CPFM Warehouse, CPFM Admin, ZIRC, & Lockshop Access 10/15/21
Posted on

Begin:  10/15/21 at 8:00 am

End:      10/15/21 at 3:00 pm

Building(s) or Area(s) Impacted:  CPFM Warehouse, CPFM Admin, ZIRC, Lockshop

Scope:  Approximately 12 concrete trucks will be routed between the CPFM warehouse and CPFM admin building for the ZIRC slab concrete pour. Trucks will be staged outside parking area to minimize disruption to traffic flow.

Services Impacted: Roadways will still be open to traffic, it will just be congested.

Work Performed By: Fortis Construction

Contact: Colin Brennan, CPFM Owner’s Representative, 541-346-8242 or 541-654-2972

 

Lokey Education Building (A&B) Domestic Water Shutdown 10/8/21
Posted on

Begin:  Friday, October 8th, 2021 at 7:00 am

End:      Friday, October 8th, 2021 at 7:30 am

Building(s) or Area(s) Impacted:  Lokey Education Building (A & B)

Scope:  The domestic water will be shut down while EWEB replaces a water meter.  The process should take approximately 15-30 minutes to complete.

Services Impacted:  Domestic water will be offline during this time, affecting sinks, drinking fountains, and restrooms.

Work Performed By:  EWEB

ContactRon Warren, CPFM Facilities Plumbing, 541-346-2319