Clinical Services Building Delivery and Construction Noise Advisory 9/7/21 – 9/11/21
Posted on

Begin:  Tuesday, September 7th, 2021 at 7:00 am

End:      Saturday, September 11th, 2021 at 4:00 pm

Building(s) or Area(s) Impacted:  Clinical Services Building Room 145

Scope:  A new sound booth will be delivered to room 145.

Services Impacted:

  • A portion of lot 19, on the north side of the building, will be blocked off for the delivery.
  • Building occupants will hear construction sounds emanating from room 145 while this is assembled.
  • No building utilities will be affected and workers will access building from north parking lot.

Work Performed By:  Swinerton Construction

ContactBruce Budzik, CPFM Small Projects & Cap Imp Manager, 541-346-8834

Lewis Integrative Science Building HVAC Shutdown 9/01/21 – 9/02/21
Posted on

Begin:  Wednesday, September 1st, 2021 at 7:00 am

End:      Thursday, September 2nd, 2021 at 6:00 pm

Building(s) or Area(s) Impacted:  Lewis Integrative Science Building

Scope:  Each HVAC unit will be shut down for approximately ½ – 1 day during the timeframe indicated to perform cleaning. This is part of the wildfire insurance response project.  Apologies for the short notice.

Services Impacted:  This will impact the main building air and should not affect mini-splits and local temperature control units.

Note:  Fume hood sashes will need to be closed and containers within the fume hoods sealed prior to the shutdown.

Work Performed By:  ERS, Inc.

ContactAdam Jones, SRS Buildings Sciences Manager, 541-346-8397

Willamette Hall HVAC Shutdown 8/31/21
Posted on

Begin:  Tuesday, August 31st, 2021 at 7:00 am

End:      Tuesday, August 31st, 2021 at 6:00 pm

Building(s) or Area(s) Impacted:  Willamette Hall

Scope:  Each HVAC unit will be shut down for approximately ½ – 1 day during the timeframe indicated to perform cleaning. This is part of the wildfire insurance response project.  Apologies for the short notice.

Services Impacted:  This will impact the main building air and should not affect mini-splits and local temperature control units.

Note:  Fume hood sashes will need to be closed and containers within the fume hoods sealed.

Work Performed By:  ERS, Inc.

ContactAdam Jones, SRS Buildings Sciences Manager, 541-346-8397

Klamath Hall HVAC Shutdown 9/07/21
Posted on

REVISED DATE

This work has been rescheduled for next Tuesday, September 7th, 2021

 

BeginMonday, August 30th, Tuesday, September 7th, 2021 at 8:00 am

End:      Monday, August 30th, Tuesday, September 7th, 2021 at 7:00 pm

Building(s) or Area(s) Impacted:  Klamath Hall

Scope:  Each HVAC unit will be shut down for approximately ½ – 1 day during the timeframe indicated to perform cleaning. This is part of the wildfire insurance response project.   Apologies for the short notice

Services Impacted:  This will impact the main building air and should not affect mini-splits and local temperature control units.

Note:  Fume hood sashes will need to be closed and containers within the fume hoods sealed.

Work Performed By:  ERS, Inc.

ContactAdam Jones, SRS Buildings Sciences Manager, 541-346-8397

EC Cares elevator is down for repairs 8/30/21
Posted on
Begin: August 30, 2021

End: TBD

Building Impacted: EC Cares

ScopeThe elevator is nonresponsive. The Otis elevator technician has been dispatched and will be on-site making repairs.

Services Impacted: The elevator is shutdown at the moment.

Extra Notes: An update will be sent when services are restored.

Work Performed By: Otis

Contact: Work Control Center, Campus Planning and Facilities Management, 541-346-2319