1/12/24 – 3/31/24 Willamette Hall Room 154 Renovation Work Advisory

Begin:  Friday, January 12, 2024, at 8:00 am

End:      Sunday, March 31, 2024, at 4:00 pm

Building(s) or Area(s) Affected:  Willamette Hall room 154

Scope:  Room 154 will undergo renovation and remodeling.

Services Impacted:  Contractors will be present in the building and lobby plus noise and odor can be expected with this type of work.

Work Performed By:  Bridgeway Contracting

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Image of Willamette 154

9/21/23 – 4/30/25 Villard Hall and University Hall “Heritage Project” Fencing and Pathway Advisory

UPDATE:
Revised pedestrian route attached.

Revised pedestrian map 9-20-23

UO Heritage Pedestrian Routes 9.20.23

 

Begin:  Thursday, September 21, 2023

End:      Wednesday, April 30, 2025

Building(s) or Area(s) Affected:  Areas surrounding Villard, University, Lillis, Lawrence, Friendly, and Fenton Halls

Scope:  Due to the renovation of Villard Hall and University Hall, known as the “Heritage Project”, the site around both buildings will fenced off for the duration of the project.

Services Impacted:

  • This will affect the walking routes in the vicinity.
  • Temporary mulch paths with fencing will be installed, and remain for the duration of the project.
  • Walkways are anticipated to be reopened during the Spring of 2025.

Work Performed By:  Fortis Construction

Contacts: Tim Allenbaugh, CPFM Owner’s Representative, 541-346-8214

Gene Mowery, CPFM Owner’s Representative, 541-346-5593

Current construction and impacts information can be found on the UO Maps site.

Image of Heritage Project Fencing Advisory Map 9-21-23 thru 4-30-25

Pages from Site Logistics Plan_Heritage_Phase 3 Rev2 SW Closed

9/22/23 – 9/26/23 Esslinger Hall Room H151, 155, 156, 156A, 157, 161, 163, & 165 Renovation Advisory

UPDATE:
Work has been rescheduled to take place Friday, 9/22, and run through Tuesday, 9/26.

 

BeginSeptember 20,   Friday, September 22, 2023

End:      September 22,    Tuesday, September 26, 2023

Building(s) or Area(s) Affected:  Esslinger Hall H151, 155, 156, 156A, 175, 161, 163, & 165

Scope:  Renovation demolition and abatement will take place in the locations listed above.

Services Impacted:  Construction noise and activity can be expected during this time.

Work Performed By:  IRS Environmental

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Image of Esslinger Hall Room H151, 155, 156, 156A, 157, 161, 163, & 165

6/23/23 – 10/30/23 Heritage Renovation Project Informational Bulletin

UPDATE 10/25/23:
Fortis Construction is fully mobilizing onto the Project site beginning October 30th.  Work activity for the removal for restoration of the University and Villard Hall windows will also commence, as well as interior building demolition within the two buildings and continue for the next few months.

Please contact UO Owner’s Representatives Tim Allenbaugh (541-346-8214) or Gene Mowery (541-346-5593) if you have questions.
NOTICE AND REMINDER 8/08/23:

  • Villard Hall Theatre Arts department move has been completed.
  • Parking Lot 9 is enclosed by construction fencing and no longer open to public access.
  • Villard Hall abatement staging began today and abatement activity will continue into September.
  • Villard Hall is closed and open only to authorized abatement and construction contractors and university personnel.

 

REMINDER 7/17/23:

  • July 17, Fortis Construction began setting up construction fencing and closing off access to Parking Lot 9. Initial construction fencing will enclose Villard Hall as well, limiting access into the building.  Sidewalks/pathways on the north and east sides of Villard will remain open.
  • Villard Hall department moves are scheduled for July 19-21.
  • Villard Hall abatement is scheduled to begin August 7 and will continue into September.
  • Access into University Hall will continue until the end of the second summer class session, August 18. (But parking lot will be offline for vehicles)

 

