3/29/24 – 4/05/24 Riverfront Sports Field Top Dress and Leveling Work Advisory

Begin:  Friday, March 29, 2024

End:      Friday, April 5, 2024

Building(s) or Area(s) Affected:  Riverfront Sports Field

Scope:  Top dress and leveling will take place on the Riverfront Sports Field.  200-tons of turf top-dress material is expected to be delivered 3/29/24 and/or 4/1/24.  Work on the field is scheduled to begin the week of 4/01/24.

Services Impacted:  Work related noise can be expected.  Roadways and sidewalks in the surrounding area will also be impacted.

Work Performed By:  Rexius Landscape

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Riverfront Fields

2/22/24 – 2/23/24 Miller Theatre West Exterior Stair Pressure Washing Advisory

Begin:  Thursday, February 22, 2024

End:      Friday, February 23, 2024

Building(s) or Area(s) Affected:  Miller Theatre

Scope:  The west exterior stairs will be pressure washed.

Services Impacted:  Noise can be expected and access will be limited during this time.

Special Instructions:  Please use an alternate entrance.

Work Performed By:  CPFM Facilities Crew

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Miller Theatre west exterior stairs

11/27/23 – 12/01/23 Millrace 1 and 2, Fine Arts C, and Woodshop Noise Advisory

Dates:  Monday, November 27, 2023, through Friday, December 1, 2023

Daily Hours:  7:00 pm until 7:00 am

Building(s) or Area(s) Affected:  Millrace 1, Millrace 2, Fine Arts C, and Woodshop. See attached map.

Scope:  Hoffman will be excavating for a new utility tunnel between the Fine Arts C and Woodshop buildings. This work will occur at night between 7:00 pm and 7:00 am in order not to impact classes in adjacent buildings.

Services Impacted: This is a noise generating activity.

Work Performed By:  Hoffman Construction

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

Current construction and impacts information can be found on the UO Maps site.

Map of Utility Tunnel Excavation work 11/27/23 through 12/1/23

POSTPONED – Lot 2 Construction Activity and Access Advisory

UPDATE 11/08/23:
Due to parts delay and scheduling conflicts with Facilities, this work has been postponed.  A new notification will be sent prior to starting the project.

 

BeginMonday, November 13, 2023  Postponed

End:      Wednesday, November 22, 2023  Postponed

Building(s) or Area(s) Affected:  Lot 2, CPFM Warehouse Bldg. 136, CPFM Administrative Quonset, CPFM Compound

Scope:  Construction associated with the replacement of the vehicle and pedestrian gates at the main entrance to the CPFM compound will begin November 13th.  This will result in intermittent closure of the main entrance while work is being performed in the roadway (asphalt cutting, excavation, installation of electrical lines, new fence panels, backfill, and resurfacing). Vehicle plates will be used to allow travel over open trenches when work is not actively being performed in the roadway.  The schedule remains fluid based on weather and contractor availability. Notification updates will be provided as the project progresses.

Services Impacted:

  • When access is restricted, vehicles should use the west entrance to the compound.
  • Caution is advised as vehicles will be traveling in both directions and the roadway narrows to one lane in some areas.

Work Performed By:  Contractor and CPFM Facilities

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Map of construction area and detour route for Lot 2 gate work

11/06/23 – 11/10/23 Matthew Knight Arena Marquee/Video Board Replacement Advisory

Begin:  Monday, November 6, 2023, at 7:30 am

End:      Friday, November 10, 2023, at 3:30 pm

Building(s) or Area(s) Affected:  Matthew Knight Arena

Scope:  The marquee/video board at the corner of Villard St. and Franklin Blvd., near the east entrance to Matthew Knight Arena, will be replaced next week.

Services Impacted:

  • Access to MKA and along the sidewalk will be maintained at all times.
  • The contractor will coordinate with Athletics on game days to avoid any disruptions from the construction work.
  • Noise is to be expected during this activity.

