Construction of Small Parking Lot 12/10 – 1/4

Campus Community,

Construction of a small parking lot in the open space on the southeast corner of Walton Hall near the intersection of Agate and 15th will begin 12/10. Impacts should be minimal and limited to the project site.

For questions or concerns please contact CPFM Design and Construction Facilities Engineer Sarah Follett at 541-346-8264.

EWEB Agate Street Water Main Replacement Starts 10/8

Campus Community,

Our utility provider EWEB requested we share information about an upcoming water main replacement along Agate Street. The water main is located in the west southbound parking strip. This will require city parking spots along the work zone to be vacated for the duration of the project. Pedestrian sidewalks and crosswalks will be impacted in this area and signage, and detours will be in place. City crews will be working each day from 7:00 am – 5:00 pm.

For questions or concerns please contact EWEB Chris Irvin, P.E. Senior Engineer, Water Engineering at 541-685-7619 christopher.irvin@eweb.org

University of Oregon Contact CPFM Design and Construction Sarah Follett 541-346-8264

This work is expected to start the week of October 8. The main construction will take 3-4 weeks with final disinfection and tie-ins following for a total project duration of approximately six weeks.

2018 Fall Street Faire Road Closure 13th Ave 10/10 – 10/12

Campus Community,

On October 10 – 12, 2018 the ASUO Fall Street Faire will have 13th Ave closed from University Street to Kincaid Street. Activity will begin in this area on October 9. Bike racks will be removed, and parking will be closed along 13th Ave to accommodate vendors.

For questions or concerns please contact event organizer Kylie MacDonald at 541-346-0622 or 541-346-7865

http://uoregon.orgsync.com/org/associatedstudentsofuo/programs_street_faire

Parking Lot 34A Closure Due to Crane Placement 10/1

Campus Community,

On Oct. 1, 2018, from 7:30 am – 9:30 am, parking lot 34A will be partially obstructed by a crane used to lift two Mammoth sculptures from 15th Ave. into the courtyard of the Museum of Natural and Cultural History. Access to the lot will be very limited. The staging of the crane, flatbed, and flagged control points are shown in the diagram. Please be aware of the activity in this area during this time.

For questions or concerns please contact CPFM Design and Construction Manager George Bleekman at 541-346-2625.

Update! ESPN GameDay 2018 Closures and Detours 9/19 – 9/22

This update has been sent to building occupants in PLC and Condon.

Building Occupants,

Due to ESPN GameDay 2018 entry into the PLC north entrance and the Condon South Entrance entry is restricted.  Please use another exit if possible (emergency egress will be allowed).

For questions or concerns please contact CPFM Work Control Center at 541-346-2319.

 

https://blogs.uoregon.edu/cpfmnotifications/2018/09/18/espn-game-day-2018-closures-and-detours-919-922/

Sent: Tuesday, September 18, 2018 4:37 PM
Subject: ESPN GameDay 2018 Closures and Detours along Kincaid 9/19 – 9/22

Campus Community,

Starting Wednesday, September 19 at 5:30 am through Saturday, September 22 at 5:30 pm Kincaid Street from 13th ave to 15th ave will experience a northbound lane closure, east side parking closures, and bike rack removals to accommodate ESPN GameDay equipment along Kincaid Street.  There will also be fencing staged in the Quad outside of Condon Hall, Prince Lucien Campbell, Jordan Schnitzer Museum of Art, Knight Library, and Chapman Hall.  Please expect increased activity and congestion in this area.

Impacts:

Northbound lane closure on Kincaid from 13th Ave to 14th Ave
East Side parking on Kincaid from 13th Ave to 15th Ave
Several Bike Rack removals along Kincaid
Fencing Staged in Condon Hall, Prince Lucien Campbell, Jordan Schnitzer Museum of Art, Knight Library, and Chapman Hall Quad

Contact:  CPFM Work Control Center

For questions or concerns please contact CPFM Work Control Center at 541-346-2319.

[1715 FRANKLIN] LANDSCAPE WORK 7/10 – 7/27 IN PREPARATION OF SUMMER PAINTING 8/1 – 8/31

Landscape Activities

Beginning July 10th, 2018 through July 27th, 2018 there will be trimming of shrubs and trees along the exterior of the building, including the bike cage and dumpster areas. There may be additional noise when work is in progress.

Painting & Power Washing Activities

The owners have contracted with Gary Pierce Painting to have the entire exterior of the building power washed and painted. Work is anticipated to begin on August 1, 2018, and be completed on or near August 31, 2018. Starting August 1st, Gary Pierce Painting will power wash the entire exterior building. Power washing will be completed in sections. After the power washing is completed, the painting will begin and also completed in sections. A lift will be on-site and used to complete this project.

Please note the following:

-There will be additional noise
-There may be odors
-Parking will be affected. Sections of parking in the row closest to the building will be blocked off  throughout the duration of this project.

Please use caution as you enter and exit the building. Also, please watch for equipment and folks that are working on this project.

Please report any water leaks from power washing immediately.


