power washing will be completed in sections. After the power washing is completed, the painting will begin and also completed in sections. A lift will be on-site and used to complete this project.

Please note the following:

-There will be additional noise
-There may be odors
-Parking will be affected. Sections of parking in the row closest to the building will be blocked off  throughout the duration of this project.

Please use caution as you enter and exit the building. Also, please watch for equipment and folks that are working on this project.

Please report any water leaks from power washing immediately.


For questions or concerns please contact CPFM Real Estate Property Coordinator and Lease Management Melinda Seeley at 541-346-5550.

6/16 – 9/15: Hayward Utility Corridor Project Impacts

Campus Community,

From June 19, 2018 – September 15, 2018 all traffic access on the service road between LLC and Walton will be closed as part of the Hayward Utility Corridor project. For the remaining occupants in Walton wing Adams sewer reroute work will impact the buildings at times and will be communicated with Housing Staff directly.  Utilities have mostly been rerouted in advance to limit impacts during the overall construction dates.  Some additional electrical outages will happen during the summer months but will be coordinated in advance and communicated to Housing and Utilities and Energy.

For questions for concerns related to this summer utility project please contact CPFM Design and Construction Jana Gerow at 541-346-8317 or 970-640-0176.

Phil and Penny Knight Campus for Accelerating Scientific Impact Construction and Traffic Updates

Construction on the Phil and Penny Knight Campus for Accelerating Scientific Impact is ramping up. You can track progress on a web cam and read traffic updates.

Construction and Traffic Updates: https://accelerate.uoregon.edu/construction-and-traffic-updates

Webcam: https://accelerate.uoregon.edu/construction-webcam

https://accelerate.uoregon.edu/sites/accelerate1.uoregon.edu/files/diagram_a_-_ped_and_bike_0.pdf

https://accelerate.uoregon.edu/sites/accelerate1.uoregon.edu/files/diagram_b_-_pepi_work.pdf

6/1/18-6/4/18: PeaceHealth Sidewalk Replacement

PeaceHealth will be replacing the sidewalk along Hilyard as it crosses the Alley entrance to the CMER building.  The work will begin on Friday, June 1st and should be completed by Monday, June 4th.

The East end of the alley and the CMER Access off of E 11th will remain open.

 

4/20: Construction Of Covered Walkway Closing West Sidewalk Outside Johnson Hall

Campus Community

As part of Tykeson Hall construction project, the Fortis Construction team will be installing a covered walkway on the west side of Johnson Hall from, 13th Ave to Johnson Hall’s ADA west entry. This covered walkway will be lit and maintain ADA access from 13th AVE. It will be in place until spring 2019. The construction fence will be moved so that pedestrian access from the south from Johnson Lane will be rerouted to the east side of Johnson Hall.

IMPORTANT: The west sidewalk will be closed the afternoon of Friday, April 20 from 12:00PM-5:00PM while the covered walkway is installed. There will be NO ADA access to the building during the time of installation.

See area 1 in blue highlight on the attached site logistics plan.

If you have any questions or concerns, please contact Owner’s Representative Martina Oxoby with CPFM Design & Construction at (541) 346-5880.

 

              

 

4/16-4/20: Site Preparations For Art Installation At EMU Green

Campus Community,

Beginning Monday, April 16 and continuing through Friday, April 20, a landscaping company will have equipment on site to make preparations for an art installation at the EMU Green. This will include pedestrian controls, safety fencing around the work areas around the Green. There will be landscape vehicles, dump trailers, and excavators on site throughout the work. Bike and pedestrian traffic will be rerouted around work area.

If you have any questions or concerns, please contact Owners Representative, Martina Oxoby, with CPFM’s Design and Construction, at (541) 346-5880.

4/12: Tykeson Hall Concrete Work Impacting Pedestrian Traffic along 13 Ave

Campus Community,

As part of the Tykeson Hall construction project, there will be a concrete truck on 13th Ave on Thursday, April 12 from 12:00 pm-5:00 pm. Vehicle access will not be impeded. However, pedestrian traffic will be rerouted to the north side of 13th Ave.

For questions or concerns please contact CPFM Design and Construction Project Manager Martina Oxoby at 541-346-8477.

4/5: Tykeson Hall Concrete Work Impacting Pedestrian Traffic along 13 Ave

Campus Community,

As part of the Tykeson Hall construction project, there will be a concrete truck on 13th Ave on Thursday, April 5 from 5:00 am-9:00 am. Vehicle access will not be impeded. However, pedestrian traffic will be rerouted to the north side of 13th Ave.