Work Performed By:  ES and A Signs

ContactLuke Helm, CPFM Owner’s Representative, 541-346-8216 or 458-256-7622

Current construction and impacts information can be found on the UO Maps site.

Image of Matthew Knight Arena

 

9/21/23 – 4/30/25 Villard Hall and University Hall “Heritage Project” Fencing and Pathway Advisory

UPDATE:
Revised pedestrian route attached.

Revised pedestrian map 9-20-23

UO Heritage Pedestrian Routes 9.20.23

 

Begin:  Thursday, September 21, 2023

End:      Wednesday, April 30, 2025

Building(s) or Area(s) Affected:  Areas surrounding Villard, University, Lillis, Lawrence, Friendly, and Fenton Halls

Scope:  Due to the renovation of Villard Hall and University Hall, known as the “Heritage Project”, the site around both buildings will fenced off for the duration of the project.

Services Impacted:

  • This will affect the walking routes in the vicinity.
  • Temporary mulch paths with fencing will be installed, and remain for the duration of the project.
  • Walkways are anticipated to be reopened during the Spring of 2025.

Work Performed By:  Fortis Construction

Contacts: Tim Allenbaugh, CPFM Owner’s Representative, 541-346-8214

Gene Mowery, CPFM Owner’s Representative, 541-346-5593

Current construction and impacts information can be found on the UO Maps site.

Image of Heritage Project Fencing Advisory Map 9-21-23 thru 4-30-25

Pages from Site Logistics Plan_Heritage_Phase 3 Rev2 SW Closed

10/02/23 – 8/30/24 Kalapuya Ilihi Repair Work Advisory

Begin:  Monday, October 2, 2023

End:      Monday, August 30, 2024

Building(s) or Area(s) Affected:  Kalapuya Ilihi plus Lots 34C, 34E and 55

Scope:  Kalapuya Ilihi Repairs: On October 2, 2023 we will set up fencing around Kalapuya Ilihi that will impact sidewalks and parking spaces adjacent to Kalapuya.

Services Impacted:

  • This will affect several spaces within Parking Lots 34C, 34E, and 55 plus sidewalks in the area.
  • The four impacted loading and unloading spaces on Moss Street dedicated to the Moss Street Children’s Center will be moved immediately to the north of the impacted spots.

Work Performed By:  Fortis Construction

ContactGeorge Bleekman, CPFM Owner’s Representative, 541-346-2625

Current construction and impacts information can be found on the UO Maps site.

Image of construction impacts around Kalapuya Ilihi

KI Fence Line

9/21/23 – 9/22/23 Campus Move In Traffic and Parking Impacts Advisory

As the UO welcomes new resident students to campus, Transportation Services would like to make you aware of some upcoming traffic and parking impacts that are expected the week of September 18th. To help accommodate this large move-in process, we encourage parkers to avoid parking lots around the residence halls this week.

Traffic impacts related to street closures near residence halls on 9/21 and 9/22:

  • Agate Street and portions of 13th, 15th, and 17th Avenues will be restricted to Move-in traffic and vehicles on UO business.
  • All 13th Ave. traffic must enter from 13th Ave. and Franklin Blvd. and should expect delays.
  • Permit holders will be able to access UO lots but should expect delays.
  • 13th Ave. between University and Agate Streets will be restricted to westbound traffic only.
  • The 13th Ave. Garage will be open to permit holders.
  • Lots 29A, 29D, 33, 36A and 37 will be reserved for Move in.

For questions or concerns, please contact Transportation Services at 541-346-5444.

Current construction and impacts information can be found on the UO Maps site.

Image of affected roads during Move In 9/21/23 - 9/22/23

9/11/23 – 9/18/23 Agate Street plus Lots 38, 39, and 43 Closure Advisory for Prefontaine Classic

Begin:  Monday, September 11, 2023

End:      Monday, September 18, 2023

Scope:  The University of Oregon is hosting the Prefontaine Classic at Hayward Field on Saturday, September 16th and Sunday, September 17th and attendance is expected to be robust.

