4/11/24 – 9/27/24 Hamilton MV Electrical Infrastructure Project (MNCH Parking Lot #34A and East Lawn Area) Advisory

Begin:  Thursday, April 11, 2024

End:      Friday, September 27, 2024

Building(s) or Area(s) Affected:  Knight Law, Museum of Natural and Cultural History, Global Scholars, the Longhouse, and the East Lawn

Scope:  Starting 4/11/24, EC Electric will begin mobilizing onsite, kicking off an electrical infrastructure project for Hamilton Hall to bring increased electrical redundancy and safety to the buildings in the area. Work will be taking place within (and will be taking over, sequentially) the Knight Law parking lot, and the East Lawn area – see attached site/traffic plan for a visual perspective. The project will begin with a first phase of groundwork occurring in the Knight Law MNCH parking lot #34A, with work taking place until June, during which time the parking lot will be offline (with the exception of ADA spaces – they will remain in use). Work will then pause during June, due to several conflicts in the area, and pick back up in July with excavation work in the East Lawn area. During this portion of work the lawn will potentially be closed to use until September. We are aware this is a high use area and accordingly the work within it will be expedited as much as possible. Note this sequencing is subject to change, as well as the timing, due to many competing considerations in the area and available timing to work around them. Any changes will be communicated as they arise.

Be advised, during the parking lot work there will be periods of loud noise and vibration. The most intrusive (shoring and pile driving) is intended to be performed, as much as possible, during off hours to minimize impacts. The second phase will be less impactful, with much less noise and vibration, but will affect pedestrian travel as a large area will be blocked off the work.

Affected building managers have been notified, and consulted with, towards how best to move through the project with the least disturbances to building occupants, and all available accommodations are being made. However, with such a large-scale project there will be some unavoidable noise, vibration, and general inconveniences, which will be limited as much as possible. There will also be minor electrical shutdowns along the way, but no major effects will be noticed. Any and all outages will be communicated and coordinate well ahead of time.

Thank you in advance for your understanding, as well as for your support of this Campus improvement project.

Work Performed By:  EC Electric, Delta Sand & Gravel, Rexius

ContactDamon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285

Current construction and impacts information can be found on the UO Maps site.

Map of affected areas for the Hamilton Hall Electrical Infrastructure project

Site & Traffic plan 4.2.24

3/13/24 – 4/05/24 Huestis Hall Exterior Work and Move-In Advisory

Begin:  Wednesday, March 13, 2024

End:      Friday, April 5, 2024

Building(s) or Area(s) Affected:  Huestis Hall and surrounding area

Scope:  The Huestis Hall Deferred Maintenance Project is nearing final completion and the following is a list of upcoming work and impacts around the building:

  • March 13 – Mulching around the south and east
  • March 21 – Construction fencing will be removed on the south and east sides of Huestis Hall.
  • March 22 – April 5 – Construction fencing will remain in place around the Streisinger courtyard to allow for the following site activities:
    • The Coast Redwood tree removal. The growth habit of this tree species in the location poses a risk to infrastructure, property, and life.
    • Replanting, mulching, and landscape repairs in the courtyard and west walkway between Huestis and Willamette Halls.
  • March 25 – Construction trailer will be removed from the site on E. 13th Ave.
  • April 1 – 30 – Occupant move in activities
  • May TBD – Exterior art work installation on the exterior brick of the south stair tower

I appreciate the patience and collaboration from all of our campus partners over the last 2 years! Thank you!!

Services Impacted:  This will affect parking, roadways, and sidewalks in the area.  Noise can also be expected from the activities listed above.

Work Performed By:  Lease Crutcher Lewis and Rexius

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

Image of Huestis Hall and surrounding area

6/23/23 North Lawn of Collier House Emergency Tree Removal

Begin:  Friday, June 23, 2023 – effective immediately

End:      Friday, June 23, 2023

Building(s) or Area(s) Affected:  North Lawn of Collier House

Scope:  For safety reasons, a mature Sitka Spruce needs to be removed immediately due to decay affecting over half the tree.

Services Impacted:  Access in the area will be affected while the tree is being removed.

Work Performed By:  CPFM Facilities

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of tree location by Collier House 6-23-23

6/09/23 – 9/30/23 Streisinger Hall and Parking Lot 12B East Science Loop Project

2nd UPDATE 9/28/23:
It is expected that the tar odors may be noticed around Klamath Hall, and possibly Onyx Bridge, tomorrow.

