9/21/17: Huestis Heating and Cooling Supply Air Shutdown

Building Occupants,

On Thursday, September 21, 2017, the heating and cooling supply air will be temporarily shut down in Huestis while contractors replace a building fan.  This shutdown will begin at 6:00 am and last for one day.

Special Instructions:  When SF 1A and 1B are shut down for the day, it will affect the supply air to the below-listed rooms. This will not shut down fume hood exhaust, but because there will not be supply air, these steps need to be followed in the fume hoods.

  1. Seal all open chemical storage in the fume hood.
  2. Keep fume hood sash closed during the shutdown period.

Impacted Areas:

1st Floor: 111, 111A, 111B, 111C, 129, 129A, 129B, 129C

2nd Floor:  209, 209A, 209B, 209C, 211A, 227A, 229A, 233B, 233C, 233D, 233E

3rd Floor:  305, 305A, 305B, 305C, 311A, 313A, 327A, 337, 337A, 337B, 337C, 337D

For questions or concerns please contact CPFM Zone B Maintenance Manager Bruce Budzik at 541-346-8834.

08/30/17: Emergency Building Wide Hot Water Shutdown Huestis

Building Occupants,

Building hot water services to Huestis restored 8/30 at 11:45 am.  Crews have checked the building; there may be lingering disruptions that we may not be aware of.  If you discover a problem resulting from the shutdown, please contact:

 

CPFM Customer Service Monday –Friday

7:30 am – 4:30 pm

541-346-2319
UOPD Afterhours 541-346-2919

 

 

____________________________________________________________________________________________________________________

 

Building Occupants,

Due to an emergency hot water leak in Huestis Room 226, the building hot water services will be temporarily shut down at 10:00 am.  This will affect hot water services to the entire building.  We will send a restore message when services are back online.

For questions or concerns please contact CPFM Zone B Maintenance Manager Bruce Budzik at 541-346-8834.

8/30/17: Various Zone A Buildings Temp Fluctuation

Building Occupants,

On Wednesday, August 30, 2017 from 7:30 am – 5:00 pm the below listed buildings may experience slightly warmer than normal temps. This is due to the ongoing work on the chilled water pump that services the buildings south of vault P17.

 

Collier House Hendricks Susan Campbell
Gerlinger Gerlinger Annex Knight Library
Lokey Education Hedco Education Annex
Frohnmayer Music Clinical Services

We apologize for any inconvenience this may cause and appreciate your patience.

For questions on how this may impact your services, please contact Jana Gerow CPFM Design and Construction Owners Representative 541-346-8317or Mo Soleimani CPFM Utilities and Energy Maintenance Supervisor 541-346-2213.

8/31/17: Klamath Hall Preventative Maintenance Asset Field Verification Starts

Building Occupants,

On Thursday, August 31, 2017, through September 21, 2017, CPFM Facilities Service Staff will be performing preventative Maintenance asset field verification in Klamath Hall.  There will be no interruptions of services.  They may enter your spaces to inspect building equipment.

For questions or concerns about this field verification or to report a sensitive research area, please contact CPFM Zone D Maintenance Manager Kevin Farthing at 541-346-2857.

9/13/17: Hayward East Grandstand Preventative Maintenance Work Impacting Air Handling Units

Building Occupants,

Due to scheduled preventative maintenance on the Hayward East Grandstand HVAC equipment, building occupants should expect intermittent shutdowns on air handling units and restroom exhaust fans to allow crews to change system filters. This scheduled work will be taking place on Wednesday, September 13, 2017, from 8:00 am – 3:30 pm.

For questions on how this may impact your services, please contact CPFM Facilities Services Zone A Maintenance Manager Jim Cody  541-346-2302.

9/13/17: Bowerman Preventative Maintenance Work Impacting Air Handling Units

Building Occupants,

Due to scheduled preventative maintenance on the Bowerman HVAC equipment, building occupants should expect intermittent shutdowns on air handling units and restroom exhaust fans to allow crews to change system filters. This scheduled work will be taking place on Wednesday, September 13, 2017, from 8:00 am – 3:30 pm.

For questions on how this may impact your services, please contact CPFM Facilities Services Zone A Maintenance Manager Jim Cody  541-346-2302.

8/30/17: Informational Notice: Klamath Hall Space Survey

Building Occupants,

On Wednesday, August 30, 2017, from approximately 10:00 am – 12:00 pm (noon) consultants will be walking through Klamath Hall surveying spaces.  There will be no interruptions of services.  They may enter your spaces for visual confirmation only.

