Streisinger and Klamath Loading Dock Blockage Advisory 7/8/19

As part of ongoing renovations, contractors will have a crane in the loading dock between Klamath Hall and Streisinger Hall on Monday, July 8th, blocking deliveries between 4:00 am – 12:00 noon.

Work will be performed by Lease Crutcher Lewis.

For questions or concerns, please contact CPFM Design & Construction Owner’s Representative Denise Stewart at 541-335-1258 or dstewart@uoregon.edu.

University Health, Counseling and Testing Power Shutdown 7/26/19 – 7/27/19

DATE REVISION: 

This shut-down has been shifted by two weeks and is now scheduled to occur Friday July 26th at 6 pm until Sat July 27th at 6 am.

 

As part of the addition and renovation project, the power will be temporarily shut down on Friday, July 12th 26th at 6:00 pm until 6:00 am on Saturday, July 13th 27th.  Prior to being shut off, the building will be checked to make sure everyone has left for the day.  Generators will be brought in to provide electricity to all items requiring emergency power.  Between now and the outage, Jesse Porras is surveying equipment that will need power during that time.

Work will be performed by Lease Crutcher Lewis.

If you have any questions or concerns, please contact CPFM Design and Construction Owner’s Representative Colin Brennan at 541-654-2972 or brennan@uoregon.edu.

1715 Franklin Fire Alarm Test 6/28/19

As part of the remodel at 1715 Franklin Blvd, fire alarm testing will be performed on Friday, June 28th from 6:00 am-6:15 am.

Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

For questions or concerns, please contact Jeff Hanson at 541-346-7991 or  Fire Systems Program Manager Zach Earl at 541-521-0351 or 541-346- 9295.

PeaceHealth North Building Noise Advisory 6/28/19 – 8/20/19

Tomorrow morning, Friday, June 28th, from 7:00 am to 9:00 am, a contractor will be installing metal wall track to the floor and ceiling of suite 452, using powder actuated fasteners. This will be a noisy activity, and may sound similar to a small firearm.

Additional (general construction) noise will occur in the same space through mid-August.

Work will be performed by Lease Crutcher Lewis.

If you have questions or concerns, please contact CPFM Design and Construction Project Manager Tim Allenbaugh at 346-8214 or timallen@uoregon.edu.

Franklin to close overnight for work on Knight Campus bridge starting July 8

Campus Community,

Overnight closures on Franklin Boulevard between Onyx and Agate streets are slated to begin July 8 while crews complete work on a skybridge, an important element of the new Phil and Penny Knight Campus for Accelerating Scientific Impact.

Starting July 8 at 9 p.m. each evening and running until Labor Day, traffic will be reduced to one lane. At 10 p.m. all vehicular lanes will be closed in both directions, reopening to two lanes in each direction at 5 a.m. Clearly marked detours will guide traffic along Agate Street, East 18th Avenue, and Patterson and Hilyard streets.

The EmX bus and emergency vehicles are expected pass through the job site without being re-routed day and night. Work on the bridge is slated to be complete by Labor Day.
Closures are needed for crews to safely complete elements of the bridge that span the roadway. Signs will be posted on Interstate 5 to re-direct truck traffic bound for downtown Eugene to help minimize truck traffic in neighborhoods adjacent to campus. Other signs will be posted along Franklin Boulevard to address local traffic.

The bridge, which will connect the Lewis Integrative Science Building with the Knight Campus, is comprised of a structural steel frame that uses two butterfly arches and suspension cables. Crews from multiple labor trades will erect the structure one half at a time, gradually increasing the load of the bridge until it is 100 percent self-supporting.

By gradually increasing the loading, crews will be able to frequently test and retest structural integrity along the way. The construction plan underwent an independent third-party engineering evaluation to ensure maximum safety.

A third-party special inspector will provide an independent inspection of all bolted and welded connections as well. At the end of every night of work, the structure will be secure and safe for vehicles to travel under during the following day.

Once the structure is erected, it will then receive finish paint, architectural sheet metal panels, curtain wall glazing and interior finishes such as doors and flooring. The bridge is scheduled to be structurally complete by Labor Day, but will not open until the Knight Campus does, in the late spring of 2020.

Updates, lane closure schedules and detour routes are available on the Knight Campus website’s construction and traffic section.

https://around.uoregon.edu/content/franklin-close-overnight-work-knight-campus-bridge

KNIGHT CAMPUS SKYBRIDGE
The bridge will connect the Lewis Integrative Science Building with the Knight Campus
Width: 14 feet (walking area)/48 feet, 2 inches (arch to arch)
Length: 190 feet
Height: 35 feet (top of walking area)/50 feet, 8 inches (top of arches)
Weight: Approximately 500 tons (bridge itself is 300 tons, concrete footings are more than 200 tons)
Building materials: Structural steel, glass and sheet metal

Willamette Hall Rooms 100, 100A, 106 and 121 Renovation Work through 9/20

Update 8/29:

This renovation work has been extended and the expected completion date is September 20th.

