11/10/25 Campus Wide – Project Development and Submission Timeline Reminder
Posted on

To Facilities Liaisons,

This is a reminder from our recent Facilities Liaison meeting of the Project Development guidelines and the Project Submission timelines for placing a project request.  Below are the slides showing the steps involved.

Please feel free to reach out to me if you have any questions.

Thank you.

Bruce Budzik
Email: bbbudzik@uoregon.edu
Office: 541-346-8834

Two slides showing the Project Development and Submission Timelines from the Fall 2025 Facilities Liaison meeting

10/13/25 – 1/09/26 Clinical Services Building Rooms 100 – 127 Remodeling Advisory
Posted on

Begin:  Monday, October 13, 2025, at 7:00 am

End:      Friday, January 9, 2026, at 4:00 pm

Building(s) or Area(s) Affected:  Clinical Services Building – Rooms 100 – 127

Scope:  The rooms listed above will be remodeled. This includes new insulation, sheetrock, painting, new flooring, new lighting, minor HVAC and plumbing modifications.

Services Impacted:

  • Occasional noise and odors typical to construction can be expected.
  • At some point, still TBD, there will need to be a water shutdown and possibly HVAC airflow.

Work Performed By:  Store and Stock LLC

ContactGlen Macdonald, CPFM Owner’s Representative, 541-346-8201

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of Clinical Services rooms 100 - 127

9/02/25 – 11/21/25 CPFM Administration Quonset 2nd Floor Remodeling Advisory
Posted on

UPDATE #2  10/30/25:
Tomorrow, Friday, October 31st, Air Inc. will be balancing the HVAC system for both the 1st and 2nd floors. They will be in each room at least twice and potentially up to four times.
– Also, the completion date has been extended to Friday, November 21st.

UPDATE #1 10/30/25:
The contractor just informed us that he will be cutting some metal tabs in the wall upstairs.  It is expected to be very loud.  Depending on the type of metal they are made of will determine how long the noise will last, potentially up to 30 minutes.

UPDATE 10/24/25:
UO Network Services has installed one of the new wireless access points outside of room 104 but will get the remaining two in next week, between Monday, 10/27/25 and Thursday, 10/30/25.

UPDATE 10/20/25:
UO Network Services will be installing three (3) new wireless hubs on the first floor outside of rooms 104 and 120 as well as in the main lobby near the reception desk.

  • Workers will not be in the area the entire duration.
  • The dates and times given are a window when Network Services could be performing work.
  • There may be some noise and passageways could be blocked.

UPDATE 10/14:
The contractor will begin cutting into the roof for the two new skylights.  Loud noise can be expected for roughly an hour and half.  They are planning to start by 10:30 am.

UPDATE 10/01:
Steam / chilled water lines will be replaced in rooms 210A, 210, and 212.
There should be no impact to the heating / cooling in the rest of the building.
There will be construction noise associated with the pipe replacement and increased foot traffic in the building.
Work will be done by Harvey & Price and Preferred Construction.

UPDATE 9/15:
The contractor just notified us that they will begin staging today near the south side of the building, by the picnic table.  It is also expected that the construction noise levels will begin to elevate in the building, potentially this afternoon.

UPDATE 9/04:
Abatement work will begin on Tuesday, September 9th at 8:30 am and will end on Friday, September 12th at 3:30 pm.
Work will be performed by Asbestos Abatement Contracting, LLC.

UPDATE 8/29:
BELCO Electric will begin removing electrical and conduit this afternoon 8/29/25.  The abatement work has been postponed and will now begin Monday, September 8, 2025 at 8:00 am.

UPDATE 8/26:
Campus Planning is relocating to Rainier during the renovation of their space on the 2nd floor of Building #136. Moving will occur Thursday, August 28th from 8:00 am to 12:00 noon.  Please expect increased activity at both sets of stairs in the Quonset.

 

Begin:  Tuesday, September 2, 2025, at 7:00 am

End:      October 31   Friday, November 21, 2025, at 5:00 pm

Building(s) or Area(s) Affected:  CPFM Administration Quonset

Scope:  Campus Planning’s space on the 2nd floor of Building #136 is being remodeled. We are building two offices on the east side of room 212. Two new skylights will be installed in the new offices.

