CPFM Warehouse, CPFM Admin, ZIRC, & Lockshop Access 10/15/21

Begin:  10/15/21 at 8:00 am

End:      10/15/21 at 3:00 pm

Building(s) or Area(s) Impacted:  CPFM Warehouse, CPFM Admin, ZIRC, Lockshop

Scope:  Approximately 12 concrete trucks will be routed between the CPFM warehouse and CPFM admin building for the ZIRC slab concrete pour. Trucks will be staged outside parking area to minimize disruption to traffic flow.

Services Impacted: Roadways will still be open to traffic, it will just be congested.

Work Performed By: Fortis Construction

Contact: Colin Brennan, CPFM Owner’s Representative, 541-346-8242 or 541-654-2972