8/7/17 update: Oregon Hall Renovations

Oregon Hall Renovations- Project Status Update

  1. Next week Abatement activities will be completed on First Floor west (Tuesday 8/8) and Fortis Construction will begin construction activities (Wednesday 8/9)
  2. Fortis Construction will be setting up a construction trailer in Lot 14 (north of Oregon Hall) and installing site fencing to create a materials staging area (beginning Monday 8/7)
  3. 2nd Floor- Workspace 220; We have removed the systems furniture and have abatement activities scheduled for the night of Wednesday 8/9. Work will begin at 6 PM and be complete by 6 AM. The plastic containment area will need to be left in place Thursday during air testing. There will be some after hours duct work Monday-Wednesday to support the work. On Saturday 8/12 Fortis will construct walls for the new mechanical room to isolate construction areas from work areas. All loud activities will be scheduled after-hours.
  4. 3rd Floor- Office 342 and Women’s Restroom 341; Abatement activities are scheduled in these areas the night of Thursday 8/10. Work will begin at 6 PM and be complete by 6 AM. The plastic containment area will need to be left in place Friday during air testing. The Women’s Restroom will be closed indefinitely beginning at 6 PM Thursday 8/10 since we are installing roof-top equipment above. We will try to re-open the restroom around construction activities. On Saturday 8/19 Fortis will construct walls for the new electrical room to isolate the construction activities from work areas. All loud activities will be scheduled after-hours.

Information provided by UO Safety and Risk Services:

Asbestos abatement is completed with a controlled environment. Unaffected surfaces are covered with thick plastic sheeting and thoroughly sealed, any penetrations are sealed, and the work area entry is protected by a two flap air lock. Air is constantly removed from the work area through use of a machine called an air filtration unit (AFU). This machine draws air from the work area, forces it through a series of filters, and then exhausts it to the exterior of the building. The final filter is HEPA, which removes 99.97% of particulate measuring .3 microns and smaller. The work area is under negative pressure, meaning that air can’t escape except through our AFU.

You may notice plastic sheeting walls with asbestos signage on them. These are to notify you of a potential hazard inside of the enclosure and are required by OSHA and LRAPA regulations. There also will be a long plastic exhaust duct. This duct carries the filtered exhaust air out of the containment and exhausts it to the building exterior. All of these controls are designed and proven to keep the potential hazard inside of the containment and away from you. If you have any questions or concerns, please contact Environmental Health & Safety at 6-3192.

Please contact me or Adam Jones with any questions.

Patrick Mucker
Owner’s Representative
Campus Planning and Facilities Management
University of Oregon
541-346-8216 office
541-517-2497 cell

 

 

8/17/17: New Residence Hall Crane Work

Campus Users,

On Thursday, August 17th, from 7:00 am until 3:00 pm, we will be placing a sculpture in the new residence hall green space (East of Columbia Street opposite the Olum Center).  We will be placing a mobile crane between the new residence hall and global scholars hall.  This activity should not impact Columbia Street, but please be aware that this overhead activity will be taking place and use caution.  A safety perimeter around the site will be set up, along with flaggers.

Work will be performed by Walsh Construction and Froelick Gallery.

For questions or concerns about how this may affect your area, contact George Bleekman, Campus Planning and Facilities Management (CPFM) Design and Construction at 346-2625.

8/25/17 – 9/9/17: SRC 2nd Floor Locker Rooms + 3rd Floor Restroom Shutdown

Building Occupants,

Beginning Friday, August 25th, until approximately Saturday, September 9th, the Student Rec’s 2nd-floor locker rooms and 3rd-floor restrooms will be closed and isolated to allow for tile replacement.  Work will occur 24/7 during this time.

This will affect the ventilation system in the above mentioned closed areas as the air handler HRV-3 will need to be shut down during this period.

Work will be performed by Howard S. Wright and their tile subcontractors.

For questions or concerns about how this may impact your area, contact Charlene Lindsay, Campus Planning and Facilities Management (CPFM) Design and Construction at 346-5503.

8/5, 8/6, 8/12, 8/13: CPFM Quonset Bldg 136 Exterior Work

Building Occupants,

For the next two weekends, 8/5, 8/6, 8/12, and 8/13, CPFM’s Facility Services will be applying a sealer coating on the roof of the CPFM Administration Building #136.

Also scheduled during this time, between 6:00 am and 4:00 pm, the exterior of this building will be pressure washed and painted.

