Klamath Hall Lab Vacuum Shutdown 6/20 – 6/21

Facilities Liaisons,

As part of the 3rd-floor renovation, contractors need to relocate the rooftop vacuum pump that serves portions of the 2nd-floor. The vacuum will be unavailable in portions of the Klamath 2nd floor for the 2-day duration.  Please select the below drawing to see impacted areas.

For questions or concerns please contact CPFM Design and Construction Owners Rep Denise Stewart 541-335-1258.

 

Huestis Hall Electrical Outage Impacting Rooms on the Third Floor 6/18

Facilities Liaisons,

CPFM Facilities Services Electrical Shop has scheduled an additional electrical outage in Huestis Hall impacting receptacles and plugmolds in rooms 330, 330A, 330B, 332, 334, dryer room 330 and autoclave room 330 on June 18 from 7 am – 8 am.  This is necessary due to a scope change.

For questions or concerns please contact CPFM Facilities Services Electrical Supervisor Rob Berg rberg@uoregon.edu  541-346-2313.

Klamath Hall Exhaust and Fume Hood Shutdown 6/17

Facilities Liaisons,

As part of renovations, contractors need to access the north exhaust plenum on the roof to Install plenum separation for work related to the third-floor project. To enter the plenum, the northern exhaust fans have to be off for safety. The new separation will allow access as needed without additional exhaust fan shutdowns.

General lab exhaust and fume hood exhaust will be offline to the north half of the building for all floors on Monday, June 17th, for a seven-hour duration (5 am – 12 pm) at most.  Work will be performed by Lease Crutcher Lewis.

Special Instructions:

Prior to the shutdown fume hood sashes need to be closed in the north half of the building for all floors.

For questions or concerns please contact CPFM Design and Construction Owners Rep Denise Stewart 541-335-1258.