Onyx Bridge Noise Advisory 6/18

Facilities Liaisons,

As part of the Onyx Bridge Elevator Project on Tuesday 6/18 from 5:00 am to 9:00 am there will be concrete saw cutting in the basement. There will be a generator in the loading dock that provides the power for the concrete saw. There will be noise associated with this work.

For questions or concerns please contact CPFM Design and Construction Project Manager Bruce Budzik 346-8834.

Clinical Services Third Floor Renovation 7/24 – 8/13

Facilities Liaisons,

Beginning July 24th, and continuing until August 13th, Facilities Services and their subcontractors will be performing renovation work on the east wing of the 3rd floor of Clinical Services Building. This will involve asbestos abatement, as well as replacement of the acoustic tile ceiling, HVAC terminal units, and lighting and paint throughout the project area. Occupants can expect to hear normal and occasional construction noises such as hammering and drilling and may smell a water-based latex, non-toxic paint, during the process. Occupants can expect to see the contractor, their subs, and UO personnel entering/exiting the building with tools and materials during normal business hours.
During the abatement and HVAC terminal unit replacements, CPFM staff will turn off the HVAC system, which will affect areas outside the project area, including West halves of the first and second floors, and the entirety of the third floor. This work will be done after-hours to mitigate impacts to building occupants and activities during regular business hours. The HVAC shutdowns are scheduled to occur over two consecutive weekends from 6 pm on Fri 7/26 to 6 am on Mon 7/29, and 6 pm on Fri 8/2 to 6 am on Mon 8/5. HVAC will be functional during the week in between.
No utility disruptions or shutoffs are expected at this time; however, if there are any additional disruptions or shutdowns to services, an additional notice will be distributed.

 

For questions or concerns please contact CPFM Facilities Services Construction Services Manager Justin Grishkin at 541-346-5242.

Columbia Hall 2nd Floor Renovation 7/1 – 7/26

DATE REVISION:

This project has been extended an additional week.  Impacts will be limited to patching and painting one wall.

 

Facilities Liaisons,

Beginning July 1st, and continuing through July 19th 26th, Facilities Services, and their subcontractor will be performing renovation work in room 254C of Columbia Hall. This will involve exhaust duct and fan demolition, fume hood removal, electrical and paint. Users can expect to hear normal and occasional construction noises such as hammering and drilling and may smell a water-based latex, non-toxic paint, during the process. Users can expect to see UO Facilities personnel and their contractor entering/exiting the building with tools and materials during regular business hours. On July 2nd, access to rooms 254A and 254B will be restricted while the duct in the hallway is removed. No utility disruptions or shutoffs are expected at this time; however, if there are any additional disruptions or shutdowns to services, an additional notice will be distributed.

For questions or concerns, please contact CPFM Facilities Services Construction Services Manager Justin Grishkin at 541-346-5242.