Services Impacted:  Construction noise is to be anticipated throughout the building for the duration of the project.

Work Performed By:  Preferred Construction

ContactRenee Benoit, CPFM Owner’s Representative, 541-346-5080

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of CPFM Administration Quonset room 212

6/23/25 – 9/12/25 Lillis Hall Basement Renovation Advisory
Posted on

2nd UPDATE for 7/30/25:
Peterson Hall and Ansett Hall will also lose power on Wednesday, July 30th, between 6:00 am and 10:00 am, but Chiles Hall will not be affected.

 

UPDATE for 7/30/25:
On Wednesday, July 30th, from 6:00 am to 10:00 am, Sunset Electric needs to shut down the normal power electrical panel for the Lillis building.

  • This will impact the normal power feed for the entire building.
  • Emergency and standby power will not be impacted.

Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.  For questions, please contact Kati Kronholm at 541-346-5370 or katik@uoregon.edu.  For non-copier questions, please reach out to the contact person listed below.

 

Begin:  Monday, June 23, 2025, at 7:00 am

End:      Friday, September 12, 2025, at 4:00 pm

Building(s) or Area(s) Affected:  Lillis Hall Basement

Scope:  Renovation of custodial space in the basement of Lillis Hall.

Services Impacted:

  • The contractor will utilize the courtyard and entrance between Chiles and Peterson and the west elevator during the duration of the project.
  • Noise and associated construction activity is to be expected.

Work Performed By:  Preferred Construction

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of Lillis Hall

6/30/25 – 12/31/27 Friendly Hall Renovation Project and Access Advisory
Posted on

UPDATE 10/08/25:
As part of the seismic work at Friendly Hall, a drill rig will be utilized in the parking lot.  Expect noise from the diesel rig during work hours of 6:00 am – 3:00 pm starting Friday, October 10th and continuing through next week to Friday, October 17th.  There will also be a concrete pumping truck on site next week.

 

UPDATE 8/15/25:
We are not able to provide campus power to the construction trailers at the Collier Lawn as previously shown. Therefore, the trailers will be located at the north side of E. 13th Ave. on the SW corner of Friendly Hall on the sidewalk and into the street on E. 13th Ave.  The revised fencing is shown in orange.  The Collier Lawn site will continue to be fenced but reduced and used for material storage and laydown purposes.

Fire access is still available on E. 13th Ave as is regular delivery vehicles, bikes, and pedestrians.  ADA crossing will be on the west side of Johnson Hall across E. 13th Ave. and signage will be updated to reflect that movement.

Updated route for Friendly Hall Renovation Project 8/15/25

UPDATE 8/08/25:
The second phase of site logistics and fencing will begin on August 11th. Site work will include tree removal, and the fencing will be revised to match the attached map.

Collier Lawn will be unavailable until December 2027. Contractor trailers will move onto the site August 25th.

Overhead map view of the Friendly Hall Site Logistics for Late August 2025

Begin:  Monday, June 30, 2025

End:      Friday, December 31, 2027

Building(s) or Area(s) Affected:  Friendly Hall

Scope:  Friendly Hall will undergo a full deferred maintenance renovation project starting this summer, June 30, 2025, through December 2027. Occupants will be moved out to allow for full abatement and construction activities. Bremik Construction is our contractor partner for this work. They have put together a site logistics maps detailing the construction fence line and impacts to pedestrian/bike/vehicle traffic and parking.

Services Impacted:

  • The area directly around Friendly Hall will be fenced off, closing Lot 11 during the timeline above.
  • Construction fencing and trailers will be placed in the Collier Hall lawn across E. 13th Ave. starting in mid-August through December 2027. Please see attached maps.
  • Pedestrian/bike/vehicle traffic and parking will be impacted.
  • E. 13th Ave. will remain open with pedestrian travel along the south sidewalk.
  • The surrounding areas/events that will be affected are Allen Hall, Collier House, Johnson Hall, Lot 11, ASUO Street Faire, EMU Scheduling and Events.