 

UPDATE 9/28/23:
The East Science Loop civil contractor will be paving the parking lot on the north side of the Streisinger building (see picture for specifics), weather depending. This is scheduled for Friday, September 29th from 7:00 am to 12:0 noon.  During this work the adjacent areas will be experiencing heavy vehicle traffic as the work is being performed, and due to this spaces might be blocked temporarily. Additionally, some paving odors will be present during the work as well.

If this work does not take place due to weather, the notice will be updated with future times/dates to be aware of.

Thank you for your understanding.

Diagram of Streisinger Lot Paving Project for 9-29-23

 

UPDATE 7/11/23:
The crane/closure dates have now been shifted, due to crane availability, to Friday, July 21st, and Wednesday, July 26th.  The third date is yet to be determined.

 

UPDATE to 6/30/23 Lab Waste Shutdown Entry (7/05/23):
After speaking with the building users regarding lab waste schedules, we are rescheduling the lab waste piping connection shutdown to Friday, July 7th, and Monday, July 10th.

 

UPDATE 7/05/23:
As part of vault deliveries for the East Loop Electrical project, the parking lot area shown will be closed and also the associated loading dock will be down for the duration of the crane work on Monday, July 17th Friday, July 21st, at 7:00 am through Tuesday, July 18th, until 6:00 pm.  Please take this into consideration for your activities, and reach out should this activity limit critical operations/needs.  This will be the first of 3 such closures, with the next potentially occurring 7/25 7/26 and 8/2 TBD. We will update this notice each time to ensure we are working around your needs as we are able.

Image of parking lot for Streisinger and Klamath

 

UPDATE 6/30/23:
Due to work needed to move the East Loop electrical project forward, the lab waste piping will be shut down for up to a days’ time to make the necessary connections to improve the system. This will affect Streisinger, Klamath, and Onyx Bridge.  Be advised that during this time, all lab waste drains will be unable to be used (eg: sink drains).  We are intending to perform this work on Tuesday, July 11th, Friday, July 7th, and Monday, July 10th, from 7:00 am to 5:00 pm.    Please let us know if that day presents a conflict in regard to your operations.  If not, we will update this work as confirmed.

 

UPDATE:
The arborist notified us that due to a change in his schedule, the tree work will take place tomorrow.

 

Begin:  Monday, June 12, 2023

End:      Saturday, September 30, 2023

Building(s) or Area(s) Affected:  Streisinger Hall, East end of Parking Lot 12B

Scope:  Beginning next week, the East Science Loop civil contractor will be kicking off ground work for the project. This will include demolition in the project area, including asphalt removal, tree/planting removal, and earthwork.

Services Impacted:

  • Please be aware associated noises and vibrations are to be expected.
  • The adjacent loading dock will be functional throughout.
  • Pedestrian rerouting (e.g.: not through the parking lot area) will be present for the life of the project. (See picture for details.)
  • No disruptions to services (not previously discussed) are expected.

Work Performed By:  Wildish Construction

ContactDamon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285

Current construction and impacts information can be found on the UO Maps site.

Diagram of Streisinger and Lot 12B

3/09/23 – 3/24/23 – 1744 Moss Street Landscape Activities

UPDATE:
The completion date has been extended to next Friday, March 24.

 

Begin:  Thursday, March 9, 2023

End:      Friday, March 17  24, 2023

Building(s) or Area(s) Affected:  1744 Moss Street and nearby lot

Scope:  Landscape and tree work are taking place in this area, including sidewalk planters directly in front of the building.

Services Impacted:

  • This will periodically affect vehicle traffic on Moss St Alley and the driveway of 1744 Moss Street as debris is hauled away.
  • Noise related to this activity can be expected during this time.

Work Performed By:  Lucan Landscape

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

3/01/23 Riverfront Parkway Northbound Lane Closure Advisory

Begin:  Wednesday, March 1, 2023 – effective immediately

End:      Wednesday, March 1, 2023 – end of day

Building(s) or Area(s) Affected:  Riverfront Parkway

Scope:  The northbound lane of Riverfront Parkway has been closed by EWEB for tree trimming activities.  We were not notified that this event was going to take place.  This activity is not associated with the Knight Campus 2 project.

Services Impacted:  Northbound lane has been closed.  Flaggers are on site.