Begin:  Friday, June 23, 2023

End:      Project Completion Summer 2025

Building(s) or Area(s) Affected:  Villard Hall, University Hall, Parking Lot 9

Scope:  General information for summer activity associated with the Heritage Renovation Project (exterior historic preservation and interior remodel of University and Villard Halls) are outlined as follows:

    • Contractors Fortis Construction and GBC Construction will periodically be in both Villard Hall and University Hall prior to established department move dates for pre-abatement and demolition investigations and activity.  When the department move dates are reached and moves completed, the buildings will be off-line for access without specific approval.  Once abatement starts, the buildings and site will be fully restrictive access.
    • The parking area between University and Villard Halls will remain open until July 16. Beginning July 17, Fortis Construction will begin setting up construction fencing and closing off access to this parking area. Initial construction fencing will enclose Villard Hall as well, limiting access into the building.
    • Villard Hall department moves are scheduled for July 19-21.
    • Villard Hall abatement is scheduled to begin August 7 and will continue into September.
    • Access into University Hall will continue until the end of the second summer class session, August 18. (But parking lot will be offline for vehicles)
    • University Hall: Mathematics department move is scheduled for August 21-23. Construction fencing to enclose University Hall is targeted to begin in this time period as well.
    • University Hall abatement is scheduled to begin September 4 and will continue into October.
    • In conjunction with construction fencing installation, vehicular and pedestrian pathway closure and rerouting signage will be put in place.

Please contact UO Owner’s Representatives Tim Allenbaugh (541-346-8214) or Gene Mowery (541-346-5593) if you have questions.

Current construction and impacts information can be found on the UO Maps site.

 

Image of Villard, University Hall, and Lot 9

6/09/23 – 9/30/23 Streisinger Hall and Parking Lot 12B East Science Loop Project

2nd UPDATE 9/28/23:
It is expected that the tar odors may be noticed around Klamath Hall, and possibly Onyx Bridge, tomorrow.

 

UPDATE 9/28/23:
The East Science Loop civil contractor will be paving the parking lot on the north side of the Streisinger building (see picture for specifics), weather depending. This is scheduled for Friday, September 29th from 7:00 am to 12:0 noon.  During this work the adjacent areas will be experiencing heavy vehicle traffic as the work is being performed, and due to this spaces might be blocked temporarily. Additionally, some paving odors will be present during the work as well.

If this work does not take place due to weather, the notice will be updated with future times/dates to be aware of.

Thank you for your understanding.

Diagram of Streisinger Lot Paving Project for 9-29-23

 

UPDATE 7/11/23:
The crane/closure dates have now been shifted, due to crane availability, to Friday, July 21st, and Wednesday, July 26th.  The third date is yet to be determined.

 

UPDATE to 6/30/23 Lab Waste Shutdown Entry (7/05/23):
After speaking with the building users regarding lab waste schedules, we are rescheduling the lab waste piping connection shutdown to Friday, July 7th, and Monday, July 10th.

 

UPDATE 7/05/23:
As part of vault deliveries for the East Loop Electrical project, the parking lot area shown will be closed and also the associated loading dock will be down for the duration of the crane work on Monday, July 17th Friday, July 21st, at 7:00 am through Tuesday, July 18th, until 6:00 pm.  Please take this into consideration for your activities, and reach out should this activity limit critical operations/needs.  This will be the first of 3 such closures, with the next potentially occurring 7/25 7/26 and 8/2 TBD. We will update this notice each time to ensure we are working around your needs as we are able.

Image of parking lot for Streisinger and Klamath

 

UPDATE 6/30/23:
Due to work needed to move the East Loop electrical project forward, the lab waste piping will be shut down for up to a days’ time to make the necessary connections to improve the system. This will affect Streisinger, Klamath, and Onyx Bridge.  Be advised that during this time, all lab waste drains will be unable to be used (eg: sink drains).  We are intending to perform this work on Tuesday, July 11th, Friday, July 7th, and Monday, July 10th, from 7:00 am to 5:00 pm.    Please let us know if that day presents a conflict in regard to your operations.  If not, we will update this work as confirmed.