Please remember to close your windows before leaving on Friday.

For questions or concerns about how this may impact your area, contact Bruce Budzik, Campus Planning and Facilities Management (CPFM) Zone B Maintenance Manager at 346-8834.

7/31/17-8/2/17: Onyx Bridge Demolition and Abatement Work Continues

Building Occupants,

On the evenings of Monday, July  31st and Tuesday, August 1st, from 5:00 pm until the following mornings at 5:00 am, demolition & abatement work needs to continue at Onyx Bridge.  This will affect the 2nd-floor rooms 270, 270A, 271, 272, 278, 279, 280, 281 and 282.

No utilities will be impacted, but there will be noise and some vibration from demolition activities.

Work will be performed by an abatement contractor.

For questions or concerns about how this may impact your area, contact Denise Stewart, Campus Planning and Facilities Management (CPFM) Design and Construction at 346-2280.

 

8/11/17-8/14/17: Ford Alumni and Columbia Parking Garage Chilled Water Shutdown

Building Occupants,

On Friday, August 11th, at 7:00 am until Monday, August 14th, at 10:00 am, Ford Alumni and Columbia Parking Garage chilled water will be shut down to repair a leak in the chilled water return line.

Since this will affect the HVAC cooling systems, there will be no air conditioning during this time.

Work will be performed by CPFM’s Facilities Services.

For questions or concerns about how this may impact your area, contact Kevin Farthing, Campus Planning and Facilities Management (CPFM) Zone D Maintenance Manager at 346-2857.

8/4/17: University Health Center Steam Shutdown

Building Occupants,

On Friday, August 4th, from 7:00 am to 4:00 pm, all steam to the University Health Center building will be shut down.  This is due to asbestos abatement in the underground tunnels adjacent to the Health Center.

This will affect autoclave steam, heating, and steam condensate.

For questions or concerns about how this may impact your area, contact Kevin Farthing, Campus Planning and Facilities Management (CPFM) Zone D Maintenance Manager at 346-2857.

8/10/17: Fenton Hall Electrical Shutdown

Update:

The Fenton Hall power shutdown is scheduled in the early morning from 6:00 am to 7:00 am.

Building Occupants,

On Thursday, August 10th, electricity to Fenton Hall will be shut down briefly to allow a power swap to the new transformer in Chapman.

Work will be performed by Fortis Construction.

For questions or concerns about how this may affect your area, contact Gene Mowery, Campus Planning and Facilities Management (CPFM) Design and Construction at 346-5593.

08/22 – 08/23: Series of Brief Electrical Outages Affecting 30 Buildings Across UO Campus

Building Occupants,

 

On August 22 – 23, during the hours of 4:00 am – 6:00 am the below listed buildings will temporarily be without power for approximately 10 minutes each. Transformers will be turned off allowing Utilities and Energy to collect fuse sizes of the transformers allowing the arc flash study to be completed.

For questions or concerns contact CPFM Utilities and Energy Electrical Supervisor Rick Tabor at 541-346-7511.

 

SHUTDOWN SCHEDULE FOR 8/22/17

ZONE BUILDING FEEDER TIME DATE
TYPE
A JANE SANDERS FIELD Normal 4:00 am 8/22/17 T
A JANE SANDERS FIELD Standby 4:10 am 8/22/17
A MAC COURT Normal 4:20 am 8/22/17 E
A REC CENTER Normal 4:30

am

8/22/17
A REC CENTER Standby 4:40

am

8/22/17 A
A BOWERMAN Normal 4:50

am

8/22/17
A STRAUB HALL Normal 5:00

am

8/22/17 M
A STRAUB HALL Standby 5:10

am

8/22/17
A/D EARL   (XFMR is ‘A’ / Building is ‘D’) Normal 5:20 am 8/22/17
A EMU Normal 5:30

am

8/22/17 “A”
A EMU Normal 5:40

am

8/22/17
A EMU Standby 5:50

am

8/22/17
D JAQUA Normal 4:00

am

8/22/17 T
D JAQUA Standby 4:10

am

8/22/17
D ALUMNI Normal 4:20

am

8/22/17 E
D ALUMNI Standby 4:30

am

8/22/17
D HAMILTON – WEST Normal 4:40

am

8/22/17 A
D BEAN Normal 4:50

am

8/22/17
D GLOBAL SCHOLARS Normal 5:00

am

8/22/17 M
D GLOBAL SCHOLARS Standby 5:10

am

8/22/17
D LONGHOUSE / OLUM Normal 5:20

am

8/22/17
D MUSEUM OF NATURAL HISTORY Normal 5:30

am

8/22/17 “B”
D KNIGHT LAW Normal 5:40

am

8/22/17
 

 

