5/03/24 Prince Lucien Campbell Intermittent HVAC Interruptions
Posted on

Begin:  Friday, May 3, 2024, at 12:00 noon

End:      Friday, May 3, 2024, at 4:00 pm

Building(s) or Area(s) Affected:  Prince Lucien Campbell

Scope:  To maintain reliability of the Building Automation System controllers, Siemens will be performing firmware updates on control panels.

Services Impacted:  Intermittent outages to HVAC and exhaust systems are to be expected.

Work Performed By:  Siemens

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Prince Lucien Campbell

 

5/03/24 Peterson Hall Intermittent HVAC Interruptions
Posted on

Begin:  Friday, May 3, 2024, at 12:00 noon

End:      Friday, May 3, 2024, at 4:00 pm

Building(s) or Area(s) Affected:  Peterson Hall

Scope:  To maintain reliability of the Building Automation System controllers, Siemens will be performing firmware updates on control panels.

Services Impacted:  Intermittent outages to HVAC and exhaust systems are to be expected.

Work Performed By:  Siemens

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Peterson Hall

5/03/24 Moss Street Children’s Center Intermittent HVAC Interruptions
Posted on

Begin:  Friday, May 3, 2024, at 8:00 am

End:      Friday, May 3, 2024, at 12:00 noon

Building(s) or Area(s) Affected:  Moss Street Children’s Center

Scope:  To maintain reliability of the Building Automation System controllers, Siemens will be performing firmware updates on control panels.

Services Impacted:  Intermittent outages to HVAC and exhaust systems are to be expected.

Work Performed By:  Siemens

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Moss Street Children's Center

5/03/24 Museum of Natural and Cultural History Intermittent HVAC Interruptions
Posted on

Begin:  Friday, May 3, 2024, at 8:00 am

End:      Friday, May 3, 2024, at 12:00 noon

Building(s) or Area(s) Affected:  Museum of Natural and Cultural History

Scope:  To maintain reliability of the Building Automation System controllers, Siemens will be performing firmware updates on control panels.

Services Impacted:  Intermittent outages to HVAC and exhaust systems are to be expected.

Work Performed By:  Siemens

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of the Museum of Natural and Cultural History

5/02/24 Lawrence Hall Intermittent HVAC Interruptions
Posted on

Begin:  Thursday, May 2, 2024, at 12:00 noon

End:      Thursday, May 2, 2024, at 4:00 pm

Building(s) or Area(s) Affected:  Lawrence Hall

Scope:  To maintain reliability of the Building Automation System controllers, Siemens will be performing firmware updates on control panels.

Services Impacted:  Intermittent outages to HVAC and exhaust systems are to be expected.

Work Performed By:  Siemens

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Lawrence Hall

5/02/24 Knight Law Intermittent HVAC Interruptions
Posted on

Begin:  Thursday, May 2, 2024, at 12:00 noon

End:      Thursday, May 2, 2024, at 4:00 pm

Building(s) or Area(s) Affected:  Knight Law

Scope:  To maintain reliability of the Building Automation System controllers, Siemens will be performing firmware updates on control panels.

Services Impacted:  Intermittent outages to HVAC and exhaust systems are to be expected.

Work Performed By:  Siemens

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Knight Law

5/02/24 Johnson Hall Intermittent HVAC Interruptions
Posted on

Begin:  Thursday, May 2, 2024, at 12:00 noon

End:      Thursday, May 2, 2024, at 4:00 pm

Building(s) or Area(s) Affected:  Johnson Hall

Scope:  To maintain reliability of the Building Automation System controllers, Siemens will be performing firmware updates on control panels.

Services Impacted:  Intermittent outages to HVAC and exhaust systems are to be expected.

Work Performed By:  Siemens

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Johnson Hall

5/02/24 HEDCO Intermittent HVAC Interruptions
Posted on

Begin:  Thursday, May 2, 2024, at 8:00 am

End:      Thursday, May 2, 2024, at 12:00 noon

Building(s) or Area(s) Affected:  HEDCO

Scope:  To maintain reliability of the Building Automation System controllers, Siemens will be performing firmware updates on control panels.

Services Impacted:  Intermittent outages to HVAC and exhaust systems are to be expected.

Work Performed By:  Siemens

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of HEDCO

5/02/24 Gerlinger Annex Intermittent HVAC Interruptions
Posted on

Begin:  Thursday, May 2, 2024, at 8:00 am

End:      Thursday, May 2, 2024, at 12:00 noon

Building(s) or Area(s) Affected:  Gerlinger Annex

Scope:  To maintain reliability of the Building Automation System controllers, Siemens will be performing firmware updates on control panels.

Services Impacted:  Intermittent outages to HVAC and exhaust systems are to be expected.

Work Performed By:  Siemens

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Gerlinger Annex

4/18/24 – 4/19/24 Knight Library AHU-2 Air Handler Down
Posted on

UPDATE:
The parts have arrived and been replaced. Work is now complete, and the system has been returned to service.

Begin:  Thursday, April 18, 2024 – effective immediately

End:      Unknown Friday, April 19, 2024, at 1:15 pm

Building(s) or Area(s) Affected:  Knight Library

Scope:  The AHU-2 air handler is currently down.  Parts are expected to arrive tomorrow, which would allow the system to be back up and running by the end of day.  An update will be sent when the system has been returned to service.

Services Impacted:  This will affect the air flow in the SE portions of all floors in the building.

Work Performed By:  CPFM Facilities

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.