Campus Wide Soap Dispenser Installations for 1/12/21

Due to issues in the supply chain and acquiring product, this project was postponed, but has since resumed as of this week.

Installations for 1/12/21:
Listed below are the buildings expected to be serviced Tuesday, January 12th, 2021.
Additional notification will be sent if installers are unable to finish on the projected date.

Paleoecology Research (112)
MNCH Archaeological Research (107)
Greenhouses (109, 110, 111)
CPFM buildings
CPS buildings
EC Cares (W 12th Avenue)

ORIGINAL NOTICE

Begin: Monday, November 9th, 2020

End: Friday, December 4th, 2020

Building(s) or Area(s) Impacted: Campus Wide Academic Buildings

Scope: The manufacturer is discontinuing our current soap refills, so we are transitioning to a different soap dispenser across the academic campus. Since this transition is manufacturer caused, they are providing the contractor to do the install at no cost to the university.

Services Impacted: Temporary access to soap dispensers in restrooms, labs, teachings spaces, and kitchenettes.

Extra Notes: Each install will only take a few minutes but there are thousands across campus.

Work Performed By: Home Depot Pro

Contact: Tim Winder, CPFM FS Custodial Services Manager, 541-346-5771

Campus Wide Soap Dispenser Installations for 1/11/21

Due to issues in the supply chain and acquiring product, this project was postponed and is now ready to begin again next week.

Installations for 1/11/21:
Listed below are the buildings expected to be serviced Monday, January 11th, 2021.
Additional notification will be sent if installers are unable to finish on the projected date.

LISB
Huestis
Deschutes
AAA North/Millrace/Wood Shop

 

ORIGINAL NOTICE

Begin: Monday, November 9th, 2020

End: Friday, December 4th, 2020

Building(s) or Area(s) Impacted: Campus Wide Academic Buildings

Scope: The manufacturer is discontinuing our current soap refills, so we are transitioning to a different soap dispenser across the academic campus. Since this transition is manufacturer caused, they are providing the contractor to do the install at no cost to the university.

Services Impacted: Temporary access to soap dispensers in restrooms, labs, teachings spaces, and kitchenettes.

Extra Notes: Each install will only take a few minutes but there are thousands across campus.

Work Performed By: Home Depot Pro

Contact: Tim Winder, CPFM FS Custodial Services Manager, 541-346-5771

Campus Wide Soap Dispenser Installations for 12/4/20

Installations for 12/04/20:

Listed below are the buildings expected to be serviced Friday, December 4th, 2020.

Additional notification will be sent if installers are unable to finish on the projected date.

Streisinger (this includes TeACS – Dan Prutzman will escort.  Meet at loading dock 7:30 am)
Huestis (no entry: 208, 212, 227)
LISB (no entry: 174, 186A, 300, and 301)
Deschutes

If the installers have time they’ll move to the North side of Franklin in the Facilities Services compound.

ORIGINAL NOTICE

Begin: Monday, November 9th, 2020

End: Friday, December 4th, 2020

Building(s) or Area(s) Impacted: Campus Wide Academic Buildings

Scope: The manufacturer is discontinuing our current soap refills, so we are transitioning to a different soap dispenser across the academic campus. Since this transition is manufacturer caused, they are providing the contractor to do the install at no cost to the university.

Services Impacted: Temporary access to soap dispensers in restrooms, labs, teachings spaces, and kitchenettes.

Extra Notes: Each install will only take a few minutes but there are thousands across campus.

Work Performed By: Home Depot Pro

Contact: Tim Winder, CPFM FS Custodial Services Manager, 541-346-5771

Campus Wide Soap Dispenser Installations for 12/3/20

Installations for 12/03/20:

Listed below are the buildings expected to be serviced Thursday, December 3rd, 2020.
Additional notification will be sent if installers are unable to finish on the projected date.

Cascade Annex
Cascade Hall
Columbia Hall (no entry in 40, 57)
Pacific Hall (no entry in 1, 14, 109, 236, 310)
Volcanology (no entry in 302)
Willamette (no entry in 32, 61, 73, 106, 209, 256, 272, 363, 410A)

ORIGINAL NOTICE

Begin: Monday, November 9th, 2020

End: Friday, December 4th, 2020

Building(s) or Area(s) Impacted: Campus Wide Academic Buildings

Scope: The manufacturer is discontinuing our current soap refills, so we are transitioning to a different soap dispenser across the academic campus. Since this transition is manufacturer caused, they are providing the contractor to do the install at no cost to the university.

Services Impacted: Temporary access to soap dispensers in restrooms, labs, teachings spaces, and kitchenettes.

Extra Notes: Each install will only take a few minutes but there are thousands across campus.

Work Performed By: Home Depot Pro

Contact: Tim Winder, CPFM FS Custodial Services Manager, 541-346-5771

Campus Wide Soap Dispenser Installations for 12/2/20

Installations for 12/02/20:
Listed below are the buildings expected to be serviced Wednesday, December 2nd, 2020.
Additional notification will be sent if installers are unable to finish on the projected date.

Columbia Hall
Pacific Hall
Volcanology
Cascade Hall
Cascade Annex
Onyx Bridge
Price Science Commons

ORIGINAL NOTICE

Begin: Monday, November 9th, 2020

End: Friday, December 4th, 2020

Building(s) or Area(s) Impacted: Campus Wide Academic Buildings

Scope: The manufacturer is discontinuing our current soap refills, so we are transitioning to a different soap dispenser across the academic campus. Since this transition is manufacturer caused, they are providing the contractor to do the install at no cost to the university.

Services Impacted: Temporary access to soap dispensers in restrooms, labs, teachings spaces, and kitchenettes.