For questions or concerns please contact CPFM Real Estate Property Coordinator and Lease Management Melinda Seeley at 541-346-5550.

Campus Wide Parking Lot Closures 7/21 – 7/22 & 7/28 – 7/29

Campus Community,

Parking and Transportation annual summer lot painting is July 21 – 22 and 28 – 29. Various lots across campus will be closed preceding the Friday night for both Saturday and Sunday work. The Parking Lots will be re-opened as soon as the paint is dry.

To view and identify lots across campus visit the UO Parking Map https://map.uoregon.edu/?cl=parking_color

For questions or concerns please contact Transportation and Parking Field Operations Manager James McGladrey at 541-36-2679

https://parking.uoregon.edu/

 

3/29: [LOT 12A] Closure due to Crane Staging

This notice has been sent to all building occupants who may use Lot 12 A in Cascade Annex, Cascade, Onyx Bridge, Pacific, Lawrence and Klamath and FS Memo List.

Building Occupants,

Parking Lot 12 A will be closed on March 29, 2018 from 5:00 am – 1:00 pm due to crane staging.  This is necessary while a contractor replaces a packaged rooftop unit that services the Bohannan Lab in Pacific Hall Room 308.

For questions or concerns please contact CPFM Facilities Services Manager Bruce Budzik at 541-346-8834.

3/6 – 3/23: NW Natural Work Zones along Millrace, Fine Arts & ZIRC Impacting Paths of Travel

Campus Community,

As part of the Knight Campus Project, our utility provider NW Natural has requested a series of work zone notifications redirecting pedestrian, bicycle, and vehicular traffic.  Please expect noise and congestion in these work areas.

Zone 1 March 6 – March 9, 2018

Service and emergency vehicle access only.  Service vehicles are encouraged to use alternate routes. Lots 3A and 3B will remain open, but access may be delayed.  Parking in Lot 4 and 56 is encouraged.

Zone 2 March 12 – March 23, 2018

Service and emergency vehicle access only.  Service vehicles are encouraged to use alternate routes.  Lots 3A and 3B will remain open, but access may be delayed.  Parking in Lot 4 and 56 is encouraged.

Looking ahead:

  • Week of March 6 Design and Construction will be coordinating a NW Natural Gas Shutdown with building occupants
  • Late March parts of Millrace Path will be closed to pedestrian and bike traffic.

For questions or concerns regarding how these activities may impact access to your buildings or research, please contact CPFM Design and Construction Project Civil Engineer Sarah Follett at 541-346-8264.

2/19/18: Knight Law Parking Lot 34A Closure

Date Revision:  The date has been pushed back to Monday, February 19th.

Campus Users,

On Thursday, February 15th Monday, February 19th from 7:00 am until 4:00 pm, the Knight Law Parking Lot 34A will be closed.  A crane will be used to do some electrical work on the roof of the law school.

Work will be performed by Scofield Electric.

For questions or concerns about how this may affect your area, contact Glen Macdonald, Campus Planning and Facilities Management (CPFM) Design and Construction at 346-2281.

2/12 – 12/15: Lane & Parking Closure 15th Ave

Campus Community,

Starting February 12  through February 15, 2018,15th Ave between Bean Hall and Global Scholars Hall/Museum of Natural and Cultural History will be limited to one lane of traffic to allow for steel deliveries for the Bean Hall Project. The sidewalk and parking spaces on the north side of the street in front of Bean Hall will be closed, along with the north lane of traffic, and traffic will be restricted to the south lane during the deliveries during this time. Flaggers will coordinate the two way traffic in the south lane. Please be aware of the limited access during this time. Pedestrian traffic on the south 15th Ave. sidewalk will not be impeded.

For questions or concerns please contact CPFM Design and Construction Owners Representative George Bleekman at 541-346-2625.

 

1/9 – 1/11: [PARKING LOT 12A] Project Deliveries Possible Congestion and Delays

Building Occupants,

There will be a series of material deliveries in Parking Lot 12A on 1/9, 1/10, and 1/11 from 7:00 am – 12:00 pm (noon) each day. These deliveries will require the use of a full-size semi and may create some additional congestion in the parking lot. Andersen Construction will have two staff monitoring the parking lot activity and assisting vehicles entering/exiting the lot.

This may impact occupants of Pacific Hall, Lawrence Hall, Cascade Hall, Cascade Annex and Onyx Bridge.

For questions or concerns, please contact CPFM Design and Construction Project Manager Nick Pritchard at 541-346-9139.

UPDATE: 12/10 – 1/2: Closure: 15th Ave Between Agate and University Street and Bowerman Parking Lot 31

Building Occupants,

 

Due to the EWEB waterline replacement project on 15th avenue, the water will be shut off to both LLC and Bowerman from 9 a.m. to 5 p.m. on Thursday, 12/21/17 to connect the building water for these two buildings to the new water main in 15th.  Domestic water from the fire line will be shut off in Bowerman ONLY, thus UO Fire Protection will provide fire watch or monitors.

