2/28/24 – 3/01/24 Onyx Bridge Rooms 361 and 362 Containment and Noise Advisory

Begin:  Wednesday, February 28, 2024, at 8:00 am

End:      Friday, March 1, 2024, at 4:00 pm

Building(s) or Area(s) Affected:  Onyx Bridge Rooms 361 and 362

Scope:  Contractor will perform abatement services to remove Asbestos containing material from Onyx Bridge room 361 and 362.

Services Impacted:

  • Containment will be enclosed to those two rooms only, but containment access will take up to 4′ into the hall wall.
  • Passage is still provided.

Work Performed By:  Rose City Contracting

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Image of Onyx Bridge 361 and 362

12/18/23 – 12/20/23 Columbia Hall 145 and 145A Carpet Abatement Advisory

Begin:  Monday, December 18, 2023

End:      Wednesday, December 20, 2023

Building(s) or Area(s) Affected:  Columbia Hall 145 and 145A

Scope:  Carpet abatement is scheduled to take place in rooms 145 and 145A.  This is part of the second phase of renovations in suites 144 and 145.

Services Impacted:  EHS has contracted with a professional abatement contractor to remove the carpet and mastic in these rooms.

Work Performed By:  AAC Asbestos Abatement Contractor

ContactJanell Cottam, CPFM Owner’s Representative, 541-346-7536

Current construction and impacts information can be found on the UO Maps site.

Image of Columbia Hall rooms 145 and 145A

10/25/23 – 10/31/23 Columbia Hall 144, 144A, and 144B Construction Work and Noise Advisory

Begin:  Wednesday, October 25, 2023, at 7:30 am

End:      Tuesday, October 31, 2023, at 4:00 pm

Building(s) or Area(s) Affected:  Columbia Hall

Scope:  Demolition of a wall and abatement of flooring will take place in rooms 144, 144A and 144B. There may be noise associated with the demolition and abatement.

Services Impacted:  The rooms most likely impacted by the noise are: 246, 247, 248, 249, 143, and 142. We are working with the contractor to limit most noise to early morning prior to classes in 143.

Work Performed By:  Asbestos Abatement Contractor, Gilberto Martinez

ContactJanell Cottam, CPFM Owner’s Representative, 541-346-7536

Current construction and impacts information can be found on the UO Maps site

Image of Columbia Hall rooms 144, 144A, 144B

9/28/23 – 10/02/23 Cascade Hall 305D Flooring Work Advisory

UPDATE 9/29/23:
The end date has been extended to Monday, October 2, 2023, at around 10:00 am.  The contractor was not able to finish the work today and will need to keep up containment until Monday.

 

UPDATE 9/28/23:
Tomorrow, one of the two HVAC units for Cascade Hall will be shut off, affecting the entire building, particularly the southern half.

 

Begin:  Thursday, September 28, 2023, at 8:00 am

End:     September 29, Monday, October 2, 2023, at approximately 10:00 am

Building(s) or Area(s) Affected:  Cascade Hall 305D

Scope:  Demolition and abatement of flooring material will take place in room 305D.

Services Impacted:

  • Construction activity and noise can be expected during this time.
  • HVAC air supply will be offline in room 305D.

Work Performed By:  Rose City Contracting

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Image of Cascade Hall room 305D

6/23/23 – 10/30/23 Heritage Renovation Project Informational Bulletin

UPDATE 10/25/23:
Fortis Construction is fully mobilizing onto the Project site beginning October 30th.  Work activity for the removal for restoration of the University and Villard Hall windows will also commence, as well as interior building demolition within the two buildings and continue for the next few months.

Please contact UO Owner’s Representatives Tim Allenbaugh (541-346-8214) or Gene Mowery (541-346-5593) if you have questions.
NOTICE AND REMINDER 8/08/23:

  • Villard Hall Theatre Arts department move has been completed.
  • Parking Lot 9 is enclosed by construction fencing and no longer open to public access.
  • Villard Hall abatement staging began today and abatement activity will continue into September.
  • Villard Hall is closed and open only to authorized abatement and construction contractors and university personnel.