For questions or concerns about this survey, please contact CPFM Design and Construction Research Manager Jen Miley at 541-346-1530.

11/16/17: Oregon Hall Renovations- Project Status Update

Below are reminders of previously scheduled shutdowns and Phase 2 Construction details.

November 16 6:30 pm – 10:00 pm After-hours electrical shutdown to panel 342 (near the freight elevator). This electrical shut-down is limited to specific 3rd Floor West areas: offices 333A-E, break-room area 333 (fridge & water heater), workstations 330, receptacles in 342, and roof top receptacles. Please turn off electronic equipment in these areas

Saturday, November 18 7:00 am – 3:30 pm Electrical shutdown to basement electrical gear to provide electrical feed to new roof-top HVAC equipment. These systems will not be in service during the shut-down: Passenger Elevators, Freight Elevator, Building Heating System and Domestic Hot Water.

Ongoing – Ending December 22 Daily Construction activities continue on the 1st Floor West. The work is scheduled to be complete 12/22/17. Window and storefront replacement has encountered additional delays from the glass manufacturers. The south storefront is scheduled to be complete the first week of December, we are scheduled to open the covered bike parking by Monday 12/4/17. Please continue to use available bike parking on the west side of the building and adjacent to Deschutes Hall.

Phase 2 Construction

There will be a series of moves over winter break (12/17/17-1/3/18) to clear areas 2W and 3W for major renovations.

Phase 2 Construction Schedule:

Abatement and demolition activities for 2W and 3W are scheduled following the moves.

Room Construction Dates (subject to modifications)
2W 1/4/18 – 7/9/18
3W 12/27/18 – 8/6/18
1E 2/9/18 – 3/30/18
2E 4/3/18 – 5/23/18
3E 5/24/18 – 7/20/18
4E 7/24/18-9/13/18

___________________________________________________________________________________________________________________

Update 10/20/17:

Heating System Update: Hydronic pumps were delivered this week and are being installed. This Saturday (10/21) 7AM-5PM the existing hydronic pipes will need to be flushed and refilled. Workers will be accessing each floor to drain the heating water. Next week, beginning 10/23 we will be circulating hot water to building HVAC equipment. There will be testing, balancing, and adjustments being made all next week to work out any issues. All areas should have heat back on-line by the end of the week (10/27).

 

Chilled Water Infrastructure Update: Chilled water infrastructure is also being replaced within the building but won’t be back online for several weeks. We are using outside air to cool the building and will continue to adjust the amount of outdoor air to provide cooler indoor temperatures in the afternoon. We appreciate your patience as we make these infrastructure improvements to the building.

 

First Floor West Side Update: First Floor west side is still under construction and is using a temporary heating system to provide adequate indoor conditions for the sheetrock, joint compound, painting activities, and millwork. The temporary equipment is situated on the west side of the building. We are coordinating with EH&S to ensure there are no safety concerns with the interim heat.

 

First-Floor Windows and Storefront Replacement Update: First-floor windows and storefront replacement has been delayed due to material delays and unexpected conditions. We hope to have all the window and storefront work complete by 11/17. We will then be able to open up the covered bike parking. In the meantime, please use available parking on the west side of the building and adjacent to Deschutes Hall.

 

Please let me know if you have any questions.

Thank you,

Patrick Mucker
Owner’s Representative
Campus Planning and Facilities Management
University of Oregon
541-346-8216 office
541-517-2497 cell

___________________________________________________________________________________________________________

Update 10/9/17: Oregon Hall Renovations- Construction Update

Saturday 10/14, 7AM-Noon; Fortis will be using a crane to lift large mechanical equipment up to the western portions of the roof.  We request the west portions of the building (all floors) be unoccupied during this activity (10/14, 7AM-Noon).  Please let me know immediately if we need to modify our crane pick around other scheduled activities.

Heating and Cooling Systems-As part of the renovations, the project is replacing the hydronic piping for both the heating water systems and chilled water systems.  Currently, both the heating and cooling systems are off-line as we replace the aging infrastructure.  We are scheduled to have the heating system functioning by Friday 10/20 and the cooling systems functioning by Friday 10/27.  Until then, the building will be cool in the morning and heat up during the day since we are circulating a combination of outside air and make-up air.  We are monitoring the temperatures and making adjustments to the air flow to try to accommodate the cold mornings and warm afternoons.

