9/24/22 Huestis Hall Basement and Lokey Labs Electrical Shutdown
Posted on

REVISED:
The shutdown has been rescheduled for Saturday, September 24th, 2022.

 

Begin:  Saturday, September 10th, September 24th, 2022 at 6:00 am

End:      Saturday, September 10th, September 24th, 2022 at 4:00 pm

Building(s) or Area(s) Affected:  Huestis Hall Basement and Lokey Labs

Scope:  Permanent shutdown of Huestis main distribution panel (MDP) to allow buildout of new construction equipment. Re-distribute power to 2N2A, BN-7, Construction temp power, and OC-2 loads from 3) new 600A fused switches to be located in transformer vault behind MDP. – see attachments

Services Impacted:  Normal power will not be available during this shutdown. Standby power will not be affected.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.

Work Performed By:  Lease Crutcher Lewis and EC

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

To view current construction and impacts. visit UO Map.

E6.13 MDP demo schematic (1) (002)

MDP distribution plan REV2

Temp power SQD H326NR (1)

9/24/22 Huestis Basement AHU-2 Air Supply and Exhaust Shutdown
Posted on

Begin:  Saturday, September 24th, 2022 at 7:00 am

End:      Saturday, September 24th, 2022 at 3:30 pm

Building and Area:  Huestis

Scope: As part of the Huestis Renovation Project, Willamette AHU-2 will be shut down on Saturday for 8 ½ hours.

Services Impacted:  This shutdown will affect air supply and exhaust in Huestis suite 34 and provide new temporary exhaust for Huestis Suite 34, restrooms, and room 11.

Work Performed By:  JH Kelly

Contact: Martina Oxoby, CPFM Owner’s Representative, 541-346-5880

To view current construction and impacts. visit UO Map.

9/24/22 Huestis Hall, Lokey Labs, Streisinger Hall Noise and Vibration Advisory
Posted on

UPDATE: Work was completed.  See notice “11/28/22 – 12/7/22 Huestis Hall Demolition Noise Advisory”

UPDATE:  This work has been cancelled and will be scheduled at a later time TBD

Begin: Saturday, September 24, 2022 at 6:00 am TBD

End:    Saturday, September 24, 2022 at 6:00 pm TBD

Building(s) or Area(s) Affected:  Huestis Hall, Streisinger Hall, and Lokey Labs

Scope:  Demolition activities on level 1, north lobby of Huestis Hall

Services Impacted:  The equipment used during this work will create noise and vibration.

Work Performed By: Lease Crutcher Lewis and Staton

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

To view current construction and impacts. visit UO Map.