 

REMINDER 7/17/23:

  • July 17, Fortis Construction began setting up construction fencing and closing off access to Parking Lot 9. Initial construction fencing will enclose Villard Hall as well, limiting access into the building.  Sidewalks/pathways on the north and east sides of Villard will remain open.
  • Villard Hall department moves are scheduled for July 19-21.
  • Villard Hall abatement is scheduled to begin August 7 and will continue into September.
  • Access into University Hall will continue until the end of the second summer class session, August 18. (But parking lot will be offline for vehicles)

 

Begin:  Friday, June 23, 2023

End:      Project Completion Summer 2025

Building(s) or Area(s) Affected:  Villard Hall, University Hall, Parking Lot 9

Scope:  General information for summer activity associated with the Heritage Renovation Project (exterior historic preservation and interior remodel of University and Villard Halls) are outlined as follows:

    • Contractors Fortis Construction and GBC Construction will periodically be in both Villard Hall and University Hall prior to established department move dates for pre-abatement and demolition investigations and activity.  When the department move dates are reached and moves completed, the buildings will be off-line for access without specific approval.  Once abatement starts, the buildings and site will be fully restrictive access.
    • The parking area between University and Villard Halls will remain open until July 16. Beginning July 17, Fortis Construction will begin setting up construction fencing and closing off access to this parking area. Initial construction fencing will enclose Villard Hall as well, limiting access into the building.
    • Villard Hall department moves are scheduled for July 19-21.
    • Villard Hall abatement is scheduled to begin August 7 and will continue into September.
    • Access into University Hall will continue until the end of the second summer class session, August 18. (But parking lot will be offline for vehicles)
    • University Hall: Mathematics department move is scheduled for August 21-23. Construction fencing to enclose University Hall is targeted to begin in this time period as well.
    • University Hall abatement is scheduled to begin September 4 and will continue into October.
    • In conjunction with construction fencing installation, vehicular and pedestrian pathway closure and rerouting signage will be put in place.

Please contact UO Owner’s Representatives Tim Allenbaugh (541-346-8214) or Gene Mowery (541-346-5593) if you have questions.

Current construction and impacts information can be found on the UO Maps site.

 

Image of Villard, University Hall, and Lot 9

3/28/23 – 9/15/23 Knight Library Basement Abatement and Demolition Advisory

UPDATE 6/15/23:
The week of June 20th electrical work will be occurring in the ceiling of hallway H037, the west hallway of the basement level.  During this above head work, the hallway will be closed to regular foot traffic.  Access to the southern portions of the basement will be directed through hallway 30 and hallway 57.

 

UPDATE 6/01/23:
Abatement of ductwork and two older mechanical units in rooms 56 and 50A is scheduled to start on Monday, June 5th and finish on Friday, June 16th.  Noise can be expected during this time.

 

UPDATE 5/02/23:
Abatement has been completed and general demolition work should be finished by next week.  We will then begin the construction phase with an expected end date in early September.
This Wednesday morning, May 3rd, Preferred Construction will be saw cutting concrete in the basement. The extra noise associated with this will occur between 7:00 am – 10:00 am.

 

UPDATE 4/6/23:
General demolition in preparation for construction will start April 17th.  Signage will be in the halls directing use of the temporary location for the Testing Center in rooms 41 & 42.  Hallway H30 will remain open, though may have temporary closures as work is occurring in the area. Please watch for signage in this area. Construction is expected to continue through the summer with completion in early September. There also will be material removal and delivery occurring through the double doors to the exterior on the basement level northwest corner at times.

Diagram of Knight Library basement

CPFMnoticePlan (1)

UPDATE:  The completion date for the abatement portion of this project has been extended out to Friday, April 14, 2023.  An update will be provided when a timeline for the demolition and construction portion has been finalized.

Begin:  Tuesday, March 28, 2023

End:      Thursday, April 6, 2023 Friday, April 14, 2023 (abatement), Friday, September 15, 2023 (project completed)

Building(s) or Area(s) Affected:  Knight Library

Scope:  Abatement and demolition will be underway in the basement as part of the Consolidated Testing Center Renovation. The lower northwest entrance and hall H30 will be blocked temporarily, but not for the entire work period. Hallway H30 and the entrance will be addressed first during the week of Spring Break to minimize ADA disruption.

Services Impacted:  Lower northwest entrance hall, H30, and a small corner in hall H57. The following rooms have been vacated and are part of the renovation: 19, 19A, 30, 30A, 32, 33, 34, H31, 31, 31A, 31B, and 58

Special Instructions:  If you need an accessible entrance during this time period, please plan to use the accessible entrance on the NE main floor.

