Black Cultural Center Construction Mobilization Starts 2/11

Campus Community,

Beginning Monday, February 11, 2019, construction mobilization activities will begin for the construction of the Black Cultural Center at the corner of E 15th Ave and Villard Alley. The current construction schedule is February 2019 through August 2019. Please review the site plan showing construction fencing, construction site access, and the building footprint. The construction team will mobilize on-site and begin installing the site fences and locating underground utilities and other activities to support the construction project. Periodic updates will be provided with more details and updated schedule information.

University Health, Counseling, & Testing Center Construction Crane Activities

Building Occupants,

On Saturday, 1/12/19, there will be a crane delivery at the University Health, Counseling, & Testing Center to support the on-going Expansion & Renovation Project. The crane will be located within the current construction fence per the attached drawing. On Monday, 1/14/19, the project will begin receiving steel deliveries and erecting the steel structure. Steel activities will continue for several weeks. All steel deliveries will enter the construction area before being unloaded. Steel deliveries will cause some minor traffic disruptions to 13th Ave at Beech Street. Lease Crutcher Lewis will manage these activities and use flaggers to assist with deliveries. The south sidewalk of 13th Ave, adjacent to the Health, Counseling, & Testing Center is closed. Pedestrians should observe the signage and use the north sidewalk along 13th Ave. (adjacent to Oregon Hall) and avoid walking in the street along the construction fence.

For questions or concerns please contact CPFM Design and Construction Owners Representative Patrick Mucker at 541-346-8216.

Chiles 328 Renovation Work 12/10 – 1/4

Building Occupants,

Preferred Construction and their sub-contractors will be doing renovation work in the Chiles 326 computer lab from 12/10 to 1/4. It will involve building three new rooms in the existing space. Work will include demo, framing, drywall, painting, electrical and mechanical work. Users can expect to hear normal and occasional construction noises such as hammering and drilling and may smell at times water-based latex, non-toxic paint. Occupants will see the general contractor and their subs entering/exiting the building with tools and materials during regular business hours.

At times users may expect longer wait times at the elevator as items are loaded/unloaded in the elevator during the course of work. No utility disruptions or shutdowns are scheduled at this time.

For questions or concerns please contact CPFM Design and Construction Project Manager Theo Davis at 541-346-1012.

HEDCO 170 Renovation Work 12/10 – 1/4

Building Occupants,

The General Contractor, Lease Crutcher Lewis, and their sub contractors will be doing light renovation work in the HEDCO suite 170 from 12/10 to 1/4. It will involve building new walls in the existing space. Work will include setting up temporary dust barriers, minor demo, framing, drywall, painting, and electrical work. Users can expect to hear normal and occasional construction noises such as hammering and drilling and may smell at times water-based latex, non-toxic paint. They will see the general contractor and their subs working and entering/exiting the building with tools and materials during regular business hours. No utility disruptions or shutdowns are expected at this time.

For questions or concerns please contact CPFM Design and Construction Project Manager Theo Davis at 541-346-1012

Knight Library Commons Area Renovation Work 12/10 – 1/4

Building Occupants,

CPFM Facilities Services, Scofield Electric, and Knight Library personnel will be doing renovation work in the Library Commons area on the main floor from 12/10 to 1/4. It will involve replacing the existing lighting with new units, demoing select built-ins, and replacing furniture. There will also be some drywall work and painting. Users can expect to hear normal and occasional construction noises such as hammering and drilling and may smell at times water-based latex, non-toxic paint. Occupants will see contractor and UO personnel entering/exiting the building with tools and materials during regular business hours. UO night crew tradespersons will also be in the building after hours. No utility disruptions or shutdownsare expected at this time.

For questions or concerns please contact CPFM Design and Construction Project Manager Theo Davis at 541-346-1012.

UO Klamath Hall 3rd Floor Laboratory Renovation Construction Logistics and Construction Notice

Campus Community,

Beginning on December 10th contractors will start mobilizing for construction to renovate the 3rd floor of Klamath Hall. Provided here is the construction logistics plan showing staging in and around the Streisinger Hall loading dock and construction office trailers in the lawn southwest of Streisinger Hall. A couple of key things to note.

1. No staff, faculty or visitor parking will be impacted. Two service vehicle locations at the Streisinger loading dock will be out of service. For a short duration of two months in the summer of 2019, two ADA stalls will be out of service. More details will follow as the summer approaches.

2. The Streisinger loading dock and the west truck bay of the dock will remain accessible for campus use throughout the project. The Streisinger dock and elevator will not be used by or for construction.

3. Construction access to the 3rd floor and rooftop of Klamath will be accessed via a temporary construction hoist/elevator located within construction fencing in the east bay of the Streisinger loading dock. Access will be up and over.

4. Existing exterior pedestrian and bike paths will remain open.

Schedule:

The current construction schedule is December 2018 through September 2020. This December 10th through January 4th contractors will be installing construction fencing, construction office trailers, scaffolding, and the temporary construction hoist/elevator as shown in the provided logistics information within this notice.