For questions or concerns please contact CPFM Design and Construction Project Manager Martina Oxoby at 541-346-8477.

3/19/18: Lot 4 Emergency Sidewalk Shutdown

Campus Users:

Effective immediately on Monday, March 19th, the sidewalk in front of parking lot #4 will be shut down due to an extreme trip hazard.  This is located on the north side of Franklin Blvd., on the west side of Riverfront Pkwy.  This closure is expected to last part of the day until a temporary fix can be put in place.

For questions or concerns about how this may impact your area, contact Kevin Farthing, Campus Planning and Facilities Management (CPFM) Zone D Maintenance Manager at 346-2857.

3/6 – 3/23: NW Natural Work Zones along Millrace, Fine Arts & ZIRC Impacting Paths of Travel

Campus Community,

As part of the Knight Campus Project, our utility provider NW Natural has requested a series of work zone notifications redirecting pedestrian, bicycle, and vehicular traffic.  Please expect noise and congestion in these work areas.

Zone 1 March 6 – March 9, 2018

Service and emergency vehicle access only.  Service vehicles are encouraged to use alternate routes. Lots 3A and 3B will remain open, but access may be delayed.  Parking in Lot 4 and 56 is encouraged.

Zone 2 March 12 – March 23, 2018

Service and emergency vehicle access only.  Service vehicles are encouraged to use alternate routes.  Lots 3A and 3B will remain open, but access may be delayed.  Parking in Lot 4 and 56 is encouraged.

Looking ahead:

  • Week of March 6 Design and Construction will be coordinating a NW Natural Gas Shutdown with building occupants
  • Late March parts of Millrace Path will be closed to pedestrian and bike traffic.

For questions or concerns regarding how these activities may impact access to your buildings or research, please contact CPFM Design and Construction Project Civil Engineer Sarah Follett at 541-346-8264.

Date Change due to Weather: [SRC, STRAUB, LLC] Sidewalk Closure and Noise 3/1 – 3/2

Due to inclement weather this work has been rescheduled for March 1 – 2, 2018

________________________________________________________________

This notice has been sent to all building users:  SRC, Straub, LLC, Earl, Bowerman and Housing.

Campus Community,

This notice has been extended through February 23, 2018 ending at 12:00 (noon).  The sidewalk will remain closed for the duration of the work.  Please expect noise from the stump grinder between 9:00 am  – 12:00 pm (noon) on the 23rd.   Work will be performed by Long Tom Sawmill.

For questions or concerns please contact CPFM Facilities Services Arborist Becket DeChant at 505-699-7007.

________________________________________________________________________________________________________

 

Campus Users,

On Thursday, February 22nd, from 8:00 am until 2:30 pm, the south side of Straub, SRC, and LLC may be impacted by noise related to the removal of a Norway Maple tree.  Sidewalk access to the Student Rec Center from the east sidewalk on the south side of E. 15th will be closed, and East 15th Avenue will have periodic restrictions by trucks loading debris.

Old injuries to the trunk coupled with irreversible root rot fungus has resulted in the large cavity at the base of this tree. This development, when considered with the weight of the canopy above and the high traffic nature of the site necessitates its removal for pedestrian safety. The site will be re-planted in consultation with campus designers.

Work will be performed by Campus Planning and Facilities Management crews.

For questions or concerns about how this may impact your area, contact Phil Carroll, Campus Planning and Facilities Management (CPFM) Grounds Maintenance Manager at pcarroll@uoregon.edu.

2/5/18-2/7/18: Pedestrian Detour Between Cascade and Pacific

Building Occupants,

Beginning today, Monday, February 5th, at 3:00 pm until Wednesday, February 7th, at 3:00 pm, the walk path between Cascade Hall and Pacific Hall on the south side will be re-routed.  Pedestrians will have to walk past the fountain to get to the breezeway between Pacific and Columbia from Cascade.

This temporary detour is needed while the windows are being resealed on the east side of Pacific Hall.

Work will be performed by a contractor.

For questions or concerns about how this may impact your area, contact Bruce Budzik, Campus Planning and Facilities Management (CPFM) Zone B Maintenance Manager at 346-8834.