Special Instructions:  The Millrace Garage, Innovation Center, and 1600 Millrace can be accessed via Moss St., Villard St., or Walnut St. (see diagram below).

Work Performed By:  EWEB

Work Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

1/25/23 – 1/27/23 Fine Arts Metalsmithing, Jewelry, and Woodshop Service Alley Closure

Begin:  Wednesday, January 25, 2023

End:      Friday, January 27, 2023

Building(s) or Area(s) Affected:  Woodshop and Fine Arts Metalsmithing & Jewelry buildings

Scope:  Due to tree relocation work, the service alley between the Woodshop and Fine Arts Metalsmithing & Jewelry buildings will be closed. Trees will be relocated to and planted at the Urban Farm Riverside site.

Services Impacted:  This will affect access to the service alley between Woodshop and Fine Arts Metalsmithing & Jewelry buildings – see attached logistics plan

Work Performed By:  Hoffman Construction

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

Current construction and impacts information can be found on the UO Maps site.

Tree Relocation Closure

10/13/22 East 13th Avenue Emergency Tree Branch Removal and Access Advisory

UPDATE:
The tree work has been completed.

 

Begin:  Thursday, October 13th, 2022 – effective immediately

End:      Thursday, October 13th, 2022 – unknown

Building(s) or Area(s) Affected:  East 13th Avenue in front of Chapman Hall

Scope:  A large overhanging branch was hit by a delivery truck and needs to be removed immediately. The area will be cordoned off.

Services Impacted:  This affects pedestrian traffic in the Street Faire area.  Work is expected to be finished within a couple of hours.

Work Performed By:  CPFM Landscape Crew

ContactRosalee Clanton, CPFM Landscape Maint Supervisor, 760-445-7302

To view current construction and impacts, visit UO Map.

Gerlinger Hall/Gerlinger Annex Tree Work Advisory 3/30/22 – 4/06/22

Begin:  Wednesday, March 30th, 2022 at 7:00 am

End:      Wednesday, April 6th, 2022 at 2:00 pm

Building(s) or Area(s) Impacted:  Area near Gerlinger Hall and Gerlinger Annex

Scope:  There is some deadwood above the sidewalk on the north side of Gerlinger and in the birch trees in Gerlinger Plaza that need to be addressed.

Services Impacted:

  • Sidewalk will remain open with intermittent closures for overhead hazards.
  • Grounds crew will have traffic control in place to assist safe passage around the lift and work area.
  • Expect to hear the occasional loud noise from chainsaw usage.

Work Performed By:  CPFM Landscape Crew

ContactBecket DeChant, CPFM Facilities Services, 541-346-1527

Road Access and Parking Between ZIRC and Millrace Studios 3/7-3/11

UPDATE 3/3: The affected area has been extended to include the blue area in the diagram below.

Begin:  March 7, 2022 at 6:00 am

End:      March 11, 2022 at 4:00 pm

Building(s) or Area(s) Impacted:  Road between ZIRC and Millrace studios

Scope:  The service road between ZIRC and the Millrace Studios will be closed for one week to install a new building utility connection to ZIRC and remove the 3 western red cedars on the south side of the ZIRC building. Parking north of ZIRC can be accessed via Riverfront Parkway during this period.

Services Impacted:  Road access and parking between ZIRC and Millrace studios

Work Performed By: Fortis Construction

Contact: Colin Brennan, CPFM Owner’s Representative, 541-346-8242 or 541-654-2972

 

Lot 16A Tree Pruning and Parking Space Advisory 12/20/21 – 12/21/21

Begin:  Monday, December 20th, 2021

End:      Tuesday, December 21st, 2021

Building(s) or Area(s) Impacted:  Lot 16A (West of Condon and PLC)

Scope:  LJ Tree Service will be pruning a tree on a property north of Lot 16A.

Services Impacted:  Spaces 84-86 will be reserved to facilitate that work, however, temporary Service Vehicle spaces will be provided.

Work Performed By:  LJ Tree Service

ContactJames McGladrey, UO Transportation Services Field Operations Manager, 541-346-2676

Franklin Blvd and E. 18th Tree Pruning Plus Parking and Fire Lane Access Advisory 8/10/21 – 8/11/21

Begin:  Tuesday, August 10th, 2021

End:      Wednesday, August 11th, 2021

Building(s) or Area(s) Impacted:  1205, 1307, 1333 Franklin Blvd., 901 E 18th Ave.