 

UPDATE:
The arborist notified us that due to a change in his schedule, the tree work will take place tomorrow.

 

Begin:  Monday, June 12, 2023

End:      Saturday, September 30, 2023

Building(s) or Area(s) Affected:  Streisinger Hall, East end of Parking Lot 12B

Scope:  Beginning next week, the East Science Loop civil contractor will be kicking off ground work for the project. This will include demolition in the project area, including asphalt removal, tree/planting removal, and earthwork.

Services Impacted:

  • Please be aware associated noises and vibrations are to be expected.
  • The adjacent loading dock will be functional throughout.
  • Pedestrian rerouting (e.g.: not through the parking lot area) will be present for the life of the project. (See picture for details.)
  • No disruptions to services (not previously discussed) are expected.

Work Performed By:  Wildish Construction

ContactDamon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285

Current construction and impacts information can be found on the UO Maps site.

Diagram of Streisinger and Lot 12B

8/01/23 – 8/31/23 McKenzie Hall Flooring Access Advisory

Begin:  Tuesday, August 1st, 2023

End:      Thursday, August 31st, 2023

Building(s) or Area(s) Affected:  McKenzie Hall

Scope:  The carpet will be replaced in the hallway areas of the 3rd floor south wing.  Due to asbestos containing materials, removal of existing carpet will require containment and abatement procedures that will prohibit access to the area, including adjoining offices, for the duration of the project.

Services Impacted:

  • Carpet will be replaced in corridors and open areas only:  H301, H375, L338, L328, L318 and L300.
  • The adjoining offices in the area will be inaccessible during the demolition and abatement phase of the project, which is expected to last 2 to 3 weeks. Occupants of these offices will need to make other arrangements for work space during this time.
  • The restrooms and lactation room will also be inaccessible during demolition and abatement.

Work Performed By:  EHS-managed abatement contractor and CPFM Facilities Services personnel

ContactJustin Grishkin, CPFM Construction Services Manager, 541-346-5242

To view current construction and impacts, please visit UO Maps.

2/06/23 – 2/28/23 Prince Lucien Campbell Room 182 Renovation Noise Advisory

Begin:  Monday, February 6, 2023

End:      Tuesday, February 28, 2023

Building(s) or Area(s) Affected:  Prince Lucien Campbell Room 182

Scope:  Intermittent demolition and renovation activities will take place in room 182.

Services Impacted:  Construction noises can be expected during this time.

Work Performed By:  CPFM Facilities

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

1/03/23 – 1/20/23 Knight Library Room 57 Renovation Work and Access Advisory

Begin:  Tuesday, January 3rd, 2023

End:      Friday, January 20th, 2023

Building(s) or Area(s) Affected:  Knight Library Room 57

Scope:  Renovation work is being done in room 57.  A flexible fresh air duct will be run down hall H57 and out the window of room 19 for two days only, January 4th and 5th.  This may cause some ADA access issues. Paint, carpet and other refresh work will follow in room 57

Services Impacted:

  • Access may be affected in Hallway H057 on Wednesday, January 4th, and Thursday, January 5th.
  • Construction noise and odor can be expected in the area.

Work Performed By:  PMG Demolition and CPFM Facilities Services

ContactJanell Cottam, CPFM Owner’s Representative, 541-346-7536

Current construction and impacts information can be found on the UO Maps site.

Lawrence and Pacific Connecting Stairway Closure 3/14/22 – 3/25/22

UPDATE:
Work will now begin the week prior to Spring Break on March 14th .  The completion date is still scheduled for March 25th.

 

Begin:  Monday, March 14 21, 2022

End:      Friday, March 25, 2022

Building(s) or Area(s) Impacted:  Lawrence Hall,  H100

Scope:  During the week of Spring Break, plus the week prior, hallway H100 will be closed in order to make repairs caused by a water leak earlier this winter.

Services Impacted: Access to the three step stairway between Lawrence and Pacific, near room 100, will be shut down.