Work Performed By:  Bremik Construction

ContactMartina Oxoby, CPFM Senior Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of area affected by the Friendly Hall Renovation 6/30/25 - 12/31/27

Friendly Hall Site Logistics Maps Notification

6/05/25 – 1776 Millrace Saw Cutting and Concrete Removal Advisory
Posted on

CORRECTION:

The date below has been corrected, this work will take place Thursday, June 5, 2025.

Begin: Friday Thursday,  June 5, 2025, at 7:00 am

End:    Friday Thursday, June 5, 2025, at 11:00 am

Building(s) or Area(s) Affected:  1776 Millrace (formerly known as 1700 Millrace)

Scope:  As part of the 1776 Millrace Interior Renovation Project, the contractor will perform saw cutting and concrete removal on first floor slab for plumbing work.

Services Impacted:

  • No disruption to the water supply is expected.
  • Associated noise and vibrations will occur during this time.

Work Performed By:  Swinerton Company

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Overhead aerial view of 1776 Millrace (formerly called 1700 Millrace)

12/16/24 – 1/03/25 Willamette Hall Classroom #110 Renovation Advisory
Posted on

Begin:  Monday, December 16, 2024

End:      Friday, January 3, 2025

Building(s) or Area(s) Affected:  Willamette Hall Classroom #110

Scope:  Classroom #110 will be offline while it is being renovated.  This will include the replacement of the flooring and seating.

Services Impacted:  Typical construction activity and noises can be expected during this time.  The flooring work will take place at night.

Work Performed By:  CPFM Facilities Services and Contractors

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of Willamette Hall Classroom #110

 

10/30/24 – 11/11/24 Gerlinger Annex Room 171 Office Renovation Advisory
Posted on

Begin:  Wednesday, October 30, 2024, at 7:00 am

End:      Monday, November 11, 2024, at 4:00 pm

Building(s) or Area(s) Affected:  Gerlinger Annex Room 171

Scope:  Gerlinger Annex room 171, Abatement and office renovation.

Services Impacted:  Noise can be expected during this time.

Work Performed By:  Rose City Contracting and CPFM Facility Services

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of Gerlinger Annex 171

9/23/24 – 1/31/25 Esslinger Hall Classrooms 112 and 116 Renovation Advisory
Posted on

Begin:  Monday, September 23, 2024, at 7:00 am

End:      Friday, January 31, 2025, at 4:00 pm

Building(s) or Area(s) Affected:  Esslinger Hall and Student Recreation Center

Scope:  The classroom renovation project in rooms 112 and 116 will include select demolition work, new finishes, and upgrades to HVAC and HVAC controls.

Services Impacted:

  • Work will take place primarily in Esslinger Hall 112 and 116.
  • This will also affect HVAC controls for Esslinger Hall 102 – 106 and 250 – 259.
  • Contractor will need to enter in Student Recreation Center rooms 006J and 006K.
  • Noise associated with this activity can be expected during this time.

Work Performed By:  Bridgeway Contracting

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Overhead map image of Esslinger Hall rooms 112 and 116

9/9/24 – TBD Klamath Hall 151A and 151B Renovation Advisory
Posted on

Begin:  Monday, September 9, 2024

End:      TBD

Building(s) or Area(s) Affected:  Klamath Hall 151A & 151B

Scope:  Minor renovation work will take place in Klamath 151A & 151B

Services Impacted:  Rooms 151A and 151B will be offline during renovation and noise should be expected.

Work Performed By:  CPFM Facilities Services

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impact information can be found on the UO Maps site.

Klamath 1st floor overhead view

5/08/24 – 7/31/24 Onyx Bridge 361 and 362 Renovation Advisory
Posted on

UPDATE 5/31/24:
The mechanical contractor Phoenix Mechanical will be routing mechanical lines through room 364. Same schedule applies for this work and noise is to be expected.   Room 364 is not part of the renovation, but contractors will be in there for the routing mechanical lines.

 

Begin:  Wednesday, May 8, 2024

End:      Wednesday, July 31, 2024

Building(s) or Area(s) Affected: Onyx Bridge

Scope:  Onyx Bridge rooms 361 and 362 will be renovated.