Work Performed By:  Rose City Contracting

ContactJanell Cottam, CPFM Owner’s Representative, 541-346-7536

Current construction and impacts information can be found on the UO Maps site.

3/13/23 Collier House Room 207 Abatement Project Advisory

Beginning on Monday, 3/13/23, restroom 207 will be off-line for a flooring replacement project. The floor tiles within that space are asbestos-containing, so the University has retained a licensed asbestos abatement contractor to perform the demolition phase as an asbestos abatement project. All removal work will be completed within a full negative pressure enclosure using HEPA air filtration units in strict adherence to regulatory requirements, and will be overseen by UO Environmental Health & Safety (EH&S).

Installation of new flooring materials will be performed by Campus Planning and Facilities Management (CPFM) after abatement work is complete.

Please feel free to contact me if you have any questions or concerns about the abatement phase of this project. Questions pertaining to the new flooring installation phase should be directed to CPFM Work Control (workcontrolcenter@uoregon.edu / 541-346-2319)

__________________________________

Nate Ferguson
Building Environmental Sciences Coordinator

http://safety.uoregon.edu/

Safety & Risk Services | University of Oregon
1260 University of Oregon | Eugene, OR 97403-1260
Office: 541.346.2901 | Mobile: 530.902.0109

Current construction and impacts information can be found on the UO Maps site.

Esslinger Hall Abatement Advisory 10/11/21 – 10/20/21

Begin:  Monday, October 11th, 2021

End:      Wednesday, October 20th, 2021

Building(s) or Area(s) Impacted:  Esslinger Hall – Rooms 006, 006B, 112, 115, 116, 122, 156A

Scope:   In preparation for the Huestis Surge relocation, abatement work will be happening in select areas of Esslinger.  All areas are either unoccupied, or occupants are aware of the upcoming work.

Services Impacted:  Building users may hear some intermittent construction noise, and observe some temporary exhaust tunnels exiting the building.

Work Performed By:  Rose City Contracting

ContactTim Allenbaugh, CPFM Owner’s Representative, 541-346-8214

Onyx Bridge Asbestos Abatement Advisory 9/24/21 – 9/30/21

Begin:  Friday, September 24th, 2021 at 7:00 am

End:      Thursday, September 30th, 2021 at 5:00 pm

Building(s) or Area(s) Impacted:  Onyx Bridge

Scope:  Asbestos abatement will be taking place in rooms 466 through 470 and in room 487.

Services Impacted:  Construction workers will be coming and going from the building.

Work Performed By:  Rose City Contracting

ContactColin Brennan, CPFM Owner’s Representative, 541-346-8242 or 541-654-2972

 

1900 Millrace Room 109 Abatement Advisory 7/12/21 – 7/16/21

Begin:  Monday, July 12th, 2021

End:      Friday, July 16th, 2021

Building Impacted:  1900 Millrace (formerly the Innovation Center) room 109

Scope:  Asbestos abatement/demo of existing minor wall and countertop in room 109.

Services Impacted:

  • No additional electrical or HVAC disruptions are known at this time.  A shut down notice will be issued as necessary.
  • Building access will be maintained during construction but may require minor detours.
  • Users can expect to hear construction noises like hammering, drilling, grinding, and see UO staff entering and exiting the building during normal business hours.

Work performed by:  Facilities Construction Services

Contact:  Theo Davis, CPFM Design & Construction Project Manager, 541-346-1012

Phase 2 of the Hamilton/Walton Residence Hall Transformation Project – Postponed

UPDATE:  Phase 2 has been postponed until further notice.

 

Begin:  July 6, 2021

End:      August 1, 2023

Building(s) or Area(s) Impacted: Walton Hall and surrounding pathways, Agate St., Unthank Jr. Hall

Scope:  We are preparing to begin Phase 2 of the Hamilton/Walton Residence Hall Transformation Project. We are finishing up the 1st Phase, Unthank Jr. Hall, and will soon move over to the Walton site to begin the demolition of that complex. For context, Walton Hall is located on the corner of 15th Ave. and Agate Street to the south and east respectively, University Health Services to the north, and the Living Learning Center to the west.