Work Performed By:  CPFM Facilities Services Crew

ContactKevin Wilson, CPFM FS Construction Field Superintendent, 541-968-4024

Streisinger Hall Drilling Noise Advisory 2/02/22

Begin:  Wednesday, February 2, 2022 at 1:00 pm

End:      Wednesday, February 2, 2022 at 4:00 pm

Building(s) or Area(s) Impacted:  Streisinger Hall Rooms 275A and B

Scope:  Contractor will be drilling concrete in the 2nd floor renovation area.

Services Impacted:  Nearby occupants can expect noise and construction activity during this time.

Work Performed By:  Mortenson Construction

ContactColin Brennan, CPFM Owner’s Representative, 541-346-8242 or 541-654-2972

CPFM Warehouse and Shops (Bldg. 130) Suite 110 Remodel 7/14/21 – 9/17/21

Begin:  Wednesday, July 14th, 2021

End:      Friday, September 17th, 2021

Building(s) or Area(s) Impacted:  CPFM Warehouse and Shops (Bldg. 130) – 110, 110B, 110A and H110A

Scope:  Remodel of Suite 110 including demolition of some existing walls and construction of new walls; modification of electrical circuits, replacement of lighting, carpet and paint throughout.

Services Impacted:  Adjacent occupants can expect to hear typical construction noises for the duration of the project, including cutting, hammering and drilling.

Work Performed By:  UO Facilities Services

ContactJustin Grishkin, CPFM Construction Services Manager, 541-346-5242

McKenzie Hall Storefront Work Advisory 5/17/21 – 5/28/21

UPDATE 5/17/21:

The HVAC system will be shut down while the ground floor level duct dampers are  tested on Thursday, May 20th, between 7:00 and 8:00 am.

 

Original Notice

Begin:  Monday, May 17, 2021

End:   Friday, May 28, 2021

Building Impacted:  McKenzie Hall

Scope:  Replace existing storefront exterior entries at 6 locations on the main and ground levels.  Each location is expected to take 2 days to replace.

Services Impacted:

  • No additional electrical or HVAC disruptions are known at this time.  A shutdown notice will be issued as necessary.
  • Building access will be maintained during construction but may require detours.  The contractor will post signs as necessary.
  • Users can expect to hear construction noises like hammering, drilling, grinding, and see construction personnel and UO staff entering and exiting the building during normal business hours, but also as early as 6

Work performed by:  Ryan Thomas Construction, Culver Glass, and CPFM Facilities Construction Services.

Contact:  Theo Davis, CPFM Design & Construction Project Manager, 541-346-1012

Windows to be replaced in UHCC B0014 on 11/30/2020

Begin:  Monday, November 30, 2020  8:00am

End:      Friday, December 4, 2020  5:00pm

Building Impacted: University Health, Counseling and Testing, B0014

Scope:  Poor performing south facing windows on the 1st floor in Clinic C and E that were not upgraded during the renovation will be replaced. Work activities will generate noise and vibration.

Work Performed By:  Dallas Glass

Contact: Colin Brennan, CPFM Owners Representative at email: brennan@uoregon.edu or phone 541-652-2972

Willamette Hall Classroom #100 Renovation Advisory 6/25/20 – 9/30/20

UPDATE 9/11: This project has been extended to the end of September.

Begin:  Thursday, June 25th, 2020 at 7:00 am

End:      Monday, August 31st, 2020 at 6:00 pm Wednesday, September 30th, 2020

Building(s) or Area(s) Impacted:  Willamette Hall

Scope:  Phase 3 of the Willamette Hall classroom #100 renovation is underway. Work includes construction of a new storage room, demolition, and installation of new flooring.

Services Impacted:  Noise related to this work will be typical.

Extra Notes:  Work will be performed during work hours of 7AM-6PM.

Work Performed By:   Bridgeway Construction

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Onyx Bridge Noise Advisory 6/3/20 – 6/4/20

Begin:  Wednesday, June 3rd, 2020 – current

End:      Thursday, June 4th, 2020 at noon

Building(s) or Area(s) Impacted:  Onyx Bridge

Scope:  Demolition and upfitting in rooms 480, 481, 482.