Event impacts and related closures, as outlined below, will start on Monday, September 11th and continue through Monday, September 18th. Please anticipate an increase in traffic around campus and at the Millrace Garage during this time.

Agate Street Closures:

  • Agate Street closed from 17th Ave. to 18th Ave. beginning 9/11.
  • Agate Street closed from 15th Ave. to 18th Ave. 9/13 – 9/18.
  • Agate Street closed from 13th Ave. to 18th Ave. 9/16 – 9/17.

Campus Lot Closures

  • Lot 38 closed 9/13 – 9/17.
  • Lot 39 and 43 closed 9/16 & 9/17.

ContactJames McGladrey, UO Transportation Services Field Operations Manager, 541-346-2676

Image showing Agate Street plus Lots 38, 39, and 43 affected by the Prefontaine Classic 9-11-23 thru 9-18-23

9/14/23 – 3/29/24 North Campus Concrete Truck Activity Advisory

Begin:  Thursday, September 14, 2023

End:      Friday, March 29, 2024

Building(s) or Area(s) Affected:  North Campus, Lot 3B, and Gallery Way.

Scope:  Periodically between 9/14/23 and 3/29/24 there will be concrete trucks delivering to the utility tunnel construction located between the Woodshop and Fine Arts Building C. The map below shows the truck routes in and out of the site.

Services Impacted:  On days that concrete trucks are delivering, parking stall #39 in Lot 3B will be closed for trucks to safely navigate the left hand turn off of Gallery Way.

Work Performed By:  Hoffman Construction

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

Current construction and impacts information can be found on the UO Maps site.

Map of North Campus Concrete Truck Route 9-14-23 thru 3-29-24

9/07/23 Oregon Hall Exterior Noise Advisory

Begin:  Thursday, September 7, 2023, at 8:00 am

End:      Thursday, September 7, 2023, at 10:00 am

Building(s) or Area(s) Affected:  Along east side of Oregon Hall

Scope:  Facilities Services will be using the Vac truck to pot a new hole to replace a sign post that was broken.

Services Impacted:  Noise can be expected during this time.

Work Performed By:  CPFM Facilities Services

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Oregon Hall

8/21/23 – 9/29/23 East 13th Ave. (between Kincaid St. and Agate St.) Surveying Advisory

UPDATE:
This notice has been extended through the end of the month.

 

Begin:  Monday, August 21, 2023

End:      Friday, September 8  29, 2023

Building(s) or Area(s) Affected:  East 13th Ave. between Kincaid St. and Agate St.

Scope:  A field survey crew will be surveying site utilities and topography along East 13th Avenue between Kincaid and Agate Streets for the next 3 weeks.

Services Impacted:  Pedestrian, bike, and vehicular access will not be impacted.

Work Performed By:  Contractor

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

Image of East 13th Avenue between Kincaid St. and Agate St.

8/28/23 – 9/01/23 Riverfront Parkway Road Closure

Begin:  Monday, August 28, 2023

End:      Friday, September 1, 2023

Building(s) or Area(s) Affected:  Riverfront Parkway between Millrace Drive and Franklin Boulevard

Scope:  All lanes of Riverfront Parkway will be closed to modify utilities beneath the roadway.  See the image below for detour routes.

Services Impacted:

  • Riverfront Parkway will be closed to all vehicle traffic during this time as well as the eastbound left turn lane on Franklin Blvd.
  • The east sidewalk will remain open for pedestrian traffic.

Work Performed By:  Hoffman Construction

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

Current construction and impacts information can be found on the UO Maps site.