 

Please reference the below updates from Jana Gerow CPFM Design and Construction Owners Representative 541-346-8317.

 

_____________________________________________________________________________________________________________

 

Campus Community,

EWEB will be replacing the main water line under 15 Ave between Agate Ave and University Street from Agate to just east of the Recreation Center starting December 11, 2017, Sunday, December 10, 2017, thru January 2, 2018.  The roadway will be closed during this time to traffic as well as the Bowerman Parking Lot #31. Work will be done from 8:00 am -5:00 pm weekdays, however, the roadway and lot will remain closed during off hours.

 

There will be an additional notice sent regarding a water shutdown for one day (likely between December 25 & Dec 31, 2017 ) that will impact LLC and Walton Bowerman.  EWEB will be providing the standard 48-hour notice and information about the water shutdown will be communicated as it is received.  NOTE: Water will NOT be shut off to Walton during this project.

 

For questions, please contact Jana Gerow CPFM Design and Construction Owners Representative 541-346-8317.

11/19: Parking lot closures at BDC and 10th & Mill

Building Occupants,

On Sunday, November 19, 2017, lot 1D will be closed for tree trimming and landscape maintenance.   This may impact Baker Downtown Center and 10th & Mill building occupants.  This is necessary due to heavy equipment and trimmed tree boughs that will be blocking entrance and egress from the east side of the lot as well as the Diamond Parking lot leased to the 10th & Mill building.

For questions for concerns, please contact Lawrence Elliott, CPFM Zone C Facility and Tenant Coordinator at 541-346-5164.

9/14 – 9/18: Pacific, Cascade Annex, and Lawrence Increased Construction Deliveries

Building Occupants,

There will be increased construction delivery activity in parking lot 12A (north east of Pacific Hall) starting September 14, 2017, through September 18, 2017.  Contractor Andersen Construction will have an employee monitoring parking lot activity during this time to help coordinate deliveries.  We appreciate your patience during construction activities.

For questions or concerns, please contact CPFM Design and Construction Project Manager Nick Pritchard 541-346-9139.

9/18 – 9/20: Parking Closure and Delays Impacting JSMA, Susan Campbell and Johnson Hall

Campus Community,

Contractors will be on site grading the entry way to Parking Lot 25 on Monday, September 18, 2017, and Tuesday, September 19, 2017.  Access to lot 25 and JSMA loading dock will still be available, but short delays may be possible. Lot 25 will be closed on Wednesday, September 20, 2017, for asphalt paving of the entry way to that lot.  Short delays may be possible in and out of Lot 23, but access will remain open to lot 23. This will affect users of JSMA, Susan Campbell and Johnson Hall.

For questions or concerns, please contact CPFM Design and Construction Owners Representative Martina Oxoby at 541-346-5880 or 541-556-8477.

 

8/18 – 8/25: Parking Lot #25 Closures

Campus Community,

As part of the Collier Parking Lot and Tykeson Hall construction work, Parking Lot #25 will be closed this weekend starting at 5:00 pm on Friday, August 18, 2017, through 5:00 pm Saturday, August 19, 2017.  This is necessary as part of the tree removal work.

Due to ongoing construction activities associated with driveway work between Johnson Lane and Lot #25 Parking Lot #25 will experience daily closures 7:00 am – 5:30 pm next week starting Monday, August 21, 2017, through Friday, August 25, 2017.  Parking Lot #25 will open up each night after 5:30 pm and be made accessible for access to the loading dock.

For questions or concerns regarding this closure please contact CPFM Design and Construction Owners Representative Martina Oxoby at 541-346-5880.

5/17/17-5/19/17: Berwick Hall Parking Lot #20 Access Lane Closure

Campus Community,

On Wednesday, May 17th at 7:00 am until Friday, May 19th at 6:00 pm, access to Parking Lot #20 will be closed due to upcoming work on the Berwick Project.  Traffic will be limited to emergency vehicles only.

This will affect School of Music and Dance, Pioneer Cemetery and access through the fire lane off of 18th Ave.

For questions or concerns about how this may impact your area, contact Martina Oxoby, Campus Planning and Facilities Management (CPFM) Campus Planning at 346-5880.

 

1/16/17 – 6/30/17: Streisinger Loading Dock – GBC Construction Staging

Campus Community,

Attached you will find a diagram of Lot 12B on the north side of Streisinger Hall showing ‘GBC Construction’ staging for the construction of the Klamath Hall 2nd Floor Core Remodel. Monday, January 16th GBC will place their job trailer and begin to occupy the areas shown. The project is scheduled to complete June 2017 at which time the trailer, dumpster, and fencing will be removed.

The loading dock will remain open for use. The attached layout has been approved by the City of Eugene Fire Marshall and UO Parking Services. The utility hole located in parking stall 14 will remain accessible to CPS.

Thank you,

Denise Stewart, CPFM Construction Project Manager

dstewart@uoregon.edu Phone: 541-346-2280

Lot 12B 8-23-16 (3)-2b51lxr