Services Impacted:  Work involves construction noises including hammering on floors, as well as debris removal using Cascade elevator.

Work Performed By:   CPFM Facilities

ContactWork Control Center, Campus Planning and Facilities Management 346-2319

HEDCO 230S Remodeling Advisory 5/18/20 – 6/18/20

Begin:  Monday, May 18th, 2020

End:      Thursday, June 18th, 2020

Building or Area Impacted:  HEDCO 230S

Scope:  Remodeling work on room 230S will include electrical, ducting, carpentry, glass installation, new carpeting, and painting.

Services Impacted:

  • Users can expect to hear normal and occasional construction noises such as hammering, cutting, and drilling,
  • Installers will be entering/exiting the building with tools and materials during normal business hours.
  • The HVAC is expected to be shut down from May 18th-21st to perform a modification on the existing system.
  • No additional utility/HVAC disruptions or shutoffs are expected at this time for this work.

Special Instructions:  Please shut down all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when power is turned back on, a power surge can corrupt the clone files in the machines, and can change preconfigured settings.

Work Performed By:  Lease Crutcher Lewis and their subcontractors

ContactTheo Davis, CPFM Project Manager, 541-346-1012

LISB Rooms 174 and 175 Renovation Advisory 4/27/20 – 9/11/20

UPDATE 8/31: This project is wrapping up with commissioning and testing and will be complete by September 11.

UPDATE 8/5/20: The project is still underway and the completion date has been extended to 8/31/2020.

Begin:  Monday, April 27th, 2020

End:      Wednesday, August 5th, 2020 Monday, August 31st, 2020 Friday, September 11th, 2020

Building or Areas Impacted:  Lewis Integrative Science Building (LISB) Rooms 174 and 175

Scope:  Demolition will start in rooms 174 and 175 in the LCNI suite for the construction of a new MRI bay.

Services Impacted:

  • Moderate noise may be experienced in rooms 153, 175, 176, 177 & potentially the 2nd floor rooms above the 174 space.
  • Vibration to the structure is not anticipated as a result of this work.

Work Performed By:   GBC Construction

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Cascade Hall Room 100 Renovation Advisory 4/20/2020 – 4/24/2020

Begin:  Monday, April 20th, 2020

End:      Friday, April 24th, 2020

Building or Area Impacted:  Cascade Hall Room 100

Scope:  Renovation work will involve removal of furniture, removal of existing carpet, installation of new carpet, and return of furniture.

Services Impacted:

  • Access to Room 100 will be restricted throughout the duration of the project.
  • Access to staff offices 100A, B, C and D is available from V110 to hallway H100.
  • No utility disruptions or shutoffs are expected at this time; however, if there are any disruptions or shutdowns to services, an additional notice will be provided.

Work Performed By:   UO CPFM Facilities Services

ContactJustin Grishkin, CPFM Construction Services Manager, 541-346-5242

HEDCO 230A Construction Advisory 4/3/20 – 6/12/20

Update 4/16/2020: This project is now expected to be completed on 6/12/2020.

Begin:  Friday, April 3rd, 2020

End:      Friday, May 15th, 2020 June 12th, 2020

Building or Area Impacted:  HEDCO 230A

Scope:  Construction is underway to remodel room 230A.

Services Impacted:

  • Remodeling work includes moving, electrical, ducting, carpentry, new carpet, and painting.
  • No utility/HVAC disruptions or shutoffs are expected at this time for this work.

Extra Notes:  Users can expect to hear normal and occasional construction noises such as hammering and drilling, as well as, the installers entering/exiting the building with tools and materials during normal business hours.

Special Instructions:  Please shut down all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when power is turned back on, a power surge can corrupt the clone files in the machines, and can change preconfigured settings.

Work Performed By:   CPFM Facilities Construction Services

ContactTheo Davis, CPFM Project Manager, 541-346-1012

Postponed – Transportation Services Building Remodeling Advisory 4/6/20 – 5/1/20

UPDATE:  This project has been postponed due to capacity issues related to the university’s response to COVID-19.  We will send a notice when a new date has been established.