Scope:  Trees will be pruned along Franklin Blvd. near Lawrence Hall and on East 18th Avenue by Clinical Services.

Services Impacted:  Flaggers will be on the road for the duration of the work.

Extra Notes:  The crew will be placing necessary parking signs a day in advance

Work Performed By:  Wright Tree Service

ContactJames McGladrey, UO Transportation Services Field Operations Manager, 541-346-2676

Tykeson Hall and Chapman Hall Lawn Renovation Advisory 3/29/21 – 7/30/21

UPDATE 7/28/21:

The fencing will remain in place through August.

 

UPDATE 7/15/21:

The fencing will remain in place until the end of July. Work is expected to be complete by July 30th.

 

UPDATE 7/7/21:

The work is still ongoing and is expected to be complete on July 23rd, 2021.

 

2nd UPDATE 5/25/21:

Concrete Work Advisory extended to 6/07/21

Due to the recent wet weather conditions, the concrete pour was delayed.  Therefore, the west entry to Tykeson will remained blocked until Tuesday, June 1.  The  construction fence will remain in place and block the west entry. This will allow for adequate cure time on the newly poured concrete.

The remainder of the concrete flatwork pavement will be poured on June 6 and 7. The west end of Johnson Lane will be blocked during these days for the concrete trucks.

 

UPDATE 5/5/21:

Concrete Work Advisory 5/17/21 – 5/28/21 6/7/21 7/23/21 7/30/21 8/31/21

Scope:  As part of the Tykeson Lawn Renovation Project, Delta Construction will be removing and pouring concrete panels outside Tykeson Hall’s west entry.

Services Impacted:  The construction fence will be moved to block access to the west entry/exit of Tykeson Hall and close the seating area under the west canopy.

Special Instructions:  See diagram below for the area involved.

Work Performed By:  Delta Construction

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

 

 

Original Notice

Begin:  Monday, March 29th, 2021

End:      Wednesday, June 30th, 2021

Building(s) or Area(s) Impacted:  Lawn between Tykeson Hall and Chapman Hall

Scope:  Fortis Construction will begin work on site next week for the renovation of the lawn area between Tykeson Hall and Chapman Hall. This exterior project will close access to the lawn until completion at the end of June. The project includes new hardscape pathways and landscape mounds with seat walls.

Services Impacted:

  • Building entries and access to Chapman and Tykeson Halls will be maintained and not impacted.
  • Typical construction activities and noises, including the sound of beeping from vehicles backing up, is to be expected in and around the landscape and hardscape areas.

Work Performed By:  Fortis Construction

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Matthew Knight Arena East Sidewalk and Parking Lane Closure 10/26/20 – 11/6/20

Begin:  Monday, October 26th, 2020

End:      Friday, November 6th, 2020

Building(s) or Area(s) Impacted:  Matthew Knight Arena Sidewalk on East Side

Scope:  The sidewalk and parking lane will be closed to replace the existing sidewalk and trees in the area highlighted in red.

Services Impacted:  Sidewalk and parking lane alongside Matthew Knight Arena

Special Instructions:  Please use the sidewalk on the east side of Villard Street.

Work Performed By:   Fortis Construction

Contact:  Work Control Center, Campus Planning and Facilities Management, 346-2319

Columbia Street and Alley Routine Power Line Clearance Pruning 9/14/20 – 9/25/20

Begin:  Monday, September 14th, 2020

End:      Friday, September 25th, 2020

Building(s) or Area(s) Impacted:  Columbia Street and Alley between E 16th Ave and E 19th Ave

Scope:  EWEB will have tree crews out pruning several different University properties in the upcoming weeks. They will be starting in the alley behind 1650 Columbia St. (Olum Child Development Center) and working Columbia Alley south to E 19th Ave.

Services Impacted:

  • Access along Columbia St and Columbia Alley.
  • This work shouldn’t cause any issues for current UO construction projects.

Work Performed By:   West Lane Tree Service for EWEB

ContactJosh Larson, EWEB Forester, 541-913-0734

Klamath Hall Natural Gas Shutdown 12/16/19

Begin:   December 16, 2019 at 7:00 am

End:     December 16, 2019 at 3:30 pm

Scope:  Contractors need to safely remove a tree stump next to the Natural Gas meter and building connection. Natural Gas will be shutoff for the duration of the tree work.