We will begin mobilizing on July 6 and begin moving the fencing over from the Unthank Jr. Hall site. The first activity will be building a paved path south of the UHC to allow an accessible exit from UHS. We will begin asbestos abatement activities in Walton Hall in July 13, and demolition of the building will begin in August. The abatement and demolition of Walton will take approximately 3 months and will be finished by late October. Work hours will generally be from 8AM – 5PM, with a quiet hour between 8AM-9AM.

Upon demolition of Walton Hall in late October, work will begin on two buildings that will replace Walton Hall totaling 300,000 square feet.  Site work will begin in October of 2021 and run through January 2022. This will be followed by foundations and then floor framing, topping out in August of 2022. Interior and then site work will run through July of 2023 when the buildings and site will open up, with all fencing removed and permanent pathways opened up.

Services Impacted:  Construction access to and from the site will be on Agate Street, with accessible pedestrian routes on both Powell Plaza to the south, and an accessible path to the south of UHS. The Agate Street Crossing will remain open during the project. The west sidewalk on Agate will be close during the project.

Special Instructions: Please refer to the attached site logistics maps, and please feel free to contact me for any questions.

Work Performed By: Fortis Construction

Contact: George Bleekman, CPFM Owner’s Representative, 541-346-2625

Lawrence Hall H230 Flooring Removal Advisory 5/11/21 – 5/13/21

Begin:  Tuesday, May 11th, 2021

End:      Thursday, May 13th, 2021

Building(s) or Area(s) Impacted:  Lawrence Hall

Scope:  The flooring will be removed in Lawrence Hall H230. The flooring is asbestos-containing, so the work area will be contained and inaccessible from May 11 – May 13, 2021.

Services Impacted:  There will also be no access to rooms 230, 231, & 232 during this period.

Work Performed By:  The removal work will be conducted by an outside contractor and overseen by Environmental Health & Safety (EHS).

ContactAdam Jones, SRS Buildings Sciences Manager, 541-346-8397

1900 Millrace 109, 116, & 120 Abatement 4/12-4/30

Begin:  Monday, April 12, 2021

End:      Friday, April 30, 2021

Building Impacted:  1900 Millrace (formerly the Innovation Center) rooms 109, 116, & 120.

Scope:  Asbestos Abatement of existing floors in room 109 & 116.  Requires pre/post work to disconnect/reconnect the fume hood in room 120.

  • April 12-16: prep work that includes shutdown of fume hood ventilation in rooms 116 & 120, hot work (welding) on West exterior side of the building.
  • April 19-21: abatement work in rooms 109 & 116
  • April 21-30: post abatement work that includes turning back on the fume hood ventilation & hot work on the West exterior side of the building.  The bulk of the work is expected to occur until 4/23, however there could be some minor residual work that lasts until 4/30.

Services Impacted:

  • No additional electrical or HVAC disruptions are known at this time.  A shut down notice will be issued as necessary.
  • Building access will be maintained during construction but may require minor detours.
  • Users can expect to hear construction noises like hammering, drilling, grinding, and see Rose City Contracting employees and UO staff entering and exiting the building during normal business hours.

Work performed by:  Facilities Construction Services, Rose City Contracting

Contact:  Theo Davis, CPFM Design & Construction Project Manager, 541-346-1012

Frohnmayer Music Abatement Advisory 2/8/21-2/12/21

Begin:  Monday, February 8, 2021

End:  Friday, February 12, 2021

Building(s) or Area(s) Impacted:  Frohnmayer School of Music

Scope:  Contractors will be doing abatement work in the basement, within elevator machine room 007, mechanical room 001, utility room 009, and crawlspaces accessed from these rooms.

Services Impacted:  Building occupants may see temporary air ducting tubes and personnel wearing PPE.

Extra Notes:  All abatement areas are fully contained and pose no risk to building users.

Work Performed By:  Rose City Contracting

Contact: Tim Allenbaugh, Construction Project Manager, 541-346-8214

Huestis Hazardous Materials Sampling Advisory 12/14/20 – 1/15/20

Begin:  December 14, 2020

End:      January 15, 2021

Building(s) or Area(s) Impacted:  Huestis Hall building-wide

Scope:  In preparation for the Huestis Hall Renovation Project, UO EH&S will be onsite taking samples of potentially hazardous materials for abatement work.

