West End of Millrace Drive Gravel Road Closure (West of Riverfront Parkway) Notice 10/23/20 and 10/26/20

Begin:  Friday, October 23rd, 2020 (daily)

End:      Monday, October 26th, 2020

Building(s) or Area(s) Impacted:  Gravel road next to the greenhouses between Gallery Walk and Riverfront Parkway

Scope:  The gravel road next to the greenhouses between Gallery Walk and Riverfront Parkway will be closed to all pedestrian, bike, and vehicle traffic on Friday, 10/23 and on Monday 10/26 for grading & paving work to tie-in the jug handle turnaround with the intersection of Riverfront Pkwy at the Garage project. The road will be open over the weekend (Saturday & Sunday).

Services Impacted:  Road closure Friday and Monday

Work Performed By:   Hoffman Construction

ContactJenna Shope, CPFM Owner’s Representative, 541-346-2281

Global Scholars Lawn Work Advisory 10/15/20 – 10/20/20

Begin:  Thursday, October 15th, 2020 at 9:00 am

End:      Tuesday, October 20th, 2020 at 5:00 pm

Building(s) or Area(s) Impacted:  Global Scholars Hall Lawn

Scope:  Sections of the lawn will be renovated, and a small area of new concrete sidewalk will be installed.

Services Impacted:  There will be intermittent noise during this period, with large trucks present in the fire lane parts of Saturday and Tuesday.

Work Performed By:   Rexius and CPFM Facilities Services

ContactPhil Carroll, CPFM FS Landscape Maint Supervisor, 541-246-0031

Matthew Knight Arena East Sidewalk and Parking Lane Closure 10/26/20 – 11/6/20

Begin:  Monday, October 26th, 2020

End:      Friday, November 6th, 2020

Building(s) or Area(s) Impacted:  Matthew Knight Arena Sidewalk on East Side

Scope:  The sidewalk and parking lane will be closed to replace the existing sidewalk and trees in the area highlighted in red.

Services Impacted:  Sidewalk and parking lane alongside Matthew Knight Arena

Special Instructions:  Please use the sidewalk on the east side of Villard Street.

Work Performed By:   Fortis Construction

Contact:  Work Control Center, Campus Planning and Facilities Management, 346-2319

Millrace Bike Path/Walkway Closure Notice 10/5/20 – 10/10/20

Begin:  Monday, October 5th, 2020

End:      Saturday, October 10th, 2020

Building(s) or Area(s) Impacted:  Pathway along the north side of the Millrace between Gallery Walk and Riverfront Parkway

Scope:  The Millrace pathway will be closed to all pedestrian and bike traffic for one (1) week. Grade work and paving to tie-in the pathway to the Knight Campus bridges over the Millrace will be taking place during this closure.

Services Impacted:  Gallery Walk will remain open to the north of the pathway, and the detour route will be the gravel road north of the Urban Farm, behind the Fine Arts Studios.

Work Performed By:   Hoffman, OEG, Eugene Sand & Gravel

ContactJenna Shope, CPFM Owner’s Representative, 541-346-2281