Image of detour route for Riverfront Parkway 8/28/23 - 9/1/23

8/16/23 – 8/17/23 Lillis Hall North Entrance Closure Advisory

Begin:  Tuesday, August 16, 2023

End:      Thursday, August 17, 2023

Building(s) or Area(s) Affected:  Lillis Hall

Scope:  The 4th floor balcony will be pressure washed.  Water will be cascading down to the areas below, which includes the north entrance.

Services Impacted:

  • The north entrance will be closed.
  • Noise is to be expected during this time.

Special Instructions:  Please use the south entry or other entrance points.

Work Performed By:  CPFM Facilities Maintenance Support

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Lillis Complex

8/14/23 – 8/17/23 Friendly Hall Pressure Washing Advisory

Begin:  Monday, August 14, 2023

End:      Thursday, August 17, 2023

Building(s) or Area(s) Affected:  Friendly Hall

Scope:  The stairs leading to the basement will be pressure washed.

Services Impacted:

  • This will affect the basement stairwells and surrounding areas.
  • Noise is to be expected during this time.

Work Performed By:  CPFM Facilities Maintenance Support

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Friendly Hall

8/09/23 Millrace 1 & 2, Fine Arts A, B, C, & Woodshop Electrical Power Shutdown

Begin:  Wednesday, August 9, 2023, at 7:00 am

End:      Wednesday, August 9, 2023, at 7:00 pm

Building(s) or Area(s) Affected:  Millrace 1, Millrace 2, Fine Arts A, Fine Arts B, Fine Arts C, & Woodshop.

Scope:  EWEB will be installing new power feeders to a new utility vault and contractors will be reconnecting buildings to new EWEB feeders.

Services Impacted:  Electrical power will be offline during this time.

Work Performed By:  EWEB and Hoffman Construction

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

Current construction and impacts information can be found on the UO Maps site.

Image of the Fine Arts and Millrace Studio buildings that will be affected

8/9/23 Millrace Path and Gallery Walk Axis Power Pole Work Advisory

UPDATE:  EWEB has changed the schedule and will now complete this work on 8/9/23

BeginThursday, August 10, 2023 – morning Wednesday, August 9, 2023

End:      Thursday, August 10, 2023 – morning Wednesday, August 9, 2023 by 10:00 a

Building(s) or Area(s) Affected:  Area SW of Urban Farm

Scope:  On the morning of August 10th, EWEB will be removing an existing power pole near the intersection of the Millrace Path and Gallery Walk Axis that will temporarily detour bike and pedestrian traffic. (See map below)

Services Impacted:

  • This will affect access in the Millrace Path and Gallery Walk Axis area.
  • Bike and pedestrian traffic will be rerouted along Franklin Blvd. and Onyx Street.

Work Performed By:  EWEB

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

Current construction and impacts information can be found on the UO Maps site.

map to closure

7/10/23 – 2/23/24 Gallery Way Road Closure Advisory

UPDATE:
Work on the utility tunnel has been extended to January 23, 2024.  (See revised map)

Revised map for Gallery Way utility tunnel project 9-19-23

Begin:  Monday, July 10, 2023

End:      December 15, 2023, Tuesday, January 23, 2024

Building(s) or Area(s) Affected:  Gallery Way road, Urban Farm access, Millrace Studios, Fine Arts Studios & Woodshop (See attached logistics plan)

Scope:  The Gallery Way road will be closed in the section directly east of the Millrace Studios for construction of a utility tunnel.

Services Impacted:

  • Pedestrian and bicycle traffic will be rerouted during this time (see diagram below).
  • Construction noise can also be expected.

Work Performed By:  Hoffman Construction

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

Current construction and impacts information can be found on the UO Maps site.

Image of Gallery Way Tunnel Work Area 7-10-23 thru 12-15-23

6/29/23 CPFM Yard and Back 40 Traffic and Access Advisory

Begin:  Thursday, June 29, 2023, at 9:00 am

End:      Thursday, June 29, 2023, at 5:00 pm

Building(s) or Area(s) Affected:  CPFM Yard and Back 40

Scope:  Large trucks will be moving through the CFPM Yard to deliver six additional Connexes into the Back 40.  This will allow Facilities Services to increase their storage capacity.