12/28/17 – 3/30/18: Sidewalk Closure between LLC and Walton

Building User,

Beginning Friday, December 28, 2017 at 7:00 am, until Friday, March 30th, 2018, at 5:00 pm, saw cutting of sidewalks has begun to allow for entry to the underground tunnel for work on the chilled water piping. Sidewalks will be closed in the Plaza area on the east side of LLC, between LLC and Walton. Fencing has been placed to protect pedestrians during this work.

An outside contractor will remove the old piping in the tunnel and replace it with new, larger chilled water piping.

For questions or concerns about how this may impact your area, contact Jana Gerow, Campus Planning and Facilities Management (CPFM) Design and Construction at 346-8317.

12/11 – 12/22: [13TH Ave & 15TH Ave] Sidewalk Repairs & Replacements

Campus Community,

From December 11 – 22, 2017 Delta Construction will be onsite completing three sidewalk repairs/replacements. There will be noise, congestion and pedestrian closures associated with this work.

 

                                                                            13th Avenue – Ford Alumni to Hamilton Sidewalk Repair

 

Date Scope
12/11 Setup Traffic Control, Saw Cutting, Erosion Control, start removal of sidewalk.
12/12 Continue sidewalk removal and prep for sidewalks.
12/13 Complete removal and prep, start forming for sidewalks (cover subgrade with blankets if temperature requires).
12/14 Complete forming and pour sidewalks.
12/15 Strip forms, backfill with loam, and clean up. Open sidewalks if they are not to green.
12/18 Pick up remaining traffic control, final clean up.

 

                                                                                 13th Avenue – Chapman Hall Sidewalk Replacement

 

Date Scope
12/11 Setup Traffic Control, Erosion Control, and Saw Cutting.
12/13 Setup Traffic Control, Erosion Control, and Saw Cutting.
12/14 Form and pour back curb and sidewalk.
12/15 Strip, back fill, remove traffic control, and clean up.

 

                                                                               15th and Agate – NW Corner Sidewalk Replacement

 

Date Scope
12/18 Setup Traffic Control, Erosion Control, Saw Cutting, start removal of sidewalk.
12/19 Complete sidewalk removal and prep for new sidewalks.
12/20 Form new sidewalks, possible placement of sidewalks.
12/21 Pour sidewalks.
12/22 Strip sidewalks, backfill w/loam, clean up, and remove traffic control.

 For questions or concerns regarding this notification, please contact CPFM Zone D and Exterior Manager Kevin Farthing at 541-346-2857.

 

UPDATE: 12/10 – 1/2: Closure: 15th Ave Between Agate and University Street and Bowerman Parking Lot 31

Building Occupants,

 

Due to the EWEB waterline replacement project on 15th avenue, the water will be shut off to both LLC and Bowerman from 9 a.m. to 5 p.m. on Thursday, 12/21/17 to connect the building water for these two buildings to the new water main in 15th.  Domestic water from the fire line will be shut off in Bowerman ONLY, thus UO Fire Protection will provide fire watch or monitors.

 

Please reference the below updates from Jana Gerow CPFM Design and Construction Owners Representative 541-346-8317.

 

_____________________________________________________________________________________________________________

 

Campus Community,

EWEB will be replacing the main water line under 15 Ave between Agate Ave and University Street from Agate to just east of the Recreation Center starting December 11, 2017, Sunday, December 10, 2017, thru January 2, 2018.  The roadway will be closed during this time to traffic as well as the Bowerman Parking Lot #31. Work will be done from 8:00 am -5:00 pm weekdays, however, the roadway and lot will remain closed during off hours.

 

There will be an additional notice sent regarding a water shutdown for one day (likely between December 25 & Dec 31, 2017 ) that will impact LLC and Walton Bowerman.  EWEB will be providing the standard 48-hour notice and information about the water shutdown will be communicated as it is received.  NOTE: Water will NOT be shut off to Walton during this project.

 

For questions, please contact Jana Gerow CPFM Design and Construction Owners Representative 541-346-8317.

11/19: Tree Work Along Franklin by Villard

Building Occupants,

On Sunday, November 19, 2017, Sperry Tree Care will be onsite by Villard at the E 11th Ave and Franklin Blvd Merger.   Contractors will be performing tree maintenance on the oak tree that overhangs Franklin Blvd.  The equipment will be staged at Franklin Blvd, and there is a possibility the contractor will need to bring equipment down the sidewalk in front of Deady and Villard.    The city has approved this work, and the contractor has coordinated pedestrian and vehicular traffic control.  Please expect intermittent chainsaw noise associated with this work.