 

Preferred Construction and Pro Sound and Video will be conducting the first phase of renovation in Willamette Hall classrooms 100, 100A, 106, and 121 starting this week and is expected to continue until approximately September 1 will continue through September 20th. Work will include minor demolition, electrical upgrades, and audio/visual equipment upgrades. Users can expect to hear occasional construction noises such as hammering and drilling. There will be increased congestion as crews enter and exit the building with tools and materials.

No utility disruptions or shutoffs are expected at this time; however, if there are any disruptions or shutdowns to services, an additional notice will be distributed.

Project Contact:

Martina S. Oxoby
Owner’s Representative | LEED AP BD+C
Design and Construction | Campus Planning and Facilities Management
University of Oregon
O: 541.346.5880 | C: 541.556.8477

HEDCO 130F Renovation 7/8 – 8/9

UPDATE:

Renovation work has been extended through August 9th.

 

Facilities Liaisons,

The general contractor, Lease Crutcher Lewis, and their subs will be doing renovation work in HEDCO room 130F starting July 8th expected to continue until approximately August 1st 9th. . It will involve minor demo, framing, drywall, electrical, carpet, and paint. Users can expect to hear occasional construction noises such as hammering and drilling. Crews will also be painting with water-based latex, non-toxic paint that may create an odor in the work area. There will be increased congestion crews enter and exit the building with tools and materials during business hours.

No utility disruptions or shutoffs are expected at this time; however, if there are any additional disruptions or shutdowns to services, an additional notice will be distributed.

Project Contact:

Theo Davis | Project Manager, PMP, LEED AP, LEAD Safe, SHP, EAR, RPCV
Office of Design & Construction | Division of Campus Planning & Facilities Management
University of Oregon
1276 University of Oregon, Eugene, OR 97403
p: 541.346.1012

Tykeson Hall Fire Alarm Testing 6/27

Campus Community,

As part of the Tykeson Hall construction project, fire alarm testing will be performed on Thursday, June 27 from 1:00PM-4:00 PM.

Occupants of neighboring buildings should be aware of the audible disruption.

Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures. If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Project Contact:

Martina S. Oxoby
Owner’s Representative | LEED AP BD+C
Design and Construction | Campus Planning and Facilities Management
University of Oregon
O: 541.346.5880 | C: 541.556.8477

SRC Closure and Flooring Project Odor Notification 8/24 – 9/8

SRC Closure and Flooring Project Odor Notification 8/24 – 9/8

Campus Community,

The Student Recreation Center will be closed August 24th – September 8th for planned annual maintenance. A portion of this closure will be dedicated to screening and sealing hardwood floors, which creates an odor in the area around the SRC that some people find unpleasant. The process is confirmed safe by UO Environmental Health and Safety, and the SRC will be ventilated thoroughly before reopening. Advanced notice was sent to Facilities Liaisons on June 25th.

Work Area:
Studio 41 (SRC Room 41)
Midtown Courts (SRC Room 138)
Uptown Courts (SRC Room 290)

Contact: Cody Weaver
For questions or concerns, please contact Cody Weaver at 541-346-8993.

_________________________________________________________________________________________________________________________

Original Notice Below Sent June, 2019

Facilities Services, EHS and Building Occupants,

As part of SRC annual maintenance during the planned closure, this is advance notice that the Student Recreation Center will screen and seal its hardwood floors over five working days starting August 28. Outside vendor, New Dimension Hardwood Floors, will apply a new seal to SRC floors, which can create an odor in the area around the SRC that some people find unpleasant. The process is confirmed safe by UO Environmental Health and Safety, and the SRC ventilates thoroughly. No work will occur August 31-September 2 because of the weekend and Labor Day holiday, and the work will be complete by September 4 although related odors may be noticeable for a few days after completion.

Work Area:

Studio 41 (SRC Room 41)

Midtown Courts (SRC Room 138)

Uptown Courts (SRC Room 290)

Cody Weaver will reach out to PE and Rec staff and occupants and other departments with staff in Esslinger Hall.

Additional reminder notifications will be sent out in August. 

Contact:  Cody Weaver

For questions or concerns, please contact Cody Weaver at 541-346-8993.

Roof Work Requires Lift Staging in Cascade Courtyard through 6/28

Facilities Liaisons,

Facilities Services is performing annual summer roof preventative maintenance on Cascade, Willamette, Klamath, and Onyx and will be blocking off sections of the Cascade courtyard through Friday, June 28. Please expect access to be temporarily blocked as they move and stage the lift around the buildings.

For questions or concerns please contact the Work Control Center at 541-346-2319.

Lawrence Hall Domestic Hot and Cold Water Shutdown 6/28

Facilities Liaisons,

Our contractor Harvey and Price needs to make a repair that involves shutting down the domestic hot and cold water at Lawrence Hall.  We have coordinated 6:00 am – 8:00 am with Kyle Harshbarger, College of Design Facilities Manager.   This will impact plumbing fixtures building wide.  The restrooms will be temporarily closed during this outage.