 

SHUTDOWN SCHEDULE FOR 8/23/17

 

 

 

ZONE BUILDING FEEDER TIME DATE
TYPE
B LISB Normal 4:00

am

8/23/17 T
B LISB Normal 4:05

am

8/23/17
B LISB Standby 4:10

am

8/23/17 E
D OREGON HALL Normal 4:20

am

8/23/17
D OREGON HALL Standby 4:30

am

8/23/17 A
D STUDENT HEALTH Standby 4:40

am

8/23/17
D STUDENT HEALTH Standby 4:50

am

8/23/17 M
D WALTON – NORTH Normal 5:00

am

8/23/17
D WALTON – SOUTH Normal 5:10

am

8/23/17
D LLC Normal 5:20

am

8/23/17
D LLC Standby 5:30

am

8/23/17 “A”
D CARSON HALL Normal 5:40

am

8/23/17
D CARSON HALL Standby 5:50

am

8/23/17
B FACILITIES QUANSET Standby 4:00

am

8/23/17 T
B ZEBRAFISH STOCK CENTER Standby 4:10

am

8/23/17
B HEUSTIS Normal 4:20

am

8/23/17 E
B ISC ONAMI Normal 4:25

am

8/23/17
B ISC ONAMI Standby 4:30

am

8/23/17 A
B ONYX BRIDGE RM 68 Normal 4:40

am

8/23/17
B VOLCANOLOGY Normal 4:50

am

8/23/17 M
D LAWRENCE HALL Normal 5:00

am

8/23/17
D LAWRENCE HALL – PRINT SHOP Normal 5:10

am

8/23/17
A PLC BASEMENT ROOM 50 Normal 5:20

am

8/23/17
A PLC Standby 5:30

am

8/23/17 “B”
A HEDCO EDUCATION Normal 5:40

am

8/23/17
A HEDCO EDUCATION Standby 5:50

am

8/23/17

 

This message was sent to users of the below highlighted buildings.

 

Postponed New Date: 13th Street Closure by Carson Hall 8/19/17

Campus Community,

On August 15, 2017, August 19, 2017 a section of 13th street will be closed from 6:30 am – 1:00 pm to accommodate crane staging associated with the roof mount chiller replacement at Carson Hall.

For questions or concerns, please contact Director of Housing Facilities Services Greg Ottoman at 541-346-6794 or Housing Facilities Manager Judd Mentzer at 541-346-5594.  This is a UHDS project.

07/26/17: Lillis Business Complex Fire Horn/Strobe System Testing

Building Occupants,

Due to reprogramming that happened today, July 25, Safety and Risk Services needs to the test horn/strobes on the fire system tomorrow July 26, 2017, at the Lillis Business Complex.  This will be a very brief test between 6:00 am – 7:00 am.  Nothing else will be impacted including the elevator.

Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, http://emc.uoregon.edu/node/50 and follow the UO Campus Emergency Procedures Manual.

You may also call Zach Earl with Safety and Risk Services at 541-346-9295 if you have any questions or concerns.

08/03/17: Onyx Bridge and Pacific Hall RO System Outage

Building Occupants,

On Thursday, August 3, 2017,  from 8:00 am – 4:00 pm the RO Water that services Onyx Bridge and Pacific Hall will be temporarily shut down while crews install a new value in the penthouse in Onyx Bridge.  This allows Onyx Bridge and Pacific Hall to be isolated from each other so lines can be capped off as part of the Onyx Bridge second floor remodel project.

For questions or concerns, contact CPFM Facilities Services Zone B Maintenance Manager Bruce Budzik at 346-8834.

08/09/17: Allen Hall Electrical Outage

Building Occupants,

On August 9, 2017, from 3:30 am – 4:00 am the normal power transformer will be off at Allen Hall while Utilities and Energy make configuration changes.  The standby transformer will be off intermittently from 4:00 am – 8:00 am  while crews do testing  to determine the vector group of that transformer.  Standby work should not affect building users. The data center will be radial fed during the testing.

For questions or concerns contact CPFM Utilities and Energy Electrical Supervisor Rick Tabor at 541-346-7511.