Extra Notes: EH&S will be accessing rooms, such as labs and offices, throughout the sampling process.

Work Performed By: UO EH&S

Contact: Adam Jones, SRS Buildings Sciences Manager, 541-346-8397

Agate Hall 2nd Floor Restrooms Shutdown 10/22/20 – 1/31/21

UPDATE 10/26: This is an informational notice regard the second floor bathrooms in Agate Hall, rooms 201 & 223. Due to sealcoat failure on the floors, the bathrooms will be taken offline while the flooring is repaired or replaced. The lower layers of flooring contain asbestos, and there is concern that if the sealcoat continues to be impacted, the asbestos layers may start getting impacted as well. This decision is being made out of an abundance of caution, and the asbestos layer has not yet been impacted at this time. EHS and CPFM are currently working out repair or replacement options. We will provide additional information as we figure out our plan.

In the meantime, please use the first floor restrooms. Please feel free to contact me if you have questions.

Begin:  Thursday, October 22nd, 2020 – Effective immediately

End:      Unknown January 31, 2021

Building(s) or Area(s) Impacted:  Agate Hall Men’s Restrooms #201 & 223

Scope:  The Men’s second floor restrooms #201 & 223, have been closed for emergency repairs/construction.

Services Impacted:  Second floor Men’s restrooms shut down.

Special InstructionsPlease use Men’s restroom #125 on the south end of the building of the 1st floor, or the All-Gender restroom #125A, which is located next to it. Please use the first floor restrooms.

Work Performed By:   CPFM Facilities and a contractor

ContactAdam Jones, SRS Buildings Sciences Manager, 541-346-8397

Onyx Bridge 486 Mold/ACM Remediation

Begin:  Thursday, October 1st, 2020 at 7:00am

End:      Friday, October 2nd, 2020 at 4:00 pm

Building or Area Impacted:  Onyx Bridge 486

Scope:  Environmental Health & Safety will be supervising subcontractors Servpro and All Aspects Environmental in the performance of mold remediation and removal of ACM pipe insulation in Onyx Bridge Room 486.

Services Impacted:  Equipment in the 4th floor hallway, masking and safety containment barriers at the door to room 486.

Work Performed By:   Environmental Health & Safety, subcontractors Servpro and All Aspects Environmental

Contact:  Nate Ferguson, Building Environmental Sciences Coordinator —541-346-2901

Pacific Hall Rooms 202, 203, and 204 Remodel Advisory 9/2/20 – 11/30/20

UPDATE: The scope of the work has been expanded and is projected to finish on 11/30.

Begin:  Wednesday, September 2nd, 2020

End:      Friday, October 23rd 30th, 2020 November 6th 30th, 2020

Building Impacted:  Pacific Hall 202, 203, 204

Scope:  Remodel of 3 suites to connect suites and refresh finishes, electrical, lighting, mechanical ventilation system and add new storefront entries.  Minor asbestos abatement is required.

Services Impacted:

  • Asbestos abatement will occur in suites 202 and 204 from 9/2 to 9/4.  It will not impact suite 203. Additional asbestos abatement will occur the week of 10/19.
  • Construction to begin 9/14.
  • No electrical or HVAC disruptions are known at this time.  A shut down notice will be issued as necessary.
  • Users can expect to hear construction noises like hammering and drilling, and see employees and UO staff entering and exiting the building during normal business hours.

Work performed by:  Chambers Construction and their subs.

Contact:  Theo Davis, CPFM Design & Construction Project Manager, 541-346-1012

Esslinger Abatement Project 8/26/19 – 1/6/2020

Update 11/4:

  • Carpet installation will occur in the entry of L101 on 11/5 and 11/6. Foot traffic will be advised to use the NW entry.
  • A floor scraping machine will be in use between (roughly) 8am and noon on Tuesday 11/5 and (perhaps) 8am-noon on Wednesday 11/7. This machine will be somewhat noisy, but we will make every attempt to close doors to contain noise.
  • Carpet installation will be occurring all week, and there will be odors associated with the carpet glue. EHS will have appropriate MSDS sheets on file.

Update 10/16:

During the abatement process some floor tiles were knocked loose in women’s restroom 113. In order to repair the tiles, the contractor will have to close restroom 113 tomorrow 10/17. While the repairs are being made, all-gender restroom 173 will still be operational as an alternative.

