9/21/17: Huestis Heating and Cooling Supply Air Shutdown

Building Occupants,

On Thursday, September 21, 2017, the heating and cooling supply air will be temporarily shut down in Huestis while contractors replace a building fan.  This shutdown will begin at 6:00 am and last for one day.

Special Instructions:  When SF 1A and 1B are shut down for the day, it will affect the supply air to the below-listed rooms. This will not shut down fume hood exhaust, but because there will not be supply air, these steps need to be followed in the fume hoods.

  1. Seal all open chemical storage in the fume hood.
  2. Keep fume hood sash closed during the shutdown period.

Impacted Areas:

1st Floor: 111, 111A, 111B, 111C, 129, 129A, 129B, 129C

2nd Floor:  209, 209A, 209B, 209C, 211A, 227A, 229A, 233B, 233C, 233D, 233E

3rd Floor:  305, 305A, 305B, 305C, 311A, 313A, 327A, 337, 337A, 337B, 337C, 337D

For questions or concerns please contact CPFM Zone B Maintenance Manager Bruce Budzik at 541-346-8834.