07/25 – 7/28: Onyx Bridge 2nd Floor Noise and Vibration Due to Construction Activities

Additional Information from Safety and Risk Services

PMG will begin asbestos abatement and demolition work in the second floor of Onyx Bridge tonight, including rooms 270, 270A, 271, 272 (west portion), 278, 279, 280, 281, and 282.  This work will be done from 5 pm to 5 am to avoid disruption to building occupants.  The hallway will not be blocked for this work.  The contractor will be removing casework, fume hoods, non-asbestos flooring, and a few CMU walls.

Please let me know if you have any questions or concerns.

__________________________________

Mike Eldredge Asbestos Program Manager
http://ehs.uoregon.edu
Safety and Risk Services | University of Oregon
5224 University of Oregon | Eugene, OR 97403-5224
Office: 541.346.2908| Fax: 541.346.7010
cellular 541.206.4488|
______________________________________

Building Occupants,

Due to construction, Onyx Bridge building occupants should expect noise and some vibration from demolition activities July 25 – 28, 2017.  Rooms impacted are: 270, 270A, 271, 272, 278, 279, 280, 281 and 282.  Work will occur between 5 pm and 5 am for the remainder of the week.  There will be no impacts to utility services.  A progress update will be sent on Friday, July 28th if work needs to continue into next week.

For questions or concerns, please contact CPFM Design and Construction Owners Representative Denise Stewart at 541-346-2280.

07/31 – 08/04: Hendricks Steam Valve Work

Building Occupants,

Steam work on the valves in the north basement of Hendricks will continue July 31 – August 4, 2017.  This will affect heating services.  Expect mild noise and construction activities from the contractor MacDonald-Miller.

For questions or concerns please contact CPFM Facilities Services Zone A Maintenance Manager Jim Cody at 541-346-2302

08/09/17: Frohnmayer Music Preventative Maintenance

Building Occupants,

Due to scheduled preventative maintenance on the Music HVAC equipment, building occupants should expect intermittent shutdowns on air handling units and restroom exhaust fans to allow crews to change system filters. This scheduled work will be taking place on Wednesday, Aug 9, from 8:00 am – 3:30 pm.

For questions or concerns please contact CPFM Facilities Services Zone A Maintenance Manager Jim Cody at 541-346-2302

Pacific Hall Building Closure 7/26/17 6:00 am – 7:00 am

Building Occupants,

Pacific Hall will close for approximately one hour, this Wednesday  morning, July 26, between 6 am and 7 am. This closure is to allow a crane to safely place equipment on the roof, for the Patrick Phillips Lab.

This is a purely precautionary measure, to ensure the safety of the building occupants.  No rooms in Pacific Hall may be occupied during the crane’s operation.

The crane will sit on the West side of Pacific Hall, which will require the temporary removal of select bicycle racks Tuesday and Wednesday and partial closure of the sidewalk, to provide a safe zone for operation. (see below map)

For questions or concerns please contact CPFM Design and Construction Research Project Manager Jen Miley jmiley@uoregon.edu at 541-346-1530.

Update Regarding Oregon Hall Renovations

Building Occupants,

We are gearing up for construction activity at Oregon Hall First Floor West (1W).

Phase 1 work is renovating First Floor West (1W) and adding roof top mechanical equipment to replace west wing HVAC equipment (Phase 1 & 2). We are scheduled to begin HVAC modifications on 1W (to cap and isolate 1W from the building) the week of 7/24. This will support abatement and demolition activities to 1W scheduled to begin 7/26. As part of the new HVAC Roof-Top equipment (September Installation) we will be building a new mechanical pump room in 220 (8/7 start) and a new Electrical Room in 342 (8/24 start).

Fortis construction will install fencing around the back parking lot on 8/7 (click on image for attached site plan). A dumpster will be placed in the west truck bay for construction, and we will leave the east truck bay open for deliveries. The construction gate will remain open during regular business hours for deliveries. Window Replacement to 1W will begin 9/6. There will be site fencing used during the window replacement.

I will provide updates on the construction activities as the project progresses.

Please contact me with any questions.

Thank you,

Patrick Mucker
Owner’s Representative
Campus Planning and Facilities Management
University of Oregon
541-346-8216 office
541-517-2497 cell

07/27/17: HEDCO Clinic Chilled Water Shutdown

Building Occupants,

The chilled water serving the HEDCO Clinic will be shutdown to repair a leak on July 27, 2017 from 5:30 pm – 8:30 pm.