Extra Notes: Each install will only take a few minutes but there are thousands across campus.

Work Performed By: Home Depot Pro

Contact: Tim Winder, CPFM FS Custodial Services Manager, 541-346-5771

Campus Wide Soap Dispenser Installations for 11/23/20

Installations for 11/23/20:
Listed below are the buildings expected to be serviced Monday, November 23rd, 2020.
Additional notification will be sent if installers are unable to finish on the projected date.

Installers will be escorted by the occupants of the below spaces:
Streisinger/LISB Animal Research Lab
Lokey Labs – Tenant occupied areas
Zebrafish International Resource Center

Based on arrival time determined by the above installations, the buildings listed below may be pushed off till the next day:
Lillis
Chiles
Peterson
Anstett

ORIGINAL NOTICE

Begin: Monday, November 9th, 2020

End: Friday, December 4th, 2020

Building(s) or Area(s) Impacted: Campus Wide Academic Buildings

Scope: The manufacturer is discontinuing our current soap refills, so we are transitioning to a different soap dispenser across the academic campus. Since this transition is manufacturer caused, they are providing the contractor to do the install at no cost to the university.

Services Impacted: Temporary access to soap dispensers in restrooms, labs, teachings spaces, and kitchenettes.

Extra Notes: Each install will only take a few minutes but there are thousands across campus.

Work Performed By: Home Depot Pro

Contact: Tim Winder, CPFM FS Custodial Services Manager, 541-346-5771

Campus Wide Soap Dispenser Installations for 11/22/20

Installations for 11/22/20:

Listed below are the buildings expected to be serviced Sunday, November 22nd, 2020.

These areas are being completed during irregular hours to avoid contact with patients, clients, and school age children, partially due to occupancy levels of the buildings and partially due to security and confidentiality issues that arise during normal business hours.

Additional notification will be sent if installers are unable to finish on the projected date.

Rainier
UOPD
University Health Center
Moss St. Childcare
Vivian Olum Childcare
Clinical Services Building
HEDCO Clinic
Computing Center

ORIGINAL NOTICE

Begin: Monday, November 9th, 2020

End: Friday, December 4th, 2020

Building(s) or Area(s) Impacted: Campus Wide Academic Buildings

Scope: The manufacturer is discontinuing our current soap refills, so we are transitioning to a different soap dispenser across the academic campus. Since this transition is manufacturer caused, they are providing the contractor to do the install at no cost to the university.

Services Impacted: Temporary access to soap dispensers in restrooms, labs, teachings spaces, and kitchenettes.

Extra Notes: Each install will only take a few minutes but there are thousands across campus.

Work Performed By: Home Depot Pro

Contact: Tim Winder, CPFM FS Custodial Services Manager, 541-346-5771

Campus Wide Soap Dispenser Installations for 11/20/20

Installations for 11/20/20:
Listed below are the buildings expected to be serviced Friday, November 20th, 2020.
Additional notification will be sent if installers are unable to finish on the projected date.

Baker Downtown
510 Oak
942 Olive
EC Cares

ORIGINAL NOTICE

Begin: Monday, November 9th, 2020

End: Friday, December 4th, 2020

Building(s) or Area(s) Impacted: Campus Wide Academic Buildings

Scope: The manufacturer is discontinuing our current soap refills, so we are transitioning to a different soap dispenser across the academic campus. Since this transition is manufacturer caused, they are providing the contractor to do the install at no cost to the university.

Services Impacted: Temporary access to soap dispensers in restrooms, labs, teachings spaces, and kitchenettes.

Extra Notes: Each install will only take a few minutes but there are thousands across campus.

Work Performed By: Home Depot Pro

Contact: Tim Winder, CPFM FS Custodial Services Manager, 541-346-5771

Campus Wide Soap Dispenser Installations for 11/19/20

Installations for 11/19/20:

Listed below are the buildings expected to be serviced Thursday, November 19th, 2020.
Additional notification will be sent if installers are unable to finish on the projected date.

Agate
Baker Downtown
Black Cultural Center
Knight Law
LERC
Longhouse
Thompson University Center

 

ORIGINAL NOTICE

Please share with building occupants

Begin: Monday, November 9th, 2020

End: Friday, December 4th, 2020

Building(s) or Area(s) Impacted: Campus Wide Academic Buildings

Scope: The manufacturer is discontinuing our current soap refills, so we are transitioning to a different soap dispenser across the academic campus. Since this transition is manufacturer caused, they are providing the contractor to do the install at no cost to the university.

Services Impacted: Temporary access to soap dispensers in restrooms, labs, teachings spaces, and kitchenettes.

Extra Notes: Each install will only take a few minutes but there are thousands across campus.

Work Performed By: Home Depot Pro

Contact: Tim Winder, CPFM FS Custodial Services Manager, 541-346-5771

Campus Wide Soap Dispenser Installations 11/9/20 – 12/4/20 & 1/11/21 – completion

1/08/2021 UPDATE:

Due to issues in the supply chain and acquiring product, this project was postponed and is now ready to begin again the week of January 11th , 2021.

 

Begin:  Monday, November 9th, 2020

End:     Friday, December 4th, 2020

Building(s) or Area(s) Impacted:  Campus Wide Academic Buildings

Scope:  The manufacturer is discontinuing our current soap refills, so we are transitioning to a different soap dispenser across the academic campus. Since this transition is manufacturer caused, they are providing the contractor to do the install at no cost to the university.

Services Impacted:  Temporary access to soap dispensers in restrooms, labs, teachings spaces, and kitchenettes.

Extra Notes:  Each install will only take a few minutes but there are thousands across campus.

Work Performed By:   Home Depot Pro

ContactTim Winder, CPFM FS Custodial Services Manager, 541-346-5771