Services Impacted:  Access will be temporarily restricted for the north side of the Back 40 plus an increase in CPFM Yard traffic is expected.

Work Performed By:  Western Storage

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of the CPFM Compound

6/23/23 – 10/30/23 Heritage Renovation Project Informational Bulletin

UPDATE 10/25/23:
Fortis Construction is fully mobilizing onto the Project site beginning October 30th.  Work activity for the removal for restoration of the University and Villard Hall windows will also commence, as well as interior building demolition within the two buildings and continue for the next few months.

Please contact UO Owner’s Representatives Tim Allenbaugh (541-346-8214) or Gene Mowery (541-346-5593) if you have questions.
NOTICE AND REMINDER 8/08/23:

  • Villard Hall Theatre Arts department move has been completed.
  • Parking Lot 9 is enclosed by construction fencing and no longer open to public access.
  • Villard Hall abatement staging began today and abatement activity will continue into September.
  • Villard Hall is closed and open only to authorized abatement and construction contractors and university personnel.

 

REMINDER 7/17/23:

  • July 17, Fortis Construction began setting up construction fencing and closing off access to Parking Lot 9. Initial construction fencing will enclose Villard Hall as well, limiting access into the building.  Sidewalks/pathways on the north and east sides of Villard will remain open.
  • Villard Hall department moves are scheduled for July 19-21.
  • Villard Hall abatement is scheduled to begin August 7 and will continue into September.
  • Access into University Hall will continue until the end of the second summer class session, August 18. (But parking lot will be offline for vehicles)

 

Begin:  Friday, June 23, 2023

End:      Project Completion Summer 2025

Building(s) or Area(s) Affected:  Villard Hall, University Hall, Parking Lot 9

Scope:  General information for summer activity associated with the Heritage Renovation Project (exterior historic preservation and interior remodel of University and Villard Halls) are outlined as follows:

    • Contractors Fortis Construction and GBC Construction will periodically be in both Villard Hall and University Hall prior to established department move dates for pre-abatement and demolition investigations and activity.  When the department move dates are reached and moves completed, the buildings will be off-line for access without specific approval.  Once abatement starts, the buildings and site will be fully restrictive access.
    • The parking area between University and Villard Halls will remain open until July 16. Beginning July 17, Fortis Construction will begin setting up construction fencing and closing off access to this parking area. Initial construction fencing will enclose Villard Hall as well, limiting access into the building.
    • Villard Hall department moves are scheduled for July 19-21.
    • Villard Hall abatement is scheduled to begin August 7 and will continue into September.
    • Access into University Hall will continue until the end of the second summer class session, August 18. (But parking lot will be offline for vehicles)
    • University Hall: Mathematics department move is scheduled for August 21-23. Construction fencing to enclose University Hall is targeted to begin in this time period as well.
    • University Hall abatement is scheduled to begin September 4 and will continue into October.
    • In conjunction with construction fencing installation, vehicular and pedestrian pathway closure and rerouting signage will be put in place.

Please contact UO Owner’s Representatives Tim Allenbaugh (541-346-8214) or Gene Mowery (541-346-5593) if you have questions.

Current construction and impacts information can be found on the UO Maps site.

 

Image of Villard, University Hall, and Lot 9

6/19/23 – 7/06/23 East 13th Ave., Kincaid St., Duck Store Area Construction Work Advisory

Begin:  Monday, June 19, 2023

End:      Thursday, July 6, 2023

Building(s) or Area(s) Affected:  West and north sides of the UO Duck Store, E. 13th Ave., and Kincaid Street

Scope:  A privately engineered public improvement (PEPI) project is planned for construction within the right-of-way that is adjacent to the UO Duck Store. The project is privately designed, privately funded, and privately constructed.  The construction will occur at 871 E 13th Avenue in Eugene, Oregon 97401.  Please see the attached map for the project location.

