Temporary Installation of Access Road Requires Stopping Water Flow in Millrace for Vegetation Removal 9/27 – 10/8

The Knight Campus project will be temporarily stopping the water flow in the Millrace in order to install a temporary construction access road. We are currently targeting the first week in October for this shutdown. The shutdown of flow will last approximately one week, at which time it will be returned to normal. The installation of this access road will include the removal of vegetation from the south side of the Millrace between Riverfront Parkway and the previous pedestrian bridge about halfway to Onyx. Please expect congestion and noise in this area.

Actual renovation work to the Millrace will not occur until next summer.

For questions or concerns please email CPFM Design and Construction Project Manager Darin Dehle ddehle@uoregon.edu 

Phil and Penny Knight Campus for Accelerating Scientific Impact

CPFM Building 130 Construction Activities 9/10 – 9/14

Abatement for the future Work Control Center area in CPFM Building 130 will begin on Monday 9/10, and it should be complete by 9/14. The contractors will be using two parking spaces north of the building, one for a dumpster, and one for their equipment van. Please expect increased activity and noise in this area.

For questions or concerns please contact CPFM Design and Construction Project Manager Tim Allenbaugh at 541-346-8214.

Deschutes 207 Construction Notice 9/5 – 9/14

Building Occupants,

CPFM Facilities Services will be doing a minor remodel in Deschutes 207 from 9/5 to 9/14. It will involve minor demo, carpeting, locks, drywall patching, and paint. Users can expect to hear normal and occasional construction noises such as hammering and drilling, and see Facilities Services personnel entering/exiting the building with tools and materials during normal business hours. No utility disruptions or shutoffs are expected at this time.

If there are any problems, please contact CPFM Design and Construction Project Manager Theo Davis, at 541-346-1012.

 

Knight Library TLC 4th Floor Construction Activities Starting 8/10

Building Occupants,

Light mechanical construction work related to the TLC project on the 4th floor of the Library will occur this Friday starting at 8 am and will continue into next week.  Users can expect to see mechanical technicians in and around the 4th-floor area.  There are no known mechanical/electrical shutdowns scheduled at this time.

Please contact CPFM Design and Construction Project Manager Theo Davis at 541-346-1012 with any questions or concerns.

[KNIGHT LAW 384] Building User Notice Construction Activities 8/6 – Early September

Building Occupants,

Light construction activities start this week in Knight Law Library room 384, and it is expected to continue until early September.  The work will involve minor demo, concrete drilling, framing, electrical, and painting.  Most construction activities will occur during the day.  Building users may expect to hear light construction noises and see UO Facilities personnel and external construction workers entering/exiting the building as they bring in materials.  There is one future electrical shutdown disruption known at this time.  The exact days and times will be communicated in advance when finalized.

For questions or concerns please contact CPFM Design and Construction Project Manager Theo Davis at 541-346-1012

8/6 – 8/20: [ALDER 104] Construction Activities

Building Occupants,

Construction will start the week of August 6th and is expected to finish the week of August 20th. This work will involve some moving, light framing, electrical, drywall, and painting. Work will occur during the day. Building users may expect to hear normal light construction noises, and see UO Facilities personnel entering/exiting the building. No shutdown disruptions are expected or known at this time.

If you have any questions or concerns, please contact Design & Construction Project Manager Theo Davis at 541-346-1012.

Bean Hall Project Road Closures July 19, 2018

Campus Community,

There are two street closures for the Bean Hall Project on July 19th.

The first is a closure of 15th street between Bean and Global Scholars Hall from 6 AM to 8 AM. We will shut down the street with flaggers to detour traffic, set up the crane and lift the rooftop units.

The second closure will be Columbia Street between Hamilton Hall and the Alumni Center. We will be closing the parking spots in lot 37 as part of the closure. This closure will be from 6 AM – 3 PM. Access to the Columbia Garage will not be affected.

For questions or concerns please contact CPFM Design and Construction Project Manager George Bleekman 541-346-2625.

Phil and Penny Knight Campus for Accelerating Scientific Impact Construction and Traffic Updates

Construction on the Phil and Penny Knight Campus for Accelerating Scientific Impact is ramping up. You can track progress on a web cam and read traffic updates.

Construction and Traffic Updates: https://accelerate.uoregon.edu/construction-and-traffic-updates

Webcam: https://accelerate.uoregon.edu/construction-webcam

https://accelerate.uoregon.edu/sites/accelerate1.uoregon.edu/files/diagram_a_-_ped_and_bike_0.pdf

https://accelerate.uoregon.edu/sites/accelerate1.uoregon.edu/files/diagram_b_-_pepi_work.pdf