 

Begin:   Monday, April 6th, 2020  Postponed

End:       Friday, May 1st, 2020

Building and Areas Impacted:  Transportation Services

  • The majority of the work will occur in rooms 100, 102, 103, 105, 106, 110, 111 and H107, however minor related work may occur in other parts of the building.

Scope:  Remodeling work throughout the Transportation Services building.  This includes moving, demo, carpentry, electrical, HVAC, fire alarms, and paint.

Services Impacted:

  • Users can expect to hear normal and occasional construction noises such as hammering and drilling.
  • Installers entering/exiting the building with tools and materials during normal business hours.
  • No utility/HVAC disruptions or shutoffs are expected at this time for this work.

Special Instructions:  Please shut down all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when power is turned back on, a power surge can corrupt the clone files in the machines, and can change preconfigured settings.

Work Performed By:  Preferred Construction and their subs, along with UO Facilities Construction Services and Information Services staff.

ContactTheo Davis, CPFM Project Manager, 541-346-1012

Knight Library Room 101 Renovation 3/17/20 – 3/27/20

Begin:  Tuesday, March 17th, 2020

End:      Friday, March 27th, 2020

Building or Area Impacted:  Knight Library Room 101

Scope:  Renovation work will involve removal of furniture, removal of existing carpet, installation of new carpet, and return of furniture.

Services Impacted:  Access to the rooms will be restricted throughout the duration of the project.  No utility disruptions or shutoffs are expected at this time; however, if there are any additional disruptions or shutdowns to services, an additional notice will be provided.

Extra Notes:  The work was originally scheduled to begin March 19th but room schedule availability has allowed staff to begin work sooner.

Special Instructions:  Building occupants can expect to see UO Facilities personnel entering/exiting the building with tools and materials during regular business hours. Removal of existing carpet and removal/return of furniture will occur during regular business hours. Installation of new carpet is scheduled to occur at night.

Work Performed By:  UO CPFM Facilities

ContactJustin Grishkin, CPFM Construction Services Manager, 541-346-5242

Klamath Hall Renovation Advisory 2/17/20 – 2/21/20

Begin:  Monday, February 17th, 2020

End:      Friday, February 21st, 2020

Building and Areas Impacted:  Klamath Hall – areas on the third-floor, highlighted on the map/drawings below, will be impacted

Scope:  Flooring and base will be install related to the December water damage.

Services Impacted:  Access, normal noise and congestion associated with renovations.

Special Instructions:  Work will be performed by Lease Crutcher Lewis

ContactJim Cody, CPFM Assoc. Dir of Facilities Services, 541-346-2302

Prince Lucian Campbell Restroom Repair 10/21/19-11/6/19

Update 11/4: This project has been extended and is expected to be completed by 11/6/19.

 

Restroom 801 will be closed from Monday, October 21st, to Monday, November 4th Wednesday, November 6th for repairs. The adjacent all-gender restroom, 803, will still be operational.

Work will be performed by Facilities Services’ Carpentry Shop.

For questions or concerns please contact CPFM Work Control Center 541-346-2319 or workcontrolcenter@uoregon.edu.

Esslinger Abatement Project 8/26/19 – 1/6/2020

Update 11/4:

  • Carpet installation will occur in the entry of L101 on 11/5 and 11/6. Foot traffic will be advised to use the NW entry.
  • A floor scraping machine will be in use between (roughly) 8am and noon on Tuesday 11/5 and (perhaps) 8am-noon on Wednesday 11/7. This machine will be somewhat noisy, but we will make every attempt to close doors to contain noise.
  • Carpet installation will be occurring all week, and there will be odors associated with the carpet glue. EHS will have appropriate MSDS sheets on file.

Update 10/16:

During the abatement process some floor tiles were knocked loose in women’s restroom 113. In order to repair the tiles, the contractor will have to close restroom 113 tomorrow 10/17. While the repairs are being made, all-gender restroom 173 will still be operational as an alternative.

