Esslinger Hall Electrical Shutdown 2/26/22

Begin:  Saturday, February 26th, 2022 at 7:00 am

End:      Saturday, February 26th, 2022 at 1:00 pm

Building(s) or Area(s) Impacted:  Esslinger Hall – First Floor and Possibly Basement Level

Scope:  Contractors will shut down power to Panels C1 and C2 to terminate 8 circuits and re-feed additional circuits for rooms 112 and 116.

Services Impacted:  Power will be offline on the first floor and possibly affect some circuits in the basement level.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.

Work Performed By:  Mortenson Construction/ EC Power

ContactTim Allenbaugh, CPFM Owner’s Representative, 541-346-8214