10/03/22 – 10/04/22 Knight Library 3D mobile mapping
Posted on

Begin:  October 3, 2022

End:  October 4, 2022

Building(s) or Area(s) Affected:  Knight Library

Scope:  Internal Architectural Space Survey is mapping the existing building using 3D mobile LiDar mapping technology.  This process will involve individuals with mobile imagine equipment walking through the facility.  No images of individuals will be included in the final CAD drawings generated.

Work Performed By:  Reality Capture in association with DLR Architects

ContactJanell Cottam, CPFM Owners Rep 541-346-7536

10/03/22 – 10/04/22 Streisinger Hall and Lokey Labs Emergency Steam Shutdown
Posted on

Begin:  Monday, October 3rd, 2022 – effective immediately

End:      Tuesday, October 4th, 2022 – end of day

Building(s) or Area(s) Affected:  Streisinger Hall and Lokey Labs

Scope:  Utilities and Energy will be working on the condensate return system Tuesday morning.  BAS shut down the steam system around 3:00 pm to allow the steam lines to cool down.  Repair work will start at 8:00 am and should be completed by the end of day Tuesday.

Services Impacted:  Steam will be offline during this time.

Work Performed By:  CPFM Utilities & Energy and Facilities

ContactPaul Langley, CPFM Interim Co-Dir Utilities & Energy, 541-346-5387 or Stacy Breaux, CPFM FS Building Automation Systems Field Supervisor, 541-346-2304

To view current construction and impacts, visit UO Map.