This will impact cooling in the following rooms/areas:

  • 110, 111, 112, 114, 115, 116, 117, 118, 170A, 170B, 177, 180, 180A, 182, 183, 184, 185, 186, 187, 188, 189, 190, 191
  • 241, 242, 243, 244, 245, 246, 258, 260, 261, 262 ,263, 264, 266, 274, 276, 277, H250, H270
  • 306, 307, 307A, 340, 341, 342, 343, 344, 345, 346, 347, 349, 358, 360, 361, 362, 363, 364, 374, 376, 377, H360, H370

For questions or concerns please contact CPFM Facilities Services Zone A Maintenance Manager Jim Cody at 541-346-2302

Notice: Campus Wide Fire Alarm Testing Schedule for 8/1 – 8/15

Building Occupants,

 

Below is the fire alarm testing schedule for August 1 – 15, 2017.

 

BUILDING TESTING DATE TIME
Susan Campbell B0075 8/1/17 6:00 am – 7:00 am
Hendricks Hall B0071 8/1/17 7:00 am – 7:30 am
Volcanology B0015 8/2/17 6:00 am – 7:00 am
Collier House B0081 8/2/17 7:00 am – 7:30 am
Columbia Hall B0036 8/3/17 6:00 am – 7:00 am
Cascade Hall B0036 8/3/17 7:00 am – 7:30am
Deschutes Hall B0044 8/8/17 6:00 am – 7:00 am
Oregon Hall B0042 8/8/17 7:00 am – 7:30 am
Prince Lucien Campbell Hall (PLC) B0008 8/9/17 6:00 am – 7:30 am
Deady Hall B0005 8/10/17 6:00 am – 7:00 am
Villard Hall B0031

(Miller Theatre)

8/10/17 6:30 am – 7:30 am
Zebrafish Stock Center B0101 8/15/17 6:00 am – 7:00 am
McKenzie Hall B0030 8/15/17 6:30 am – 7:30 am

Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time, but there may be an activity such as door holders closing and smoke detector testing that will occur throughout the morning. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, http://emc.uoregon.edu/node/50 and follow the UO Campus Emergency Procedures Manual.

You may also contact Fire Protection Manager Simon Ditton with Safety and Risk Services at 541-346-2958 if you have any questions or concerns.

08/14 – 09/29: Cascade Hall Re-Roof Project Starting

Building Occupants,

Starting August 14, 2017, the Cascade Hall re-roof project will begin and run through September 29, 2017.  There are no anticipated closures, shutdowns or detours anticipated.  There will be noise associated with the removal of the rock ballast from the roof.  It will be noisy at times for about 2-hours each day, with the exception of rock ballast removal which will be all day noise for about 4 – 5 days sometime during the project timeline.  Additional details are listed below as informational.

  • No equipment or systems shutdowns anticipated.
  • No entries will be blocked.
  • Contractors will be working within the already established fenced off work area in conjunction with the contractors already working at the Pacific Hall remodel.
  • There will be a truck brought in each morning that will be stationed within the staging/work zone.
  • Materials will be brought in on the truck and debris will be hauled away on the same truck.
  • The contractor will be using an electric hoist, to cut down on motor/engine noise.

For questions or concerns related to this project contact CPFM Design and Construction Owners Representative  Gene Mowery at 541-346-5593.

 

 

Cascade Hall re-roof notification draft1-2mzk4lg

CASCADE HALL RE-ROOF PROJECT

Cascade Hall will undergo a re-roofing project scheduled to begin Monday, August 14th.  The project should take 6 to 7 weeks to complete.  The re-roof will take place on the flat area of the roof, contained within the center of the building roof area and surrounded by the sloped metal panel clad roofs that you see from the ground and surrounding buildings.

