Advisory: 6/23 – 6/30: Johnson Hall Exterior Steps Restoration

Building Occupants,

The North, main entry steps of Johnson Hall will be receiving a restoration treatment beginning Friday June 23rd through June 30th. This will result in periodic closing of these areas. Affected areas will receive cones and caution tape identifying the work space. Work will be intermittent as the various materials used are allowed to cure. Weather and material cure time will play a role in the time table. If there is an extension of the time, building users will be notified.

Work will be performed by Brown Concrete.

For questions about how this may impact your area, contact Jim Cody, CPFM Zone A Maintenance Manager at 346-2302.

Notice: Pacific Hall Construction Impacts to Lab Gas, Drain Lines, Compressed Air, RO System and Water Starting 6/21/17 Ending 07/07/17

Building Occupants,

As part of the Pacific Hall Project, the following impacts will be happening starting June 21, 2017 and running through July 7, 2017.

 

Starting June 21, 2017, at 7:00 am

Ending June 22, 2017, by 4:00 pm

Scope: Lab gas will be disconnected temporarily to allow for construction activities.

 

Starting June 22, 2017, at 7:00 am

Ending June 23, 2017, by 4:00 pm

Scope: Lab sink drain lines need to be temporarily disconnected and configured to accommodate construction activities.

 

Starting June 23, 2017, at 7:00 am

Ending June 23, 2017, by 4:00 pm

Scope: Compressed air will be disconnected to allow construction activities.

 

Starting June 26, 2017, 7:00 am

Ending June 29, 2017, by 4:00 pm

Scope: RO water will temporarily be disconnected to allow for construction activities.

 

Starting July 5, 2017, at 7:00 am

Ending July 7, 2017, by 4:00 pm

Scope: The chilled and hot water will be temporarily disconnected to allow for construction activities.

 

For questions regarding these impacts contact CPFM Design and Construction Nick Pritchard at 612-803-0664 or Jen Miley at 541-346-1530.

 

Notice: Water Intrusion at Huestis Hall (1st and 2nd floors)

Building Occupants:

There was a small water intrusion related to an ongoing construction project on the first and second floors of Huestis Hall. Visible impacts included damage to some ceiling finishes in the first floor hallway. Environmental Health and Safety and Campus Planning and Facilities Management staff responded over the weekend and repaired the leak point and cleaned up all bulk water and debris. Follow-up investigation into damage and mitigation will follow on Monday morning. It does not appear as though impacts extend into instructional spaces. We apologize for any inconvenience!

Notice provided by Adam Jones, Building Sciences Manager (6-8397)

 

 

4/20/17-5/2/17: Klamath Abatement Shutdown

Building Occupants,

Beginning Thursday night, April 20th at 7:00 p.m. until 6:00 a.m. and again on Friday evening, April 21st, at 7:00 p.m. until 6:00 a.m., contractors will be working on the ground floor, 1st, 2nd and 3rd floors doing Abatement as shown on red in the attached maps.

Starting April 24th, during their 4:00 a.m. to 7:30 a.m. work time, Anderson Construction will begin to open up wall sections as shown in Green on the 2nd floor only. These areas marked in green will then be abated from 7p.m. to 6a.m. starting Thursday, April 27th, and continuing during these hours until complete, approximately 3 days.

The areas affected are the Klamath hallways, some labs and janitor spaces where exposed water pipe fittings are.

For questions or concerns about how this may impact your area, contact Jana Gerow, Campus Planning and Facilities Management (CPFM) Design and Construction at 346-8317.

5/3/17: Streisinger Air Supply Shutdown

Building Occupants,

On Wednesday, May 3rd, from 8:00 am to 3:30 pm, there will be intermittent air supply disruptions throughout the day.  Between the hours of 8:00 am to 11:00 am, please keep lab doors open. Between the hours of 11:00 am to 3:30 pm, please keep fume hood sashes closed.  Systems affected will be the cooling, exhaust, fume hoods, and HVAC air supply.

Work will be performed by CPFM’s Facilities Services.

For questions or concerns about how this may impact your area, contact Bruce Budzik, Campus Planning and Facilities Management (CPFM) Zone B Maintenance Manager at 346-8834.

4/22/17: Klamath Domestic Hot & Cold Water, Natural Gas, Nitrogen, RO/DI Water, Vacuum Shutdown

Building Occupants,

On Saturday, April 22nd, between 7:00 am and 5:00 pm, the below services will be interrupted due to continued work on the 2nd floor renovation in Klamath Hall.