Construction continues on First Floor West which is scheduled to be complete 12/22/17.  We will then have a series of moves over Winter Break to prepare for the next phase of construction.  More details to come.

Fortis will begin working a night shift and weekends to complete activities that require access into occupied areas of the building.  They will also be working on the roof to deliver roof curbs and roof-top equipment.

Window and Storefront Replacement continues on 1st Floor West- Currently the crews are working on the west and south sides.  When the work is complete on the south, the temporary walls will be removed and access will be available to the covered bike racks.

Let me know if you have any questions.

Thank you,

Patrick Mucker
Owner’s Representative
Campus Planning and Facilities Management
University of Oregon
541-346-8216 office
541-517-2497 cell

____________________________________________________________________________________________________________________

10/2/17: New Update!

Building Occupants,

Construction continues on First Floor West which is scheduled to be completed 12/22/17.  We will then have a series of moves over Winter Break to prepare for the next phase of construction.  More details to come.

Fortis will begin working a night shift and weekends to complete activities that require access to occupied areas of the building.  They will also be working on the roof to deliver roof curbs and roof-top equipment.

Window and Storefront Replacement continues on 1st Floor West- Currently, the crews are working on the west and south sides.  When the work is complete on the south, the temporary walls will be removed, and access will be available to the covered bike racks.

Dates Time Activity
10/2 – 10/6 6:00 PM – 5:00 AM There will be night work to remove ceiling tile outside the new mechanical room to begin installation of pipe hangers and pipe to feed the new mechanical equipment
10/5 6:00 AM – 7:30 AM Early morning work to deliver curbs to the roof with a crane.  The crane will park in the North Construction area and hoist material to the roof over the northwest portions of the roof.  We request the northern portions of the 2nd Floor West (under roof) and 3rd Floor West to be unoccupied during this time (10/5, 6:00 AM-7:30 AM).  I am coordinating with International Affairs and Enrollment Management.  Please let me know immediately if we need to modify our early morning work.
10/4 – 10/5 Fortis will be working on the roof in preparation for the delivery on 10/5
Saturday 10/7 Fortis will be cutting sections of the roof to coordinate for the new rooftop equipment.  This will impact areas of 3rd Floor West.
Saturday 10/14 7:00 AM – Noon Fortis will be using a crane to lift large roof-top equipment.  We request the western portions of the building (all floors) be unoccupied during this activity (10/14, 7AM-Noon).  Please let me know immediately if we need to modify our crane pick around other scheduled activities.

For questions or concerns please contact CPFM Design and Construction Owners Representative Patrick Mucker 541-346-8216 (office) 541-517-2497 (cell).

 

 

______________________________________________________________________________________________________________

August Update:

Building Occupants,

Oregon Hall Renovations- Project Status Update:

1. Demo and Construction Activities continue on 1st Floor West

2. Due to safety concerns, we need to restrict non-essential personnel at the loading dock/ construction staging area. Please refrain from using the north loading dock entrance to enter and leave the building, please use the south main entrance. New signs will be placed restricting traffic through the loading dock (the north building exits will be emergency only). New site fencing will be installed Tuesday 8/29 to restrict access at the loading dock, see attached Loading Dock Fence Plan.

3. Window/ Storefront replacement on 1st Floor West, south elevation, is scheduled from 8/31-9/24. During this time temporary safety and security walls will be built around the covered bike parking (see attached plan). The covered bike parking will not be available from 8/31-9/24. Please use the bike parking adjacent to the raised plaza or along Deschutes Hall.

4. Loud Construction activities are scheduled before and after normal working hours (before 7 AM and after 6 PM) and during weekends

We appreciate your patience during construction activities.

Thanks,
Patrick

Patrick Mucker
Owner’s Representative
Campus Planning and Facilities Management
University of Oregon
541-346-8216 office
541-517-2497 cell

Window Replacement 1W Plan-yef69p

Loading Dock Fence Plan 08.22.2017-2bhldmg

8/26 & 9/9: CPFM Administration Building #136 Exterior Roof Work

Building Occupants,

For the next two weekends, August 26 – 27, 2017 and September 9 – 10, 2017, CPFM Facilities Services will be applying a sealer coating on the roof of the CPFM Administration Building #136.

Please remember to close your windows before leaving on Friday.

For questions or concerns about how this may impact your area, contact CPFM Zone B Maintenance Manager Bruce Budzik at 346-8834.