Please contact Becket Dechant 505-699-7007 or Phil Carrol with questions or concerns.

 

 

10/16 – 10/20: Emerald Path Closure Related to Stadium Construction Activities

Campus Community,

The “Emerald Path,” the north-south path that runs east of Jane Sanders Stadium, will be closed for construction activities October 16, 2017 – October 20, 2017, related to the addition of permanent bleachers. The extent of the closure is shown on the below site plan.

For questions or concerns related to this outage, please contact CPFM Design and Construction Owners Representative Charlene Lindsay 541-346-5503.

Closure: 18th Street Traffic Control Plan 10/3 – 10/6

Campus Community,

As part of the Jane Sanders Expansion Project, 18th Street and Sidewalk between Agate and Hilyard will experience closures October 3 – 6, 2017.  Detour signage and barricades will be in place to identify closures and detours. Please review the below traffic control plan.

For questions or concerns, please contact CPFM Design and Construction Owners Representative Charlene Lindsay at 541-346- 5503.

9/18 – 9/21: Street and Sidewalk Closure between HEDCO and Education Building

Campus Community,

Due to the installation of a ADA ramp starting September 18, 2017, through September 21, 2017 the sidewalk and street between HEDCO and the Education Building will be temporarily closed. Contractors will have signage in place to direct traffic.

For questions or concerns related to this project, please contact CPFM Design and Construction Project Manager Glen Macdonald at 541-346-2281.

8/11/17: Core Drilling on South Side of East 15th between Villard and Villard Alley

Campus Users,

On Friday, August 11th from 9:00 am to 3:00 pm, GRI plans to do some core drilling in three locations on the south side of 15th between Villard and Villard Alley, the future home of the Black Cultural Center.

Equipment will be at each bore location for 2 hours.

Work will be performed by GRI.

For questions or concerns about how this may impact your area, contact Martina Oxoby, Campus Planning and Facilities Management (CPFM) Campus Planning at 346-5880.

8/23 – 9/22: Sidewalk Closure 15th Ave Related to Bean Construction Activities

Campus Community,

The sidewalk on the north side of 15th Avenue between Agate Street and crosswalk west of Bean will be temporarily closed August 23 – September 22 to allow for demolition activities on the south side of Bean Hall.  Pedestrians will be directed to the south side of 15th Ave.

For questions or concerns please contact George Bleekman CPFM Design and Construction Owners Representative   541-346-2625.

Update Regarding Oregon Hall Renovations

Building Occupants,

We are gearing up for construction activity at Oregon Hall First Floor West (1W).

Phase 1 work is renovating First Floor West (1W) and adding roof top mechanical equipment to replace west wing HVAC equipment (Phase 1 & 2). We are scheduled to begin HVAC modifications on 1W (to cap and isolate 1W from the building) the week of 7/24. This will support abatement and demolition activities to 1W scheduled to begin 7/26. As part of the new HVAC Roof-Top equipment (September Installation) we will be building a new mechanical pump room in 220 (8/7 start) and a new Electrical Room in 342 (8/24 start).

Fortis construction will install fencing around the back parking lot on 8/7 (click on image for attached site plan). A dumpster will be placed in the west truck bay for construction, and we will leave the east truck bay open for deliveries. The construction gate will remain open during regular business hours for deliveries. Window Replacement to 1W will begin 9/6. There will be site fencing used during the window replacement.

I will provide updates on the construction activities as the project progresses.

Please contact me with any questions.

Thank you,

Patrick Mucker
Owner’s Representative
Campus Planning and Facilities Management
University of Oregon
541-346-8216 office
541-517-2497 cell

06/20/17 – 08/17/17: Summer Student Recreation Center Roof Project

Campus Community,

Starting June 20, 2017, the Summer Student Recreation Center roofing project will begin and run through August 17, 2017.  During the duration of this project, there will be various intermittent sidewalk closures and building access detours along 15th Street.  Due to potential weather or other delays, the exact duration for each staging area cannot be determined.  The contractor will be working closely with the project manager and block construction areas with appropriate signage and barricades.  There may also be noise associated with this project.  Zone A and Building Automated Controls will work with the contractor to reduce fan speeds as necessary to mitigate odors associated with this project.

If you have any questions or concerns contact CPFM Owners Representative Charlene Lindsay 541-346-5503.