Building Impacted:  Klamath Hall

Services Impacted:  Natural gas

Contact:  Denise Stewart, Owner’s Representative, 541-346-2280 or 541-335-1258

Huestis Hall Exterior & Window Washing 11/2/19-11/3/19

On Saturday, November 2nd, at 10:00 am through Sunday, November 3rd, at 5:00 pm the exterior of the building and the exterior windows will be washed at Huestis Hall. Due to the use of a lift, the walkways will be partially blocked, but will not interfere with ADA entrances.

There will possibly be exhaust from the power washer; U of O Facilities Services will work with the contractor to minimize this by positioning the power washer away from building air intakes

Please close all exterior windows on these dates.

Work will be performed by DDJ.

For questions or concerns please contact Kevin Farthing at kfarthin@uoregon.edu or 541-346-2857.

15th Avenue Tree Planting 10/18/19 – 10/23/19

Trees will be planted along both sides of 15th Avenue, beginning on the North end of the SRC to the Western edge of Hayward Field.  Prep work will start Friday, October 18th, with the tree planting scheduled to begin Monday, October 21st, for approximately three days.

Cones and yellow ropes will be set up to establish a perimeter around the work zone.  Access to the buildings should not be impeded, and there will be spotters to ensure pedestrian safety.

For questions or concerns, please contact Work Control Center at 346-2319 or workcontrolcenter@uoregon.edu.

Message to Campus Partners Regarding Landscape Protection 9/18/19

All Vehicle Users,

With the fall rains beginning to soften the earth, I’d like to take a moment to remind you that the campus landscape is a valuable asset to the University, one that is worth protecting just as any of our facilities are. A few simple guidelines will help protect our trees, lawns, and plantings for the enjoyment and education of our students and campus visitors alike.

Tips  Did you Know?
Follow driving guidelines Driving, and parking on lawns and landscape beds is permitted only with the approval of Campus Planning and Facilities Management.  Yes, even golf carts!
Use the EMU Scheduling Office
for your outdoor event
They will be able to assist you to make your event successful and avoid damaging practices like driving stakes into the ground and tying ropes to campus plants or fixtures
Contact Facilities Services Landscape Team for advice We are here to support campus activities as best we can, offering advice and guidance on landscape preservation and project planning to minimize your landscape repair costs

Thank you for helping to keep the campus beautiful.

Contact:  Phil Carroll

For questions or concerns please contact Landscape Supervisor Phil Carroll 541-246-0031.

Tree Removal Notice 12/20

Campus Community,

On 12/20 Sperry Tree Care will be onsite removing an incense cedar tree. This will impact sidewalk access to the paths between Deady Hall and the west side of the old quad.

The incense cedar has unfortunately developed a considerable amount of decay behind some robust carpenter ant activity in the base of the tree. Its crown structure and live trunk are balanced upon a decreasing amount of sound wood and the tree’s proximity to frequently occupied sidewalks, benches necessitate its removal to protect life and property. This venerable veteran of North Campus has contributed positively to the atmosphere and ecology of the area for many decades and shall be missed by the University Community.

Please contact Phillip Carroll University of Oregon Landscape Maintenance Supervisor with any Questions or concerns concerning this process pcarroll@uoregon.edu

 

[1715 FRANKLIN] LANDSCAPE WORK 7/10 – 7/27 IN PREPARATION OF SUMMER PAINTING 8/1 – 8/31

Landscape Activities

Beginning July 10th, 2018 through July 27th, 2018 there will be trimming of shrubs and trees along the exterior of the building, including the bike cage and dumpster areas. There may be additional noise when work is in progress.

Painting & Power Washing Activities

The owners have contracted with Gary Pierce Painting to have the entire exterior of the building power washed and painted. Work is anticipated to begin on August 1, 2018, and be completed on or near August 31, 2018. Starting August 1st, Gary Pierce Painting will power wash the entire exterior building. Power washing will be completed in sections. After the power washing is completed, the painting will begin and also completed in sections. A lift will be on-site and used to complete this project.

Please note the following:

-There will be additional noise
-There may be odors
-Parking will be affected. Sections of parking in the row closest to the building will be blocked off  throughout the duration of this project.

Please use caution as you enter and exit the building. Also, please watch for equipment and folks that are working on this project.

Please report any water leaks from power washing immediately.


For questions or concerns please contact CPFM Real Estate Property Coordinator and Lease Management Melinda Seeley at 541-346-5550.