Services Impacted: Rooms 361 and 362 will be offline during renovation and noise should be expected.

Work Performed By:  CPFM Facilities Services

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Overhead view of Onyx Bridge 3rd floor

1/12/24 – 5/17/24 Willamette Hall Room 154 Renovation Work Advisory
Posted on

UPDATE:
Renovations and remodeling are still in process and the end date has been extended into the middle of May.

 

Begin:  Friday, January 12, 2024, at 8:00 am

End:      March 31   Friday, May 17, 2024, at 4:00 pm

Building(s) or Area(s) Affected:  Willamette Hall room 154

Scope:  Room 154 will undergo renovation and remodeling.

Services Impacted:  Contractors will be present in the building and lobby plus noise and odor can be expected with this type of work.

Work Performed By:  Bridgeway Contracting

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Image of Willamette 154

9/21/23 – 4/30/25 Villard Hall and University Hall “Heritage Project” Fencing and Pathway Advisory
Posted on

UPDATE:
Revised pedestrian route attached.

Revised pedestrian map 9-20-23

UO Heritage Pedestrian Routes 9.20.23

 

Begin:  Thursday, September 21, 2023

End:      Wednesday, April 30, 2025

Building(s) or Area(s) Affected:  Areas surrounding Villard, University, Lillis, Lawrence, Friendly, and Fenton Halls

Scope:  Due to the renovation of Villard Hall and University Hall, known as the “Heritage Project”, the site around both buildings will fenced off for the duration of the project.

Services Impacted:

  • This will affect the walking routes in the vicinity.
  • Temporary mulch paths with fencing will be installed, and remain for the duration of the project.
  • Walkways are anticipated to be reopened during the Spring of 2025.

Work Performed By:  Fortis Construction

Contacts: Tim Allenbaugh, CPFM Owner’s Representative, 541-346-8214

Gene Mowery, CPFM Owner’s Representative, 541-346-5593

Current construction and impacts information can be found on the UO Maps site.

Image of Heritage Project Fencing Advisory Map 9-21-23 thru 4-30-25

Pages from Site Logistics Plan_Heritage_Phase 3 Rev2 SW Closed

9/22/23 – 9/26/23 Esslinger Hall Room H151, 155, 156, 156A, 157, 161, 163, & 165 Renovation Advisory
Posted on

UPDATE:
Work has been rescheduled to take place Friday, 9/22, and run through Tuesday, 9/26.

 

BeginSeptember 20,   Friday, September 22, 2023

End:      September 22,    Tuesday, September 26, 2023

Building(s) or Area(s) Affected:  Esslinger Hall H151, 155, 156, 156A, 175, 161, 163, & 165

Scope:  Renovation demolition and abatement will take place in the locations listed above.

Services Impacted:  Construction noise and activity can be expected during this time.

Work Performed By:  IRS Environmental

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Image of Esslinger Hall Room H151, 155, 156, 156A, 157, 161, 163, & 165

6/23/23 – 10/30/23 Heritage Renovation Project Informational Bulletin
Posted on

UPDATE 10/25/23:
Fortis Construction is fully mobilizing onto the Project site beginning October 30th.  Work activity for the removal for restoration of the University and Villard Hall windows will also commence, as well as interior building demolition within the two buildings and continue for the next few months.

Please contact UO Owner’s Representatives Tim Allenbaugh (541-346-8214) or Gene Mowery (541-346-5593) if you have questions.
NOTICE AND REMINDER 8/08/23:

  • Villard Hall Theatre Arts department move has been completed.
  • Parking Lot 9 is enclosed by construction fencing and no longer open to public access.
  • Villard Hall abatement staging began today and abatement activity will continue into September.
  • Villard Hall is closed and open only to authorized abatement and construction contractors and university personnel.