Informational Notice Regarding Pacific Hall Roofing and Painting Projects

Building Occupants,

There will be roof work on Pacific Hall starting August 28, 2017, and ending on September 1, 2017. Users may experience strong odors during this time, especially through open windows.

From August 24, 2017, through September 6, 2017, there will also be painting occurring within the construction zone on the Basement, 1st, & 2nd floors. Andersen Construction will be containing this work area and exhausting directly out of the building, but users may experience some residual odors.

For questions, concerns please contact CPFM Design and Construction Project Manager Nick Pritchard 541-346-9139.

8/24/17: Pacific Hall Construction Activities Third Floor Corridor

Building Occupants,

There will be work occurring in the third-floor corridor of Pacific Hall starting at 7:00 pm on August 24, 2017, and finishing by 6:00 am on August 25, 2017.  Plastic sheeting will be partially obstructing the corridor near the Onyx Bridge connection and Pacific stairwell.  A pathway will be maintained at all times.

For questions, concerns please contact CPFM Design and Construction Project Manager Nick Pritchard 541-346-9139.

 

9/22 – 9/23: Steam, City Water and Air Shutdown Impacting Pacific, Columbia, Volcanology and Cascade

Building Occupants,

On Friday, September 22 starting at 4:00 pm through 8:00 pm on Saturday, September 23, 2017, steam will be temporarily shut down impacting services to Pacific, Columbia, Volcanology, and Cascade.  On Saturday, September 23, 2017 the city water services and service air will be temporarily shut down to facilitate the steam work. All utilities will be back on by 8:00 pm Saturday, September 23, 2017.  This is necessary as part of the ongoing Steam Tunnel Project.  Utilities and Energy will be replacing a failing 16” expansion joint in the campus tunnel system.

For questions or concerns about how this may impact your building services, please contact CPFM Utilities and Energy Supervisor Mo Soleimani at 541-346-2213 or CPFM Zone B Maintenance Manager Bruce Budzik at 541-346-8834.

9/9/17: Pacific Hall South Wing Building Closure Due to Crane Staging

Building Occupants,

Due to crane staging related to construction activities on the west side of Pacific Hall, the entire South Wing will have to be vacated on Saturday, September 9, 2017, from 5:00 am – 5:00 pm to ensure the safety of building occupants. The North Wing will remain open. If any users require access to the building, it must be coordinated with CPFM Design and Construction ahead of time.

For questions, concerns or building entry coordination please contact CPFM Design and Construction Project Manager Nick Pritchard 541-346-9139.

8/30/17: Instructions for Klamath Hall, Cascade Hall and the Science Library Fume Hoods During Preventative Maintenance Work

Building Occupants,

On Wednesday, August 30, 2017, from 8:00 am – 12:00 pm CPFM Personnel will be performing preventative maintenance on the air handlers that service Klamath Hall, Cascade Hall, and the Science Library.  During the hours listed, please keep lap doors open for make-up air to the fume hoods.

For questions or concerns about how this may impact your area, contact CPFM Facilities Services Zone B Maintenance Manager Bruce Budzik at 346-8834.

8/29/17: Walton Steam Outage

Building Occupants,

On Tuesday, August 29, 2017 from 7:30 am – 9:30 am the small 60# steam line that services Walton will be temporarily shut down.  This will impact the basement clothing dryers.

For questions regarding this outage please contact CPFM Utilities and Energy Maintenance Supervisor Mo Soleimani at 541-346-2213.

8/26/17: Power Outage Impacting Susan Campbell, Hendricks and Gerlinger

Building Occupants,

Due to the Collier House transformer relocation power will be temporarily shut down impacting Susan Campbell, Hendricks and Gerlinger on Saturday, August 26, 2017 from 8:00 am – 12:00 pm.

For questions or concerns contact CPFM Design and Construction Owners Representative Jana Gerow at 541-346-8317 or  CPFM Utilities and Energy Electrical Supervisor Rick Tabor at 541-346-7511.

9/5/17: Allen Hall Standby Transformer Maintenance 9/5

Building Occupants,

Due work associated with the normal feeder Utilities and Energy will be performing maintenance on the standby Transformer Tuesday, September 5, 2017, from 6:00 am – 7:00 pm.  This should not impact building occupants.  In the event of an emergency, U&E will manually engage the feeder back online at the switch house.

For questions or concerns contact CPFM Utilities and Energy Electrical Supervisor Rick Tabor at 541-346-7511.

