Tykeson Hall Paving and Parking Lot 25 Closure July 22 – 30

Campus Community,

As part of the Tykeson Hall construction project, Fortis Construction will be completing the flatwork paving at the south end of the building. This will impact the west end of Johnson Lane and access to Lot 25 and the JSMA loading dock.

New closure dates July 22 – 30.

For questions or concerns please contact CPFM Design and Construction Owners Rep Martina Oxoby at 541-346-5880

 

Roof Work Requires Lift Staging in Cascade Courtyard through 6/28

Facilities Liaisons,

Facilities Services is performing annual summer roof preventative maintenance on Cascade, Willamette, Klamath, and Onyx and will be blocking off sections of the Cascade courtyard through Friday, June 28. Please expect access to be temporarily blocked as they move and stage the lift around the buildings.

For questions or concerns please contact the Work Control Center at 541-346-2319.

Lillis Roofing Project 6/18 – 9/21

Facilities Liaisons,

The roof project at Lillis Business Complex has started and will run through September 21, 2019. There will be increased contractor activity limiting building entry access on the north side of the building due to overhead work. Please expect noise associated with roofing activities.

For questions or concerns, please contact CPFM Design and Construction Project Manager Tim Allenbaugh at 541-346-8214.

Klamath Hall Pedestrian Walkway Closures 6/24 – 7/26

Facilities Liaisons,

Over the coming weeks, the Klamath renovation contractor will be building steel platforms on and at the edges of the rooftop. As the platforms progress around the rooftop sections of pedestrian walkways below will be closed for pedestrian safety. Please be aware of changing signage and barricades as overhead work progresses around the rooftop perimeter. Work will be performed by Lease Crutcher Lewis.

For questions or concerns please contact CPFM Design and Construction Owners Rep Denise Stewart 541-335-1258.

Utility Connections Related to the Black Cultural Center Project Impacting Areas Along 15th Ave 6/18 – 6/22

Campus Community,

As part of the Black Cultural Center project, Andersen Construction will perform underground utility connections from Moss Street east along 15th Ave to the Black Cultural Center construction site. The work will occur between June 18 – 22 from 7:00 AM – 5:30 PM.

The north end of Villard Alley at 15th Ave will be closed from June 18 – 22. Deliveries or access should be rerouted from 17th Ave. The northern end of Moss Street at 15th Ave will be closed from June 19 – 22. Deliveries or access should be rerouted from 17th Ave. The sidewalk on 15th Ave between Moss Street and Villard Street will be closed. Pedestrian traffic will be rerouted to the north sidewalk.

For questions or concerns please contact CPFM Design and Construction Owners Rep Martina Oxoby at 541-346-5880

 

Sidewalk and Building Entrance Closure at Berwick Hall 6/10 – 6/12

Campus Community,

From June 10- June 12, Lease Crutcher Lewis will be pressure washing the wood facade at Berwick Hall between the hours of 7:00AM and 3:30PM. Sidewalks around the building will be temporarily blocked. The north exit out of Berwick Hall will be closed for about 1-2 hours in the early mornings while working near the exit. The noise impact will be equivalent to a lawnmower.

For questions or concerns please contact CPFM Design and Construction Owners Rep Martina Oxoby at 541-346-5880

Parking Lot 12B Space Closures 6/18 – 7/26

Facilities Liaisons,

Parking lot 12B, north of Klamath Hall, will be impacted by exterior work related to the Klamath 3rd floor renovation. Transportation Services will contact users of parking stalls 28, 29 & 30 and assign a new stall for the duration. An accessible route will be maintained from the lot. Please see below map showing work areas and the accessible route.

For questions or concerns please contact CPFM Design and Construction Owners Rep Denise Stewart at 541-335-1258.

 

Lawrence Hall East Entry Closure 4/3

Facilities Liaisons,

The East entry to Lawrence Hall will be temporarily re-routed while Terra Firma Foundation Systems is on site making necessary sidewalk repairs. The East entry will remain accessible for emergency egress only. Please see below diagram for the work area. Use caution in the yellow area. There will also be intermitted low-level noise during this work.