Date Change due to Weather: [SRC, STRAUB, LLC] Sidewalk Closure and Noise 3/1 – 3/2

Due to inclement weather this work has been rescheduled for March 1 – 2, 2018

________________________________________________________________

This notice has been sent to all building users:  SRC, Straub, LLC, Earl, Bowerman and Housing.

Campus Community,

This notice has been extended through February 23, 2018 ending at 12:00 (noon).  The sidewalk will remain closed for the duration of the work.  Please expect noise from the stump grinder between 9:00 am  – 12:00 pm (noon) on the 23rd.   Work will be performed by Long Tom Sawmill.

For questions or concerns please contact CPFM Facilities Services Arborist Becket DeChant at 505-699-7007.

________________________________________________________________________________________________________

 

Campus Users,

On Thursday, February 22nd, from 8:00 am until 2:30 pm, the south side of Straub, SRC, and LLC may be impacted by noise related to the removal of a Norway Maple tree.  Sidewalk access to the Student Rec Center from the east sidewalk on the south side of E. 15th will be closed, and East 15th Avenue will have periodic restrictions by trucks loading debris.

Old injuries to the trunk coupled with irreversible root rot fungus has resulted in the large cavity at the base of this tree. This development, when considered with the weight of the canopy above and the high traffic nature of the site necessitates its removal for pedestrian safety. The site will be re-planted in consultation with campus designers.

Work will be performed by Campus Planning and Facilities Management crews.

For questions or concerns about how this may impact your area, contact Phil Carroll, Campus Planning and Facilities Management (CPFM) Grounds Maintenance Manager at pcarroll@uoregon.edu.

1/22: [Museum of Natural & Cultural History] Tree Removal, Sidewalk and Building Entrance Closure

Building Occupants,

On Monday, January 22, 2018, from 8:00 am – 12:00 pm the Red Alder Tree on the north side of the Museum of Natural & Cultural History (MNCH) will be removed This red alder tree has, unfortunately, been infected by a phytopthera. This disease of plants causes a borderless canker on the trunk and branches that exudes a discharge that is an aesthetic issue for both the building and walkway as well as a contagion issue for other alder trees in the area.  Other alder trees on campus are infected with this disease and will be removed in the near future to attempt to limit the vector’s spread. This is regrettable but necessary.  CPFM will replant the site with a suitable species and consult with MNCH.

During this removal the sidewalk and employee entrance on the north side of the building will be temporarily closed.  There will be noise and congestion associated with this work.

For questions or concerns, please contact CPFM Arborist Becket Dechant at 505-699-700 or CPFM Landscape Supervisor Phill Carroll at 541-246-0031.

1/6/18: Tree Removal by Lot 11 and between [FRIENDLY & COLUMBIA]

Campus Community,

On January 6, 2018, from 8:00 am – 3:00 pm Sperry Tree Care will be on site removing the Oak tree located between Friendly and Columbia.  This tree has been displaying a decline in health and vigor over recent years.  Increasingly, large sections have been dying back and sizable limbs have fallen out during minor weather events.  The University’s arborist has identified several large limbs with substantial decay issues. The tree stands over a major traffic hub for pedestrians and cars parking in the lot adjacent to Friendly hall.  The likelihood of major sections breaking out, possibly targeting the many people who could be passing during inclement weather is troubling and needs to be addressed. We have not anticipated pedestrian closures, and parking lot 11 will remain open but expect possible temporarily delays by the contractor as trucks and equipment come and go from the plaza.   There will also be noise associated with this work.

For questions or concerns please contact CPFM Tree Arborist Becket Dechant or CPFM Landscape Supervisor Phill Carroll.

11/19: Tree Work Along Franklin by Villard

Building Occupants,

On Sunday, November 19, 2017, Sperry Tree Care will be onsite by Villard at the E 11th Ave and Franklin Blvd Merger.   Contractors will be performing tree maintenance on the oak tree that overhangs Franklin Blvd.  The equipment will be staged at Franklin Blvd, and there is a possibility the contractor will need to bring equipment down the sidewalk in front of Deady and Villard.    The city has approved this work, and the contractor has coordinated pedestrian and vehicular traffic control.  Please expect intermittent chainsaw noise associated with this work.

Please contact Becket Dechant 505-699-7007 or Phil Carrol with questions or concerns.