 

9/5/17: Frohnmayer Music and Berwick Power Outage

Building Occupants,

Due work associated with the normal feeder Utilities and Energy will have the Frohnmayer Music Building on standby power, and Berwick will experience a power outage on Tuesday, September 5, 2017, from 5:00 am – 7:00 am

For questions or concerns contact CPFM Utilities and Energy Electrical Supervisor Rick Tabor at 541-346-7511.

 

8/18 – 8/25: Parking Lot #25 Closures

Campus Community,

As part of the Collier Parking Lot and Tykeson Hall construction work, Parking Lot #25 will be closed this weekend starting at 5:00 pm on Friday, August 18, 2017, through 5:00 pm Saturday, August 19, 2017.  This is necessary as part of the tree removal work.

Due to ongoing construction activities associated with driveway work between Johnson Lane and Lot #25 Parking Lot #25 will experience daily closures 7:00 am – 5:30 pm next week starting Monday, August 21, 2017, through Friday, August 25, 2017.  Parking Lot #25 will open up each night after 5:30 pm and be made accessible for access to the loading dock.

For questions or concerns regarding this closure please contact CPFM Design and Construction Owners Representative Martina Oxoby at 541-346-5880.

8/25/17: Klamath 2nd and 3rd Floor Water Shutdown

Building Occupants,

On Friday, August 25, 2017, from 4:00 am – 8:00 am Andersen Construction will be temporarily turning the water off in Klamath Hall that services the 2nd and 3rd floors.  Water will be turned off on the 2nd floor at the North end of the corridor which will also affect the third floor. If you have any questions, concerns or notice unidentified building smells please contact Joe Hubbard with Andersen Construction at 541-514-5794 after hours. 

 If you have any questions or concerns about the project, please reach out to CPFM Design and Construction Owners Representative Jana Gerow at 541-346-8317

8/25 – 8/27: Friendly Hall Electrical Shutdown

Building Occupants,

Due to the replacement of an existing transformer, Friendly Hall will temporarily be without power Friday, August 25, 2017, starting at 5:00 pm through Sunday, August 27, 2017, at 5:00 pm.

For questions or concerns contact CPFM Design and Construction Owners Representative Jana Gerow at 541-346-8317 or  CPFM Utilities and Energy Electrical Supervisor Rick Tabor at 541-346-7511.

UPDATE [NOW INCLUDING GERLINGER AND GERLINGER ANNEX] Chilled Water Shutdown Various Zone A Buildings

Update:

Building Occupants,

In addition to the extension that went out, earlier this week contractors discovered this afternoon the scheduled shutdown is also impacting Gerlinger and Gerlinger Annex.

We apologize for any inconvenience this may cause and appreciate your patience.

For questions on how this may impact your services, please contact Jana Gerow CPFM Design and Construction Owners Representative 541-346-8317or Mo Soleimani CPFM Utilities and Energy Maintenance Supervisor 541-346-2213.

____________________________________________________________

Update:  This shutdown has been extended until noon on Sunday, August 27, 2017.

 

For questions on how this may impact your services please contact Jana Gerow CPFM Design and Construction Owners Representative 541-346-8317or Mo Soleimani CPFM Utilities and Energy Maintenance Supervisor 541-346-2213.

____________________________________________________________

 

Building Occupants,

On August 26, 2017, the chilled water will be turned off that services the Knight Library, Lokey Education, Hedco Education, Education Annex, Clinical Services, Frohnmayer Music and Berwick Hall from 6:00 am – 6:00 pm.  This temporary shutdown is necessary to allow piping from the tunnel to the Knight Library equipment room to be put in place in anticipation of adding two pumps for chilled water.   This will affect air conditioning services that are supplied by chilled water.

For questions on how this may impact your services please contact Jana Gerow CPFM Design and Construction Owners Representative 541-346-8317or Mo Soleimani CPFM Utilities and Energy Maintenance Supervisor 541-346-2213.

8/31/17: Lawrence Hall 60 Pound Steam Shutdown

Building Occupants,

On Thursday, August 31st, from 7:00 am until 4:00 pm, Lawrence Hall 60 pound steam will be shut down.

There will be no access to hot water or building heat.

Work will be performed by a contractor.

For questions or concerns about how this may impact your area, contact Mo Soleimani, Campus Planning and Facilities Management (CPFM) Utilities Maintenance Supervisor at 346-2213.