Construction within E. 13th Avenue will begin in late June, approximately June 26th. Construction within Kincaid Street will begin roughly a week later.  During construction, the sidewalk on the north side of E. 13th Avenue and on the west side of Kincaid Street will be closed. Work on Kincaid Street will be done at night.  This project includes utility Improvements. The improvements include:

  • Sanitary sewer line extension
  • New sanitary manhole
  • Storm line extension
  • New storm manhole
  • Minor paving 12th Alley, E 13th Avenue and Kincaid Street

Work Performed By:  John Hyland Construction

Contact:  If you have questions or concerns regarding design Issues, please contact:

Donna Stark
City of Eugene Public Works Engineering
OR 99E Broadway, Ste 400
Eugene, OR 97401
541.729.4638
dstark@eugene-or.gov

Aaron Williams
John Hyland Construction
1941Laura Street
Springfield, OR 97477
541.501.8623
awi1liams@jhconst.com

Current construction and impacts information can be found on the UO Maps site.

Map of area by the Duck Store 6-14-23

Construction Work by UO Duck Store

6/09/23 – 9/30/23 Streisinger Hall and Parking Lot 12B East Science Loop Project

2nd UPDATE 9/28/23:
It is expected that the tar odors may be noticed around Klamath Hall, and possibly Onyx Bridge, tomorrow.

 

UPDATE 9/28/23:
The East Science Loop civil contractor will be paving the parking lot on the north side of the Streisinger building (see picture for specifics), weather depending. This is scheduled for Friday, September 29th from 7:00 am to 12:0 noon.  During this work the adjacent areas will be experiencing heavy vehicle traffic as the work is being performed, and due to this spaces might be blocked temporarily. Additionally, some paving odors will be present during the work as well.

If this work does not take place due to weather, the notice will be updated with future times/dates to be aware of.

Thank you for your understanding.

Diagram of Streisinger Lot Paving Project for 9-29-23

 

UPDATE 7/11/23:
The crane/closure dates have now been shifted, due to crane availability, to Friday, July 21st, and Wednesday, July 26th.  The third date is yet to be determined.

 

UPDATE to 6/30/23 Lab Waste Shutdown Entry (7/05/23):
After speaking with the building users regarding lab waste schedules, we are rescheduling the lab waste piping connection shutdown to Friday, July 7th, and Monday, July 10th.

 

UPDATE 7/05/23:
As part of vault deliveries for the East Loop Electrical project, the parking lot area shown will be closed and also the associated loading dock will be down for the duration of the crane work on Monday, July 17th Friday, July 21st, at 7:00 am through Tuesday, July 18th, until 6:00 pm.  Please take this into consideration for your activities, and reach out should this activity limit critical operations/needs.  This will be the first of 3 such closures, with the next potentially occurring 7/25 7/26 and 8/2 TBD. We will update this notice each time to ensure we are working around your needs as we are able.

Image of parking lot for Streisinger and Klamath

 

UPDATE 6/30/23:
Due to work needed to move the East Loop electrical project forward, the lab waste piping will be shut down for up to a days’ time to make the necessary connections to improve the system. This will affect Streisinger, Klamath, and Onyx Bridge.  Be advised that during this time, all lab waste drains will be unable to be used (eg: sink drains).  We are intending to perform this work on Tuesday, July 11th, Friday, July 7th, and Monday, July 10th, from 7:00 am to 5:00 pm.    Please let us know if that day presents a conflict in regard to your operations.  If not, we will update this work as confirmed.

 

UPDATE:
The arborist notified us that due to a change in his schedule, the tree work will take place tomorrow.

 

Begin:  Monday, June 12, 2023

End:      Saturday, September 30, 2023

Building(s) or Area(s) Affected:  Streisinger Hall, East end of Parking Lot 12B

Scope:  Beginning next week, the East Science Loop civil contractor will be kicking off ground work for the project. This will include demolition in the project area, including asphalt removal, tree/planting removal, and earthwork.