 

On Monday, August 26th, at 7:00 am through Friday, September 6th at 4:00 pm, abatement work will be performed by Belfor Environmental in two phases:

Phase 1 Abatement (see clouded area in 1st diagram) 8/26-8/30:

  • Occupants of these offices have been temporarily moved to allow for work.
  • Access to Esslinger during Phase 1 will be restricted to the northwest lobby L102.
  • REC offices adjacent to H102 can access offices from L102 during Phase 1.

Phase 2 Abatement (see clouded area in 2nd diagram) 9/2-9/6:

  • Access to Esslinger will be through L101.
  • Stairs at L102/ S101 will remain open.
  • REC staff in offices 102, 103A-D, 104, and 104A-B will be able to access their suite though L101 to 102. (Door hardware will be temporarily replaced for access.)
  • Room 106, and restrooms 115/117 will be offline during phase 2.
  • Classrooms 105, 107, 112, and 116 have been taken offline by the registrar for the duration of the abatement project.

 

On Monday, October 14th through Monday, January 6th, 2020, flooring work will be performed by Facilities Services and a number of subcontractors:

Phase 3 Flooring (see highlighted areas in 3rd diagram) 10/14/19-1/6/20:

  • Carpet will be replaced in 170, 172, 174, 175, 176, 177, 179, 180A, 181A, and 181B in phases and is expected to be completed before 11/8/19.
  • Wall and drywall framing work is expected to be completed before 11/15/19.
  • Ceiling work in 180/181 and the perimeter is expected to be completed before 12/1/19.
  • Plumbing work in 171 is expected to be completed before 12/15/19.
  • Resilient flooring is expected to be installed in H102 and H103 before 10/31/19.
  • Resilient flooring is expected to be installed in H101 and H111 before 12/15/19.
  • Carpet will be replaced in 180/181 and is expected to be completed before 12/30/19.
  • The doors, storefront, break room, etc. is expected to be completed before 1/6/20.

For questions or concerns, please contact Tim Allenbaugh at 346-8214 or timallen@uoregon.edu.

 

Knight Library L205, 206, and 206A Renovation Advisory 8/19 – 9/27/19 – UPDATE

UPDATE:

Beginning, Monday, August 19 through September 27, CPFM Construction Services Design and Construction will be renovating Knight Library Special Collections Rooms 205 and 206 L205, 206, and 206A. This work involves demo, electrical, carpentry, paint, new carpet, and furniture. Building users can expect to hear normal and occasional construction noises, such as hammering and drilling; in addition, during the paint portion, occupants may notice a faint smell from the low-VOC, non-toxic paint. Contractors and UO personnel will be entering/exiting the building with tools and materials during normal business hours.

Asbestos abatement is planned for August 21-23. During this time, technicians will turn off HVAC ventilation system as part of normal safety precautions, which will affect portions of Floors 1 and 2, as well as the basement. No other utility disruptions or shutoffs are expected at this time; however, additional notice(s) will be distributed, should any occur.

Preferred Construction will perform this renovation work.

For any questions or concerns, please contact Project Manager Theo Davis at 541-346-1012 or tdavis1@uoregon.edu.

ORIGINAL MESSAGE:

Beginning, Monday, August 19 through September 27, CPFM Construction Services will be renovating Knight Library Special Collections Rooms 205 and 206.  This work involves demo, electrical, carpentry, paint, new carpet, and furniture. Building users can expect to hear normal and occasional construction noises, such as hammering and drilling; in addition, during the paint portion, occupants may notice a faint smell from the low-VOC, non-toxic paint. Contractors and UO personnel will be entering/exiting the building with tools and materials during normal business hours.

Asbestos abatement is planned for August 21-23. During this time, technicians will turn off HVAC ventilation system as part of normal safety precautions, which will affect portions of Floors 1 and 2, as well as the basement. No other utility disruptions or shutoffs are expected at this time; however, additional notice(s) will be distributed, should any occur.

Preferred Construction will perform this renovation work.

For any questions or concerns, please contact Project Manager Theo Davis at 541-346-1012 or tdavis1@uoregon.edu.