For questions or concerns please contact CPFM Facilities Services Landscape Supervisor Phil Carroll at 541-246-0031.

Huestis Hall North Access Control System Offline through 4/12

Facilities Liaisons,

The network module in the AMAG panel has failed, the northwest and northeast access control system at Huestis Hall will offline for repairs through April 12, 2019.  This means that occupants requiring after hour access will need to use the south exterior or the north exterior (next to Streisnger (George) Hall).
For questions or concerns, please contact CPFM Work Control Center at 541-346-2319.

Campus Bark Blowing Advisory over Spring Break

Facilities Liaisons,

Lane Forest Products will be on campus March 27 – 28 spreading bark. Please expect noise from bark blowing trucks and temporary obstructions in designated areas. Crews will be working from 8:00 am – 3:00 pm both days.

Impacted Areas:

Deady

Jaqua Academic Center

Knight Library

Knight Law

Lokey Education

For questions or concerns please contact CPFM Landscape Supervisor Phil Carroll at 541-246-0031.

Black Cultural Center Utility Service Work Impacting Pedestrian Traffic 3/25 – 3/28

Campus Community,

As part of ongoing utility service work for the Black Cultural Center project, the fence line will be changing on the west and north ends of the project site.

The fence line on Villard Alley has been shifted to accommodate construction vehicle access points.

The sidewalk on 15th in front of the project will be closed starting Monday 3/25 and reopened on Thursday, 3/28 to allow for a new domestic water vault to be excavated and installed at the NE corner of the site. Pedestrian traffic will be routed to the north side of E 15th Ave.

For questions or concerns please contact CPFM Design and Construction Owners Rep Martina Oxoby at 541-346-5880.

 

UO BCC Site Logistics Plan Updated 3.5.19-SpringBreak-1ew6ccs

Johnson Hall ADA Ramp Closure 3/23 – 3/31

Facilities Liaisons,

As part of the Tykeson Hall construction project, Fortis Construction will be repaving the sidewalk and ADA ramp from 13th Ave to the west entrance of Johnson Hall. ADA access will NOT be available during Spring Break, from March 23 – March 31. For ADA access to Johnson Hall, please call VPFA Office Staff at 541-346-3003. Additional site work will also be completed during this time. All thru-way pedestrian and bike traffic will be rerouted to the east side of Johnson Hall.

Sequence of work:
Saturday 3/23
Relocate site fence to incorporate sidewalks on north and east
Start Demo
Monday 3/25 – Friday 3/29
Demo sidewalks
Excavate for walks and Johnson rain drain
Install drain connections, backfill
Prep, form and pour sidewalks
Strip forms, tune up grading at walks
Saturday 3/30 – Sunday 3/31
Return fence to the original location on the east site boundary
Fence on 13th to remain in place, incorporating 13th sidewalk thru 5/31/19

General Project Questions: Martina Oxboy 541-346-5880

ADA Access: VPA Office Staff 541-346-3003

Johnson Hall ADA ramp (1)-2cybg63

Construction Closure Notification for the University Health, Counseling, and Testing Center

Campus Community,

Beginning Monday, 12/17/18, the north entrance will be closed to the University Health Center, University Counseling Center and Testing Center due to the construction of the new three-story addition. The south entrance to the building will serve as the main entrance during the remainder of the construction project. We are scheduled to have the north entrance open by October 2019.

Over Winter Break, the project will be removing the concrete curb that supported the information kiosk on 13th Avenue and patching with asphalt. There will also be some utility connections on 13th Avenue. LCL will keep the road open to traffic during these activities.

For questions please contact CPFM Design and Construction Manager Patrick Mucker at 541-346-8216.

Chiles 328 Renovation Work 12/10 – 1/4

Building Occupants,

Preferred Construction and their sub-contractors will be doing renovation work in the Chiles 326 computer lab from 12/10 to 1/4. It will involve building three new rooms in the existing space. Work will include demo, framing, drywall, painting, electrical and mechanical work. Users can expect to hear normal and occasional construction noises such as hammering and drilling and may smell at times water-based latex, non-toxic paint. Occupants will see the general contractor and their subs entering/exiting the building with tools and materials during regular business hours.

