11/16/17: Oregon Hall Renovations- Project Status Update

Below are reminders of previously scheduled shutdowns and Phase 2 Construction details.

November 16 6:30 pm – 10:00 pm After-hours electrical shutdown to panel 342 (near the freight elevator). This electrical shut-down is limited to specific 3rd Floor West areas: offices 333A-E, break-room area 333 (fridge & water heater), workstations 330, receptacles in 342, and roof top receptacles. Please turn off electronic equipment in these areas

Saturday, November 18 7:00 am – 3:30 pm Electrical shutdown to basement electrical gear to provide electrical feed to new roof-top HVAC equipment. These systems will not be in service during the shut-down: Passenger Elevators, Freight Elevator, Building Heating System and Domestic Hot Water.

Ongoing – Ending December 22 Daily Construction activities continue on the 1st Floor West. The work is scheduled to be complete 12/22/17. Window and storefront replacement has encountered additional delays from the glass manufacturers. The south storefront is scheduled to be complete the first week of December, we are scheduled to open the covered bike parking by Monday 12/4/17. Please continue to use available bike parking on the west side of the building and adjacent to Deschutes Hall.

Phase 2 Construction

There will be a series of moves over winter break (12/17/17-1/3/18) to clear areas 2W and 3W for major renovations.

Phase 2 Construction Schedule:

Abatement and demolition activities for 2W and 3W are scheduled following the moves.

Room Construction Dates (subject to modifications)
2W 1/4/18 – 7/9/18
3W 12/27/18 – 8/6/18
1E 2/9/18 – 3/30/18
2E 4/3/18 – 5/23/18
3E 5/24/18 – 7/20/18
4E 7/24/18-9/13/18

___________________________________________________________________________________________________________________

Update 10/20/17:

Heating System Update: Hydronic pumps were delivered this week and are being installed. This Saturday (10/21) 7AM-5PM the existing hydronic pipes will need to be flushed and refilled. Workers will be accessing each floor to drain the heating water. Next week, beginning 10/23 we will be circulating hot water to building HVAC equipment. There will be testing, balancing, and adjustments being made all next week to work out any issues. All areas should have heat back on-line by the end of the week (10/27).

 

Chilled Water Infrastructure Update: Chilled water infrastructure is also being replaced within the building but won’t be back online for several weeks. We are using outside air to cool the building and will continue to adjust the amount of outdoor air to provide cooler indoor temperatures in the afternoon. We appreciate your patience as we make these infrastructure improvements to the building.

 

First Floor West Side Update: First Floor west side is still under construction and is using a temporary heating system to provide adequate indoor conditions for the sheetrock, joint compound, painting activities, and millwork. The temporary equipment is situated on the west side of the building. We are coordinating with EH&S to ensure there are no safety concerns with the interim heat.

 

First-Floor Windows and Storefront Replacement Update: First-floor windows and storefront replacement has been delayed due to material delays and unexpected conditions. We hope to have all the window and storefront work complete by 11/17. We will then be able to open up the covered bike parking. In the meantime, please use available parking on the west side of the building and adjacent to Deschutes Hall.

 

Please let me know if you have any questions.

Thank you,

Patrick Mucker
Owner’s Representative
Campus Planning and Facilities Management
University of Oregon
541-346-8216 office
541-517-2497 cell

___________________________________________________________________________________________________________

Update 10/9/17: Oregon Hall Renovations- Construction Update

Saturday 10/14, 7AM-Noon; Fortis will be using a crane to lift large mechanical equipment up to the western portions of the roof.  We request the west portions of the building (all floors) be unoccupied during this activity (10/14, 7AM-Noon).  Please let me know immediately if we need to modify our crane pick around other scheduled activities.

Heating and Cooling Systems-As part of the renovations, the project is replacing the hydronic piping for both the heating water systems and chilled water systems.  Currently, both the heating and cooling systems are off-line as we replace the aging infrastructure.  We are scheduled to have the heating system functioning by Friday 10/20 and the cooling systems functioning by Friday 10/27.  Until then, the building will be cool in the morning and heat up during the day since we are circulating a combination of outside air and make-up air.  We are monitoring the temperatures and making adjustments to the air flow to try to accommodate the cold mornings and warm afternoons.