  • From 7:00 am to 11:00 am, emergency showers, emergency eye washes, drinking fountains, restroom sinks and kitchen sinks will not have water.  All levels of Klamath Hall will be affected.  No hot or cold domestic water will be available during this time.
  • From 11:00 am to 1:00 pm, natural gas will not be available.  All Bunsen burner gas valves should remain closed.  All levels of Klamath Hall will be affected.
  • From 1:00 pm to 3:00 pm, nitrogen will be offline.  All levels of Klamath Hall will be affected.
  • From 3:00 pm to 5:00 pm, the RO/DI water will be offline.  Only the 2nd floor of Klamath Hall will be affected.
  • From 3:00 pm to 5:00 pm, the vacuum will be offline.  Only rooms 292, 292B, 295, 296, and 297 of Klamath Hall will be affected.

This work was scheduled on a Saturday to limit the impact to building occupants.

For questions or concerns about how this may impact your area, contact Denise Stewart, Campus Planning and Facilities Management (CPFM) Design and Construction at 346-2280.

4/24/17 – 4/26/17: Autoclave Untreated Steam Shutdown for Huestis, Klamath, Onyx, and Zebra Fish

Building Occupants:

On April 24th at 7:00 am until April 26th at 4:00 pm, the autoclave untreated steam will be shut down for annual service maintenance and overhaul.

There will be access to treated 60# steam if you send a request to Mo Soleimani by e-mail.

Work will be performed by CPS Maintenance, a Mueller technician, and a S2 Industrial contractor.

For questions or concerns, please contact Mo Soleimani at 346-2213.

 

4/19/17: Planned heating water shutdown for Willamette Hall

Building Occupants,

Due to scheduled repairs on Willamette Hall (East side, 1st floor, rooms #139-#178), occupants should expect intermittent shutdowns (heating water) to install valves. The affected areas will be cooler than during a normal shutdown .  Scheduled work will take place on Wednesday, April 19, 2017, from 7:00 am – 9:00 am.

For additional questions on how this may impact your services, please contact Glen MacDonald at 541-346-2281.

 

 

4/12/17: Planned HVAC Shutdown for preventative maintenance work (ZIRC/ZIRC Annex)

Building Occupants,

Due to scheduled preventative maintenance on ZIRC 101 and ZIRC Annex, occupants should expect intermittent shutdowns (heating and cooling) on air handling units and restroom exhaust fans to allow crews to change system filters.  Scheduled work will be taking place on Wednesday, April 12, 2017, from 8:00 am – 3:30 pm.

For additional questions on how this may impact your services, please contact Bruce Budzik at 541-346-8834.

 

4/5/17 – 4/11/17: Klamath Hall (night work) Asbestos Abatement

Building Occupants,

PMG (contractor) will be conducting asbestos abatement work above the ceiling spaces in the women’s restrooms from the basement through 3rd floor levels of Klamath Hall. The work will begin tonight (April 5th) at 5:00PM and is estimated to be completed by early next week at the latest. All work will be conducted at night between 5:00PM and 6:00AM.

For questions or concerns about this project, contact Nate Ferguson Safety & Risk Services at 346-2901.

 

  

4/3/17 – 4/7/17 – Huestis 2nd Floor – Demolition of Environmental Chambers

Building Occupants:

During the week of April 3-7 demolition and removal of the environmental chambers on the 2nd floor of Huestis is scheduled to begin. Chambers are located in Rooms: 232A, 226A, 226B, and 226C.  This activity is expected to last 2-4 weeks.  The typical work schedule  will be 4am – 8am.

As work begins, we will be able to partially demo some of the chambers to access the utilities that are concealed by the chambers. Once this field verification is complete, we will provide an update and advance notifications of any required shut-downs.

For questions or concerns about this project, contact Colin Brennan, CPFM Design and Construction at 346-8242.

3/31/17 Susan Campbell Hall and Hendricks Hall Domestic Water Shutdown

Building Occupants:

On Friday, March 31st from 8:30 am to 2:30 pm, the domestic water supply will be shut down to all fixtures in Susan Campbell Hall and Hendricks Hall.  Work is being performed to replace faulty water valves in the vault at the intersection of University & 15th, near Gerlinger. Sinks, toilets, urinals, drinking fountains, lavatory faucets, and janitorial faucets will also be affected in this area. Please plan ahead to make arrangements to use water in adjacent buildings during shutdown hours.

Work will be performed by Twin Rivers Plumbing.

For questions or concerns about how this may impact your area, contact Sarah Follett, CPFM Campus Planning, Design & Construction at 346-8264.

 

Esslinger Hall HVAC Preventative Maintenance 4/5/17

Building Occupants,

Due to scheduled preventative maintenance on the Esslinger Hall HVAC equipment, building occupants should expect intermittent shutdowns on air handling units and restroom exhaust fans to allow crews to change system filters.  This scheduled work will be taking place on Wednesday, April 5, 2017, from 8:00 am – 3:30 pm.

For additional questions on how this may impact your services, please contact Jim Cody at 541-346-2302.