UPDATE:
Work has been completed, and service has been restored.
Begin: Thursday, June 12, 2025, at 7:30 am
End: Thursday, June 12, 2025, at 8:30 am
Building(s) or Area(s) Affected: Willamette Hall – East side of the building on the following floor levels: Basement, Floor-1, Floor-2 and Floor-3.
Scope: Building supply air will be off to allow personnel access into the internal fan compartment to make urgent repairs to supply damper actuators.
Services Impacted: Supply air to the east side of the building will be off. Exhaust fans will continue to operate, which may cause pressures between the east side rooms and adjacent corridors.
Work Performed By: CPFM BAS Crew
Contact: Stacy Breaux, CPFM Building Automation Systems Field Supervisor, 541-346-2304
Work Control Center, Campus Planning and Facilities Management, 541-346-2319
Current construction and impacts information can be found on the UO Maps site.