Construction continues on First Floor West which is scheduled to be complete 12/22/17.  We will then have a series of moves over Winter Break to prepare for the next phase of construction.  More details to come.

Fortis will begin working a night shift and weekends to complete activities that require access into occupied areas of the building.  They will also be working on the roof to deliver roof curbs and roof-top equipment.

Window and Storefront Replacement continues on 1st Floor West- Currently the crews are working on the west and south sides.  When the work is complete on the south, the temporary walls will be removed and access will be available to the covered bike racks.

Let me know if you have any questions.

Thank you,

Patrick Mucker
Owner’s Representative
Campus Planning and Facilities Management
University of Oregon
541-346-8216 office
541-517-2497 cell

____________________________________________________________________________________________________________________

10/2/17: New Update!

Building Occupants,

Construction continues on First Floor West which is scheduled to be completed 12/22/17.  We will then have a series of moves over Winter Break to prepare for the next phase of construction.  More details to come.

Fortis will begin working a night shift and weekends to complete activities that require access to occupied areas of the building.  They will also be working on the roof to deliver roof curbs and roof-top equipment.

Window and Storefront Replacement continues on 1st Floor West- Currently, the crews are working on the west and south sides.  When the work is complete on the south, the temporary walls will be removed, and access will be available to the covered bike racks.

Dates Time Activity
10/2 – 10/6 6:00 PM – 5:00 AM There will be night work to remove ceiling tile outside the new mechanical room to begin installation of pipe hangers and pipe to feed the new mechanical equipment
10/5 6:00 AM – 7:30 AM Early morning work to deliver curbs to the roof with a crane.  The crane will park in the North Construction area and hoist material to the roof over the northwest portions of the roof.  We request the northern portions of the 2nd Floor West (under roof) and 3rd Floor West to be unoccupied during this time (10/5, 6:00 AM-7:30 AM).  I am coordinating with International Affairs and Enrollment Management.  Please let me know immediately if we need to modify our early morning work.
10/4 – 10/5 Fortis will be working on the roof in preparation for the delivery on 10/5
Saturday 10/7 Fortis will be cutting sections of the roof to coordinate for the new rooftop equipment.  This will impact areas of 3rd Floor West.
Saturday 10/14 7:00 AM – Noon Fortis will be using a crane to lift large roof-top equipment.  We request the western portions of the building (all floors) be unoccupied during this activity (10/14, 7AM-Noon).  Please let me know immediately if we need to modify our crane pick around other scheduled activities.

For questions or concerns please contact CPFM Design and Construction Owners Representative Patrick Mucker 541-346-8216 (office) 541-517-2497 (cell).

 

 

______________________________________________________________________________________________________________

August Update:

Building Occupants,

Oregon Hall Renovations- Project Status Update:

1. Demo and Construction Activities continue on 1st Floor West

2. Due to safety concerns, we need to restrict non-essential personnel at the loading dock/ construction staging area. Please refrain from using the north loading dock entrance to enter and leave the building, please use the south main entrance. New signs will be placed restricting traffic through the loading dock (the north building exits will be emergency only). New site fencing will be installed Tuesday 8/29 to restrict access at the loading dock, see attached Loading Dock Fence Plan.

3. Window/ Storefront replacement on 1st Floor West, south elevation, is scheduled from 8/31-9/24. During this time temporary safety and security walls will be built around the covered bike parking (see attached plan). The covered bike parking will not be available from 8/31-9/24. Please use the bike parking adjacent to the raised plaza or along Deschutes Hall.

4. Loud Construction activities are scheduled before and after normal working hours (before 7 AM and after 6 PM) and during weekends

We appreciate your patience during construction activities.

Thanks,
Patrick

Patrick Mucker
Owner’s Representative
Campus Planning and Facilities Management
University of Oregon
541-346-8216 office
541-517-2497 cell

Window Replacement 1W Plan-yef69p

Loading Dock Fence Plan 08.22.2017-2bhldmg