CORRECTION: This will affect all fume hoods east of the Atrium from the basement through the fourth floor.
Begin: Thursday, November 7, 2024 at 7:00 am
End: Thursday, November 7, 2024 at 5:00 pm
Building(s) or Area(s) Affected: Willamette Hall east of the Atrium – Basement through the 4th floor rooms 35, 35A, 40A, 45, 55, 85, 85A, 85B, 95, 95A, 95B
Scope: The exhaust fans serving these rooms will be down to balance the system and test for improved airflow. The contractor will be in these rooms testing the air flow after the balancing work is completed.
Services Impacted: Room exhausts and fume hood exhausts in these rooms will be down for the entire day.
Special Instructions: Fume hood sashes should be closed and containers within the fume hoods sealed before this date.
Work Performed By: Air Introduction and Regulation
Contact: Work Control Center, Campus Planning and Facilities Management, 541-346-2319
Current construction and impacts information can be found on the UO Maps site.