Services Impacted:

  • Please be aware associated noises and vibrations are to be expected.
  • The adjacent loading dock will be functional throughout.
  • Pedestrian rerouting (e.g.: not through the parking lot area) will be present for the life of the project. (See picture for details.)
  • No disruptions to services (not previously discussed) are expected.

Work Performed By:  Wildish Construction

ContactDamon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285

Current construction and impacts information can be found on the UO Maps site.

Diagram of Streisinger and Lot 12B

6/13/23 Condon Hall Roof Crane Work Advisory

UPDATE:
We apologize for this late notice, but we just received notification that this work will take place tomorrow morning.  The crane will be staged on Kincaid Street around 6:30 or 7:00 am.  The sidewalk and exit will be blocked off and the contractor will be on site redirecting people.  Work is expected to be completed by 12:00 noon.

 

UPDATE:
The equipment replacement at Condon has been delayed.  Once the contractor can confirm materials are in place, the date will be reset.  Facilities Services expects this to be the week of June 12th.  The specific date will be shared once we hear from the contractor.

 

Begin: Monday, June 5, 2023, at 8:00 am   TBD Tuesday, June 13, 2023, at 6:30 am

End: Tuesday, June 6, 2023, at 3:00 pm      TBD  Tuesday, June 13, 2023, at 12:00 noon

Building(s) or Area(s) Affected: Condon Hall

Scope: Work will be occurring on the roof of Condon to replace a failed cooling unit beginning Monday, June 5th  Tuesday, June 13th. On the following day, crane work will take place on East 13th Avenue, on Kincaid Street, next to Condon, to remove old equipment and install a new unit.

Services Impacted:

  • This will affect the HVAC air supply.
  • 13th Avenue will be partially blocked during this time.  The sidewalk on Kincaid will be blocked off.

Work Performed By: FS Sheetmetal

Contact: Work Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Condon Hall

 

5/15/23 – 9/12/23 Parking Lot 12B (North of Streisinger) Closure

Begin:  Monday, May 15, 2023

End:      Tuesday, September 12, 2023

Building(s) or Area(s) Affected:  Lot 12B, Streisinger, Klamath Hall, and Lewis Integrated Science Bldg.

Scope:  As part of the East Science Loop Electrical Project, the east side of the parking lot to the north of Streisinger, and south of Franklin Blvd., will be closed for the duration of work. Notifications will be posted in advance of any work expected to be impactful to the surrounding areas, as well as for any related outages.

Services Impacted:

  • Parking and other associated services within the work zone, outlined as pictured, will be unavailable – please plan accordingly.
  • The adjacent loading dock will continue to be operational.
  • Noise and vibration are to be expected during this time.

Work Performed By:  Wildish Construction

ContactDamon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285

Current construction and impacts information can be found on the UO Maps site.

Image of Log 12B closure area north of Streisinger

5/08/23 – 7/15/23 Walton Hall Project Area and Powell Plaza Fence Adjustment

Begin:  Monday, May 8, 2023, at 8:00 am

End:      Saturday, July 15, 2023, at 5:00 pm

Building(s) or Area(s) Affected:  Walton Project Area / Powell Plaza

Scope:  On May 8th at the Walton replacement project, we will shifting the fence line on Powell Plaza to the south in order to finish the landscaping on the project.

Services Impacted:  This will not impact pedestrian flow, and the fencing will remain in place until the removal of the fencing July 15th.

Special Instructions:  We will have a bump out in the fence to allow for deliveries.  During large track events, this bump out will be pulled back.

Work Performed By:  Fortis Construction

ContactGeorge Bleekman, CPFM Owner’s Representative, 541-346-2625

Current construction and impacts information can be found on the UO Maps site.

Diagram of Walton Replacement Fencing shift