A few details about the project:

  • Working hours will generally be from 6:00am to 3:00pm, Monday through Friday.
  • The staging area for the project will be in the same area that is currently isolated with construction fencing between Cascade Hall and Pacific Hall. During the duration of the re-roof project the area will be shared with the construction company currently working on the Pacific Hall remodel.  Re-roof construction activity will be contained in this area, with entry and exit taking place in the alleyway between Pacific Hall and Cascade Annex.  See the attached aerial photo showing the staging and re-roof areas.
  • In general, re-roof vehicle/truck activity will be limited to delivery in the morning, at start of work, and end of work day. There will be no continuous running or idling of vehicles used by the contractors (Anderson Roofing) for the re-roof project.
  • Scaffolding will be erected within the staging area on the west side of the building to access the roof. An electric hoist will be attached to the scaffolding system to facility transporting materials on and off the roof.  Erection of the scaffolding is scheduled to begin August 14th.
  • There is existing rock ballast on the project area of the roof. It will be removed and taken off the roof in buckets, transported down the electric hoist and dumped into a container truck in the staging area.  This will generate noise and is expected to last about 4 to 5 days.  Target date to begin rock ballast removal is August 22nd.  The new roof system will not have rock ballast.
  • Some dust will be generated by the removal of the existing rock ballast and old roof and insulation material. Much of the dust will be mitigated by the hand/bucket removal of the rock ballast, as well as use of the hoist to transport other demolished materials from the roof, rather than a chute system to discard material from the roof.  The grated areaway into the Cascade Hall basement mechanical space will be covered with filter fabric to mitigate dust entry into that area.
  • The materials that are to be demolished have all tested negative for asbestos.
  • Tarps will be draped in front of windows near the scaffolding as a safety precaution.
  • The new roofing is a single ply sheet system that includes adhesives to secure it to the underlying material. The adhesives will put out a bit of an odor when initially applied.  We do not expect odor to be a problem because of the roof location, prevailing winds, and no air intakes into the building near the work area.  The product is low VOC so should not be a health concern to building occupants.  If you do detect an odor and are concerned please contact me (Gene Mowery, 541-346-5593 or gmowery@uoregon.edu) or the UO Environmental Health (EHS) office (Adam Jones, 541-346-8397 or asjones@uoregon.edu).

Should you have questions or concerns regarding this project please feel free to contact me: Gene Mowery, UO office phone 541-346-5593, or email gmowery@uoregon.edu.  I will keep you all informed if the project schedule changes and provide progress reports once the project is underway.

7/26/17 (new date): Columbia Parking Garage and Ford Alumni Elevator Shutdown

Revision:  Date changed from 7/27/17 to 7/26/17

Building Occupants,

On Wednesday, July 26th, there will be a three to five hour elevator shutdown, between the hours of 8 am to 5 pm, in the Columbia Parking Garage and the Ford Alumni Center.

This is necessary to do a five-year full load safety test.

For questions or concerns about how this may impact your area, contact Rob Berg, Campus Planning and Facilities Management (CPFM) Electrical Supervisor at 346-2313.

7/27/17 (new date): Global Scholars and Clinical Services Elevator Shutdown

2nd Revision:  The 7/27/17 elevator shutdown for Clinical Services has been postponed until further notice.

Revision:  Date changed from 7/26/17 to 7/27/17

Building Occupants,

On Thursday, July 27th, there will be a 3 to 5 hour elevator shutdown, between the hours of 8 am to 5 pm, in Global Scholars and the Clinical Services Building.

This is necessary to do a five-year full load safety test.

For questions or concerns about how this may impact your area, contact Rob Berg, Campus Planning and Facilities Management (CPFM) Electrical Supervisor at 346-2313.

7/25/17: Allen Hall and EMU Elevator Shutdown

Building Occupants,

On Tuesday, July 25th, there will be a 3 to 5 hour elevator shutdown, between the hours of 8 am to 5 pm, in Allen Hall and the EMU (Erb Memorial Union).

This is necessary to do a five-year full load safety test.

For questions or concerns about how this may impact your area, contact Rob Berg, Campus Planning and Facilities Management (CPFM) Electrical Supervisor at 346-2313.

7/24/17-7/25/17 revision: Fenton Hall and LISB Elevator Shutdown

Revised Notice: 

Testing for the five-year full load safety test for LISB will need to be completed in the morning.  The elevator is currently up and running but will need to be shut down tomorrow from 7:00 am until 9:30 am.

(Fenton Hall testing was completed on 7/24/17.)

 

Building Occupants,

On Monday, July 24th, there will be a 3 to 5 hour elevator shutdown, between the hours of 8 am to 5 pm, in Fenton Hall and LISB (Lewis Integrated Science Building).

This is necessary to do a five-year full load safety test.

For questions or concerns about how this may impact your area, contact Rob Berg, Campus Planning and Facilities Management (CPFM) Electrical Supervisor at 346-2313.