 

On Monday, August 26th, at 7:00 am through Friday, September 6th at 4:00 pm, abatement work will be performed by Belfor Environmental in two phases:

Phase 1 Abatement (see clouded area in 1st diagram) 8/26-8/30:

  • Occupants of these offices have been temporarily moved to allow for work.
  • Access to Esslinger during Phase 1 will be restricted to the northwest lobby L102.
  • REC offices adjacent to H102 can access offices from L102 during Phase 1.

Phase 2 Abatement (see clouded area in 2nd diagram) 9/2-9/6:

  • Access to Esslinger will be through L101.
  • Stairs at L102/ S101 will remain open.
  • REC staff in offices 102, 103A-D, 104, and 104A-B will be able to access their suite though L101 to 102. (Door hardware will be temporarily replaced for access.)
  • Room 106, and restrooms 115/117 will be offline during phase 2.
  • Classrooms 105, 107, 112, and 116 have been taken offline by the registrar for the duration of the abatement project.

 

On Monday, October 14th through Monday, January 6th, 2020, flooring work will be performed by Facilities Services and a number of subcontractors:

Phase 3 Flooring (see highlighted areas in 3rd diagram) 10/14/19-1/6/20:

  • Carpet will be replaced in 170, 172, 174, 175, 176, 177, 179, 180A, 181A, and 181B in phases and is expected to be completed before 11/8/19.
  • Wall and drywall framing work is expected to be completed before 11/15/19.
  • Ceiling work in 180/181 and the perimeter is expected to be completed before 12/1/19.
  • Plumbing work in 171 is expected to be completed before 12/15/19.
  • Resilient flooring is expected to be installed in H102 and H103 before 10/31/19.
  • Resilient flooring is expected to be installed in H101 and H111 before 12/15/19.
  • Carpet will be replaced in 180/181 and is expected to be completed before 12/30/19.
  • The doors, storefront, break room, etc. is expected to be completed before 1/6/20.

For questions or concerns, please contact Tim Allenbaugh at 346-8214 or timallen@uoregon.edu.

 

Knight Library L205, 206, and 206A Renovation Advisory 8/19 – 9/27/19 – UPDATE

UPDATE:

Beginning, Monday, August 19 through September 27, CPFM Construction Services Design and Construction will be renovating Knight Library Special Collections Rooms 205 and 206 L205, 206, and 206A. This work involves demo, electrical, carpentry, paint, new carpet, and furniture. Building users can expect to hear normal and occasional construction noises, such as hammering and drilling; in addition, during the paint portion, occupants may notice a faint smell from the low-VOC, non-toxic paint. Contractors and UO personnel will be entering/exiting the building with tools and materials during normal business hours.

Asbestos abatement is planned for August 21-23. During this time, technicians will turn off HVAC ventilation system as part of normal safety precautions, which will affect portions of Floors 1 and 2, as well as the basement. No other utility disruptions or shutoffs are expected at this time; however, additional notice(s) will be distributed, should any occur.

Preferred Construction will perform this renovation work.

For any questions or concerns, please contact Project Manager Theo Davis at 541-346-1012 or tdavis1@uoregon.edu.

ORIGINAL MESSAGE:

Beginning, Monday, August 19 through September 27, CPFM Construction Services will be renovating Knight Library Special Collections Rooms 205 and 206.  This work involves demo, electrical, carpentry, paint, new carpet, and furniture. Building users can expect to hear normal and occasional construction noises, such as hammering and drilling; in addition, during the paint portion, occupants may notice a faint smell from the low-VOC, non-toxic paint. Contractors and UO personnel will be entering/exiting the building with tools and materials during normal business hours.

Asbestos abatement is planned for August 21-23. During this time, technicians will turn off HVAC ventilation system as part of normal safety precautions, which will affect portions of Floors 1 and 2, as well as the basement. No other utility disruptions or shutoffs are expected at this time; however, additional notice(s) will be distributed, should any occur.

Preferred Construction will perform this renovation work.

For any questions or concerns, please contact Project Manager Theo Davis at 541-346-1012 or tdavis1@uoregon.edu.