A Neighborhood meeting will be held this Wednesday, November 28th at 12 pm in the Visualization Lab of the Price Science Commons & Research Library, Room B006. Please come to hear project information, further construction details and to pose any questions or concerns you have.

For questions or concerns please contact CPFM Design and Construction Project Manager Denise Stewart at 541-335-1258 or email dstewart@uoregon.edu 

 

Temporary Installation of Access Road Requires Stopping Water Flow in Millrace for Vegetation Removal 9/27 – 10/8

The Knight Campus project will be temporarily stopping the water flow in the Millrace in order to install a temporary construction access road. We are currently targeting the first week in October for this shutdown. The shutdown of flow will last approximately one week, at which time it will be returned to normal. The installation of this access road will include the removal of vegetation from the south side of the Millrace between Riverfront Parkway and the previous pedestrian bridge about halfway to Onyx. Please expect congestion and noise in this area.

Actual renovation work to the Millrace will not occur until next summer.

For questions or concerns please email CPFM Design and Construction Project Manager Darin Dehle ddehle@uoregon.edu 

Phil and Penny Knight Campus for Accelerating Scientific Impact

CPFM Building 130 Construction Activities 9/10 – 9/14

Abatement for the future Work Control Center area in CPFM Building 130 will begin on Monday 9/10, and it should be complete by 9/14. The contractors will be using two parking spaces north of the building, one for a dumpster, and one for their equipment van. Please expect increased activity and noise in this area.

For questions or concerns please contact CPFM Design and Construction Project Manager Tim Allenbaugh at 541-346-8214.

Deschutes 207 Construction Notice 9/5 – 9/14

Building Occupants,

CPFM Facilities Services will be doing a minor remodel in Deschutes 207 from 9/5 to 9/14. It will involve minor demo, carpeting, locks, drywall patching, and paint. Users can expect to hear normal and occasional construction noises such as hammering and drilling, and see Facilities Services personnel entering/exiting the building with tools and materials during normal business hours. No utility disruptions or shutoffs are expected at this time.

If there are any problems, please contact CPFM Design and Construction Project Manager Theo Davis, at 541-346-1012.

 

Knight Library TLC 4th Floor Construction Activities Starting 8/10

Building Occupants,

Light mechanical construction work related to the TLC project on the 4th floor of the Library will occur this Friday starting at 8 am and will continue into next week.  Users can expect to see mechanical technicians in and around the 4th-floor area.  There are no known mechanical/electrical shutdowns scheduled at this time.

Please contact CPFM Design and Construction Project Manager Theo Davis at 541-346-1012 with any questions or concerns.

[KNIGHT LAW 384] Building User Notice Construction Activities 8/6 – Early September

Building Occupants,

Light construction activities start this week in Knight Law Library room 384, and it is expected to continue until early September.  The work will involve minor demo, concrete drilling, framing, electrical, and painting.  Most construction activities will occur during the day.  Building users may expect to hear light construction noises and see UO Facilities personnel and external construction workers entering/exiting the building as they bring in materials.  There is one future electrical shutdown disruption known at this time.  The exact days and times will be communicated in advance when finalized.

For questions or concerns please contact CPFM Design and Construction Project Manager Theo Davis at 541-346-1012

8/6 – 8/20: [ALDER 104] Construction Activities

Building Occupants,

Construction will start the week of August 6th and is expected to finish the week of August 20th. This work will involve some moving, light framing, electrical, drywall, and painting. Work will occur during the day. Building users may expect to hear normal light construction noises, and see UO Facilities personnel entering/exiting the building. No shutdown disruptions are expected or known at this time.

If you have any questions or concerns, please contact Design & Construction Project Manager Theo Davis at 541-346-1012.

Bean Hall Project Road Closures July 19, 2018

Campus Community,

There are two street closures for the Bean Hall Project on July 19th.

The first is a closure of 15th street between Bean and Global Scholars Hall from 6 AM to 8 AM. We will shut down the street with flaggers to detour traffic, set up the crane and lift the rooftop units.

The second closure will be Columbia Street between Hamilton Hall and the Alumni Center. We will be closing the parking spots in lot 37 as part of the closure. This closure will be from 6 AM – 3 PM. Access to the Columbia Garage will not be affected.

For questions or concerns please contact CPFM Design and Construction Project Manager George Bleekman 541-346-2625.

Phil and Penny Knight Campus for Accelerating Scientific Impact Construction and Traffic Updates

Construction on the Phil and Penny Knight Campus for Accelerating Scientific Impact is ramping up. You can track progress on a web cam and read traffic updates.

Construction and Traffic Updates: https://accelerate.uoregon.edu/construction-and-traffic-updates

Webcam: https://accelerate.uoregon.edu/construction-webcam

https://accelerate.uoregon.edu/sites/accelerate1.uoregon.edu/files/diagram_a_-_ped_and_bike_0.pdf

https://accelerate.uoregon.edu/sites/accelerate1.uoregon.edu/files/diagram_b_-_pepi_work.pdf