Contact:  Work Control Center

For questions or concerns please contact CPFM Work Control Center at 541-346-2319

Johnson Hall Window Washing 6/29 – 6/30

Facilities Liaisons,

June 29 – 30 a contractor will be onsite washing the exterior windows at Johnson Hall. This may impact access for short amounts of time. The contractor will mark off the areas they are working as they move around the building.

For questions or concerns, please contact CPFM Associate Director Kevin Farthing at 541-346-2857

Oregon Hall Fire Sprinkler Shutdown 7/2

Facilities Liaisons,

As part of the Freight Elevator Project, the sprinkler system will need to be temporarily shut down on July 2 from 7:30 am – 11:30 am while contractors relocated sprinkler heads. The contractor Preferred Construction will provide fire watch for the duration of the shutdown.

Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

For questions or concerns please contact CPFM Design and Construction Project Manager Bruce Budzik at 541-346-8834.

Water Shutdown Impacting Buildings: 108, 109, 110, 111, 112, 115 & 116 (6/27)

Facilities Liaisions,

On June 27 from 7:00 am – 3:30 pm Facilities Services needs to temporarily shut down the domestic cold and hot water that services the following buildings:

Quonset 108
Greenhouse Preparation 109
Old Greenhouse 110
Research Greenhouse 111
Paleoecology Research 112
MNCH Prep Lab 115
Archaeology Research 116

This is necessary for Greenhouse Operations swamp cooler repairs. The Greenhouse is dealing with a failed value and having to manually put water in the units. There are restrooms available in the CPFM Administration Building and portable toilets outside the CPFM Warehouse that can be accessed during this outage.

We appreciate your patience as we make urgent repairs to the swamp coolers.

For questions or concerns please contact CPFM Work Control Center at 541-346-2319

Lillis Roofing Project 6/18 – 9/21

Facilities Liaisons,

The roof project at Lillis Business Complex has started and will run through September 21, 2019. There will be increased contractor activity limiting building entry access on the north side of the building due to overhead work. Please expect noise associated with roofing activities.

For questions or concerns, please contact CPFM Design and Construction Project Manager Tim Allenbaugh at 541-346-8214.

Onyx Bridge Chilled Water Shutdown Impacting Cooling 6/27 7pm – 6/28 5am

Facilities Liaisons,

Revisions to the existing piping in the basement are needed in association with the Klamath 3rd Floor Renovation. This will impact cooling to the east half of Onyx Bridge on floors 1, 2 and 3.

An evening outage was coordinated is to reduce the impact to the occupants.

The controlled temperature (CT) rooms will not be impacted.

For questions or concerns please contact CPFM Design and Construction Owners Rep Denise Stewart 541-335-1258.

Klamath Hall Pedestrian Walkway Closures 6/24 – 8/2

REVISED DATE:

Below is the newest aerial plan with revised dates that extend out to August 2nd for the protection at the NE area of work.

 

Original notice:

Over the coming weeks, the Klamath renovation contractor will be building steel platforms on and at the edges of the rooftop. As the platforms progress around the rooftop sections of pedestrian walkways below will be closed for pedestrian safety. Please be aware of changing signage and barricades as overhead work progresses around the rooftop perimeter. Work will be performed by Lease Crutcher Lewis.

For questions or concerns please contact CPFM Design and Construction Owners Rep Denise Stewart 541-335-1258.

Allen Hall, SOJC Lower Level Remodel through September

Facilities Liaisons,

The SOJC is undertaking a remodel in the lower level of Allen Hall that started June 18th and will continue into the early part of September. You will see construction fences placed at the Allen Hall main east entry and across the walkway in the bike area adjacent to Pacific Hall. The walkway (also serves as fire lane) to Lawrence Hall remains open, and the contractor will monitor any construction activity in this zone. There will be typical construction noise during the work, but most of this will be contained within Allen Hall.

The Owners Rep will work with Allen Hall occupants and ensure they are made aware of specific dates and times of activities that may have significant noise impacts. There will also be some noise generating activity in the fenced in bike area adjacent to Pacific Hall, but this activity should be limited and not excessive.

Please contact CPFM Design and Construction Owners Rep Gene Mowery at 541-346-5593 if you have concerns or questions at any time during this activity.

Water Shutdown Impacting Cascade Hall and Price Science Commons 6/20

Facilities Liaisons,

Due to emergency repairs to a toilet on the third floor of Cascade Hall the domestic water will need to be temporarily shut down until 2 pm on Thursday, June 20.

This will impact Price Science Commons and Cascade Hall.

Facilities Services confirmed that this would not impact the Cafe because it closed during this time. This will not impact the industrial cold water.

Contact:  Work Control Center

For questions or concerns please contact the Work Control Center at 541-346-2319.

Allen Hall Fire Sprinkler Shutdown 6/24

Facilities Liaisons,

On 6/24 from 7:00 am – 3:00 pm the fire sprinkler in Allen Hall will be temporarily shutdown while contractors cut and cap and safe-off the branch line to the northern half of the lower level of Allen Hall for a summer remodel project. The activity should not impact building occupants.

Contractors performing the work and monitoring systems are Harvey and Price and IES.

For questions or concerns please contact Project Manager Gene Mowery at 541-346-5593