 

REMINDER 7/17/23:

  • July 17, Fortis Construction began setting up construction fencing and closing off access to Parking Lot 9. Initial construction fencing will enclose Villard Hall as well, limiting access into the building.  Sidewalks/pathways on the north and east sides of Villard will remain open.
  • Villard Hall department moves are scheduled for July 19-21.
  • Villard Hall abatement is scheduled to begin August 7 and will continue into September.
  • Access into University Hall will continue until the end of the second summer class session, August 18. (But parking lot will be offline for vehicles)

 

Begin:  Friday, June 23, 2023

End:      Project Completion Summer 2025

Building(s) or Area(s) Affected:  Villard Hall, University Hall, Parking Lot 9

Scope:  General information for summer activity associated with the Heritage Renovation Project (exterior historic preservation and interior remodel of University and Villard Halls) are outlined as follows:

    • Contractors Fortis Construction and GBC Construction will periodically be in both Villard Hall and University Hall prior to established department move dates for pre-abatement and demolition investigations and activity.  When the department move dates are reached and moves completed, the buildings will be off-line for access without specific approval.  Once abatement starts, the buildings and site will be fully restrictive access.
    • The parking area between University and Villard Halls will remain open until July 16. Beginning July 17, Fortis Construction will begin setting up construction fencing and closing off access to this parking area. Initial construction fencing will enclose Villard Hall as well, limiting access into the building.
    • Villard Hall department moves are scheduled for July 19-21.
    • Villard Hall abatement is scheduled to begin August 7 and will continue into September.
    • Access into University Hall will continue until the end of the second summer class session, August 18. (But parking lot will be offline for vehicles)
    • University Hall: Mathematics department move is scheduled for August 21-23. Construction fencing to enclose University Hall is targeted to begin in this time period as well.
    • University Hall abatement is scheduled to begin September 4 and will continue into October.
    • In conjunction with construction fencing installation, vehicular and pedestrian pathway closure and rerouting signage will be put in place.

Please contact UO Owner’s Representatives Tim Allenbaugh (541-346-8214) or Gene Mowery (541-346-5593) if you have questions.

Current construction and impacts information can be found on the UO Maps site.

 

Image of Villard, University Hall, and Lot 9

6/09/23 – 9/30/23 Streisinger Hall and Parking Lot 12B East Science Loop Project
Posted on

2nd UPDATE 9/28/23:
It is expected that the tar odors may be noticed around Klamath Hall, and possibly Onyx Bridge, tomorrow.

 

UPDATE 9/28/23:
The East Science Loop civil contractor will be paving the parking lot on the north side of the Streisinger building (see picture for specifics), weather depending. This is scheduled for Friday, September 29th from 7:00 am to 12:0 noon.  During this work the adjacent areas will be experiencing heavy vehicle traffic as the work is being performed, and due to this spaces might be blocked temporarily. Additionally, some paving odors will be present during the work as well.

If this work does not take place due to weather, the notice will be updated with future times/dates to be aware of.

Thank you for your understanding.

Diagram of Streisinger Lot Paving Project for 9-29-23

 

UPDATE 7/11/23:
The crane/closure dates have now been shifted, due to crane availability, to Friday, July 21st, and Wednesday, July 26th.  The third date is yet to be determined.

 

UPDATE to 6/30/23 Lab Waste Shutdown Entry (7/05/23):
After speaking with the building users regarding lab waste schedules, we are rescheduling the lab waste piping connection shutdown to Friday, July 7th, and Monday, July 10th.

 

UPDATE 7/05/23:
As part of vault deliveries for the East Loop Electrical project, the parking lot area shown will be closed and also the associated loading dock will be down for the duration of the crane work on Monday, July 17th Friday, July 21st, at 7:00 am through Tuesday, July 18th, until 6:00 pm.  Please take this into consideration for your activities, and reach out should this activity limit critical operations/needs.  This will be the first of 3 such closures, with the next potentially occurring 7/25 7/26 and 8/2 TBD. We will update this notice each time to ensure we are working around your needs as we are able.

Image of parking lot for Streisinger and Klamath

 

UPDATE 6/30/23:
Due to work needed to move the East Loop electrical project forward, the lab waste piping will be shut down for up to a days’ time to make the necessary connections to improve the system. This will affect Streisinger, Klamath, and Onyx Bridge.  Be advised that during this time, all lab waste drains will be unable to be used (eg: sink drains).  We are intending to perform this work on Tuesday, July 11th, Friday, July 7th, and Monday, July 10th, from 7:00 am to 5:00 pm.    Please let us know if that day presents a conflict in regard to your operations.  If not, we will update this work as confirmed.

