Begin:  Wednesday, August 3, 2022 at 7:00 am

End:      Wednesday, August 3, 2022 at 12:00 noon

Building(s) or Area(s) Affected:  Huestis Hall

Scope:  The fire suppression system will be shut down to complete the isolation of the renovation zone from the active basement zone. Fire watch will be in place.

DetailsHorns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special InstructionsIf there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By:  Lease Crutcher Lewis, Harvey & Price

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880