Frohnmayer Music Building 121A and Lobby 120 Renovation Advisory 8/19 – 9/6/19

Update 8/30/19:

This renovation work has been extended a week and is expected to be completed on September 6th.

 

Beginning, Monday, August 19 through August 30 September 6th, CPFM Construction Services will be doing a minor renovation project in Room 121A and Lobby 120 in the Frohnmayer Music Building. This work involves demo, minor abatement of base, framing, door install, drywall, patching, and painting. Building users can expect to hear normal and occasional construction noises, such as hammering and drilling; in addition, during the paint portion, occupants may notice a faint smell from the low-VOC, non-toxic paint. Occupants may also notice UO personnel entering/exiting the building with tools and materials during normal business hours.

No other utility disruptions or shutoffs are expected at this time; however, additional notice(s) will be distributed, should any occur.

UO CPFM Facilities Services will perform the entire renovation.

For any questions or concerns, please contact Project Manager Theo Davis at 541-346-1012 or tdavis1@uoregon.edu.

Knight Library #364-#366 Renovation 6/17/19 – 8/31/19

Beginning June 17th, and continuing until the end of August, the general contractor, Preferred Construction, and their subs will be doing renovation work in rooms 364-366 in the Knight Library.  This will involve asbestos abatement, minor demo and framing, drywall, duct work, electrical, carpet and paint.  Users can expect to hear normal and occasional construction noises such as hammering and drilling, and may smell a water-based latex, non-toxic paint, during the painting portion.  Users will see the contractor, their subs and UO personnel entering/exiting the building with tools and materials during normal business hours.

During abatement (6/18-6/20), CPFM staff will turn off the HVAC system, which might affect areas outside the construction zone on the third floor.

No other utility disruptions or shutoffs are expected at this time, but if there are any more, then an additional notice will be distributed.

If there are any issues or concerns, please contact Theo Davis, the CPFM project manager, at 541-346-1012, or tdavis1@uoregon.edu.

CPFM Building 130 Construction Activities 9/10 – 9/14

Abatement for the future Work Control Center area in CPFM Building 130 will begin on Monday 9/10, and it should be complete by 9/14. The contractors will be using two parking spaces north of the building, one for a dumpster, and one for their equipment van. Please expect increased activity and noise in this area.

For questions or concerns please contact CPFM Design and Construction Project Manager Tim Allenbaugh at 541-346-8214.

Bean Hall Project Road Closures July 19, 2018

Campus Community,

There are two street closures for the Bean Hall Project on July 19th.

The first is a closure of 15th street between Bean and Global Scholars Hall from 6 AM to 8 AM. We will shut down the street with flaggers to detour traffic, set up the crane and lift the rooftop units.

The second closure will be Columbia Street between Hamilton Hall and the Alumni Center. We will be closing the parking spots in lot 37 as part of the closure. This closure will be from 6 AM – 3 PM. Access to the Columbia Garage will not be affected.

For questions or concerns please contact CPFM Design and Construction Project Manager George Bleekman 541-346-2625.

[embeddoc url=”https://blogs.uoregon.edu/cpfmnotifications/files/2018/07/General-Sheet-Metal-Bean-Hall-Crane-Pick-Site-Plan-1-1reluog.pdf” download=”all” viewer=”google” ]

[embeddoc url=”https://blogs.uoregon.edu/cpfmnotifications/files/2018/07/Crane-Laydown-Aerial-View-2-212zc7g.pdf” download=”all” viewer=”google” ]

3/19 – 3/23: McKenzie Suite 275 Abatement

Building Occupants of McKenzie Suite 275:

Beginning Monday, March 19th at 4:00 pm until Friday, March 23rd, a contractor will be performing asbestos abatement in Suite 275.  The contractor has requested that all the HVAC supply/returns in the suite to be shut off so they can cover up the vents with plastic.

Work will begin at approximately 4:00 pm and they will work in the evening.  We expect them to finish by Friday but it could end sooner, TBD.
Abatement work will be performed by Rose City.

For questions or concerns about how this may impact your area, contact Theo Davis, Campus Planning and Facilities Management (CPFM) Design and Construction at 346-1012.

[embeddoc url=”https://blogs.uoregon.edu/cpfmnotifications/files/2018/03/Mckenzie-275-Floor-Plan-area-of-work-5-1xpx2r3.pdf” download=”all” viewer=”google” ]