At times users may expect longer wait times at the elevator as items are loaded/unloaded in the elevator during the course of work. No utility disruptions or shutdowns are scheduled at this time.

For questions or concerns please contact CPFM Design and Construction Project Manager Theo Davis at 541-346-1012.

HEDCO 170 Renovation Work 12/10 – 1/4

Building Occupants,

The General Contractor, Lease Crutcher Lewis, and their sub contractors will be doing light renovation work in the HEDCO suite 170 from 12/10 to 1/4. It will involve building new walls in the existing space. Work will include setting up temporary dust barriers, minor demo, framing, drywall, painting, and electrical work. Users can expect to hear normal and occasional construction noises such as hammering and drilling and may smell at times water-based latex, non-toxic paint. They will see the general contractor and their subs working and entering/exiting the building with tools and materials during regular business hours. No utility disruptions or shutdowns are expected at this time.

For questions or concerns please contact CPFM Design and Construction Project Manager Theo Davis at 541-346-1012

Knight Library Commons Area Renovation Work 12/10 – 1/4

Building Occupants,

CPFM Facilities Services, Scofield Electric, and Knight Library personnel will be doing renovation work in the Library Commons area on the main floor from 12/10 to 1/4. It will involve replacing the existing lighting with new units, demoing select built-ins, and replacing furniture. There will also be some drywall work and painting. Users can expect to hear normal and occasional construction noises such as hammering and drilling and may smell at times water-based latex, non-toxic paint. Occupants will see contractor and UO personnel entering/exiting the building with tools and materials during regular business hours. UO night crew tradespersons will also be in the building after hours. No utility disruptions or shutdownsare expected at this time.

For questions or concerns please contact CPFM Design and Construction Project Manager Theo Davis at 541-346-1012.

Student Recreation Center Exterior Stucco Repair 12/10 – 12/14

Building Occupants,

During the week of December 10-14, contractors will be repairing the stucco on the east side of the Student Recreation Center. Pedestrian access may be affected but will remain open between the Student Recreation Center and 15th Ave.

For questions or concerns please contact CPFM Design and Construction Project Manager Martina Oxoby at 541-346-5880.

Volcanology North Entrance Closure 10/31 – 11/1

Building Occupants,

As part of the Volcanology Project, the North Entrance and North Stairwell will be temporarily closed October 31 – November 1 to allow Electricians to replace light fixtures in the North Stairwell. The other three entrances will remain open. Please use the East ADA ramp, South Main Entrance or the West Main Entrance.

For questions or concerns please contact CPFM Project Manager Bruce Budzik at bbbudzik@uoregon.edu or 541-3466-8834.

UO Tykeson Hall Tower Crane Dismantle Logistics Plan Nov. 5 – 6

Campus Community,

On November 5 and 6 the Tower Crane at Tykeson Hall will be dismantled onto trucks into Johnson Lane south of Tykeson at the entrance to parking lot 25. Access to the parking lot and JSMA loading dock will be maintained, however, expect delays.

For questions or concerns please contact CPFM Design and Construction Project Manager Martina Oxoby moxoby@uoregon.edu at 541-346-5880.

 

 

EUGfun! Event Closes Kincaid and 13th Ave to Alder Street Impacting Traffic, LTD and Parking

Campus Community,

Due to EUGfun! Kincaid will be closed as well as 13th Ave to Alder. The South Kincaid LTD station will be relocated to 14th Ave, and North Kincaid station will be relocated to 12th Ave. LTD will put signage out indicating the temporary relocation. Parking along Kincaid and 13th Ave will be temporarily closed.

This event is encouraging the community to use public transportation Friday, October 12 due to street and parking closures.

For questions please contact Larissa Ennis, UO Assistant Director, Community Relations 541-346-2054 or email lennis@uoregon.edu

ROTC Practice McArthur Court 10/11

Building Occupants, 

ROTC Cadets will be practicing at McArthur Court East facing basement entries on October 11, 2018 from 1:30 pm – 6:00 pm.. Please expect increased activity in this area.

For questions or concerns, please contact CPFM Facilities Services Associate Director Jim Cody at 541-346-2302