 

UPDATE:
The arborist notified us that due to a change in his schedule, the tree work will take place tomorrow.

 

Begin:  Monday, June 12, 2023

End:      Saturday, September 30, 2023

Building(s) or Area(s) Affected:  Streisinger Hall, East end of Parking Lot 12B

Scope:  Beginning next week, the East Science Loop civil contractor will be kicking off ground work for the project. This will include demolition in the project area, including asphalt removal, tree/planting removal, and earthwork.

Services Impacted:

  • Please be aware associated noises and vibrations are to be expected.
  • The adjacent loading dock will be functional throughout.
  • Pedestrian rerouting (e.g.: not through the parking lot area) will be present for the life of the project. (See picture for details.)
  • No disruptions to services (not previously discussed) are expected.

Work Performed By:  Wildish Construction

ContactDamon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285

Current construction and impacts information can be found on the UO Maps site.

Diagram of Streisinger and Lot 12B

8/01/23 – 8/31/23 McKenzie Hall Flooring Access Advisory
Posted on

Begin:  Tuesday, August 1st, 2023

End:      Thursday, August 31st, 2023

Building(s) or Area(s) Affected:  McKenzie Hall

Scope:  The carpet will be replaced in the hallway areas of the 3rd floor south wing.  Due to asbestos containing materials, removal of existing carpet will require containment and abatement procedures that will prohibit access to the area, including adjoining offices, for the duration of the project.

Services Impacted:

  • Carpet will be replaced in corridors and open areas only:  H301, H375, L338, L328, L318 and L300.
  • The adjoining offices in the area will be inaccessible during the demolition and abatement phase of the project, which is expected to last 2 to 3 weeks. Occupants of these offices will need to make other arrangements for work space during this time.
  • The restrooms and lactation room will also be inaccessible during demolition and abatement.

Work Performed By:  EHS-managed abatement contractor and CPFM Facilities Services personnel

ContactJustin Grishkin, CPFM Construction Services Manager, 541-346-5242

To view current construction and impacts, please visit UO Maps.

2/06/23 – 2/28/23 Prince Lucien Campbell Room 182 Renovation Noise Advisory
Posted on

Begin:  Monday, February 6, 2023

End:      Tuesday, February 28, 2023

Building(s) or Area(s) Affected:  Prince Lucien Campbell Room 182

Scope:  Intermittent demolition and renovation activities will take place in room 182.

Services Impacted:  Construction noises can be expected during this time.

Work Performed By:  CPFM Facilities

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

1/03/23 – 1/20/23 Knight Library Room 57 Renovation Work and Access Advisory
Posted on

Begin:  Tuesday, January 3rd, 2023

End:      Friday, January 20th, 2023

Building(s) or Area(s) Affected:  Knight Library Room 57

Scope:  Renovation work is being done in room 57.  A flexible fresh air duct will be run down hall H57 and out the window of room 19 for two days only, January 4th and 5th.  This may cause some ADA access issues. Paint, carpet and other refresh work will follow in room 57

Services Impacted:

  • Access may be affected in Hallway H057 on Wednesday, January 4th, and Thursday, January 5th.
  • Construction noise and odor can be expected in the area.

Work Performed By:  PMG Demolition and CPFM Facilities Services

ContactJanell Cottam, CPFM Owner’s Representative, 541-346-7536

Current construction and impacts information can be found on the UO Maps site.

Lawrence and Pacific Connecting Stairway Closure 3/14/22 – 3/25/22
Posted on

UPDATE:
Work will now begin the week prior to Spring Break on March 14th .  The completion date is still scheduled for March 25th.

 

Begin:  Monday, March 14 21, 2022

End:      Friday, March 25, 2022

Building(s) or Area(s) Impacted:  Lawrence Hall,  H100

Scope:  During the week of Spring Break, plus the week prior, hallway H100 will be closed in order to make repairs caused by a water leak earlier this winter.

Services Impacted: Access to the three step stairway between Lawrence and Pacific, near room 100, will be shut down.

Work Performed By:  CPFM Facilities Services Crew

ContactKevin Wilson, CPFM FS Construction Field Superintendent, 541-968-4024

Streisinger Hall Drilling Noise Advisory 2/02/22
Posted on

Begin:  Wednesday, February 2, 2022 at 1:00 pm

End:      Wednesday, February 2, 2022 at 4:00 pm

Building(s) or Area(s) Impacted:  Streisinger Hall Rooms 275A and B

Scope:  Contractor will be drilling concrete in the 2nd floor renovation area.

Services Impacted:  Nearby occupants can expect noise and construction activity during this time.

Work Performed By:  Mortenson Construction

ContactColin Brennan, CPFM Owner’s Representative, 541-346-8242 or 541-654-2972

CPFM Warehouse and Shops (Bldg. 130) Suite 110 Remodel 7/14/21 – 9/17/21
Posted on

Begin:  Wednesday, July 14th, 2021

End:      Friday, September 17th, 2021

Building(s) or Area(s) Impacted:  CPFM Warehouse and Shops (Bldg. 130) – 110, 110B, 110A and H110A

Scope:  Remodel of Suite 110 including demolition of some existing walls and construction of new walls; modification of electrical circuits, replacement of lighting, carpet and paint throughout.

Services Impacted:  Adjacent occupants can expect to hear typical construction noises for the duration of the project, including cutting, hammering and drilling.

Work Performed By:  UO Facilities Services

ContactJustin Grishkin, CPFM Construction Services Manager, 541-346-5242

McKenzie Hall Storefront Work Advisory 5/17/21 – 5/28/21
Posted on

UPDATE 5/17/21:

The HVAC system will be shut down while the ground floor level duct dampers are  tested on Thursday, May 20th, between 7:00 and 8:00 am.

 

Original Notice

Begin:  Monday, May 17, 2021

End:   Friday, May 28, 2021

Building Impacted:  McKenzie Hall

Scope:  Replace existing storefront exterior entries at 6 locations on the main and ground levels.  Each location is expected to take 2 days to replace.

Services Impacted:

  • No additional electrical or HVAC disruptions are known at this time.  A shutdown notice will be issued as necessary.
  • Building access will be maintained during construction but may require detours.  The contractor will post signs as necessary.
  • Users can expect to hear construction noises like hammering, drilling, grinding, and see construction personnel and UO staff entering and exiting the building during normal business hours, but also as early as 6

Work performed by:  Ryan Thomas Construction, Culver Glass, and CPFM Facilities Construction Services.

Contact:  Theo Davis, CPFM Design & Construction Project Manager, 541-346-1012

Windows to be replaced in UHCC B0014 on 11/30/2020
Posted on

Begin:  Monday, November 30, 2020  8:00am

End:      Friday, December 4, 2020  5:00pm

Building Impacted: University Health, Counseling and Testing, B0014

Scope:  Poor performing south facing windows on the 1st floor in Clinic C and E that were not upgraded during the renovation will be replaced. Work activities will generate noise and vibration.

Work Performed By:  Dallas Glass

Contact: Colin Brennan, CPFM Owners Representative at email: brennan@uoregon.edu or phone 541-652-2972

Willamette Hall Classroom #100 Renovation Advisory 6/25/20 – 9/30/20
Posted on

UPDATE 9/11: This project has been extended to the end of September.

Begin:  Thursday, June 25th, 2020 at 7:00 am

End:      Monday, August 31st, 2020 at 6:00 pm Wednesday, September 30th, 2020

Building(s) or Area(s) Impacted:  Willamette Hall

Scope:  Phase 3 of the Willamette Hall classroom #100 renovation is underway. Work includes construction of a new storage room, demolition, and installation of new flooring.

Services Impacted:  Noise related to this work will be typical.

Extra Notes:  Work will be performed during work hours of 7AM-6PM.

Work Performed By:   Bridgeway Construction

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880