Begin: Tuesday, March 28, 2023
End: Wednesday, March 29, 2023
Building(s) or Area(s) Affected: Lewis Integrative Science Building, Lokey Labs, and Willamette Hall
Scope: CPFM Design and Construction will temporarily isolate individual process chilled water equipment drops in Lewis Integrative Science Building and Lokey Labs. The process chilled water system needs a few final adjustments to complete the project to improve system operation, water quality, and redundancy.
3/28-3/29: Installation of additional ball valves on equipment drops in LISB and Lokey Labs will allow for bypass water flow when equipment is not connected. This will require equipment to be disconnected during installation. Immediately following valve installation, the equipment can be reconnected. The process chilled water system will remain active during this work and the only interruption will occur at individual equipment drops.
3/29-3/31: Water flow adjusting and balancing for the system will occur during this time. A contractor will need to access each equipment drop and will make adjustments to the manual balance valves. Flow to individual equipment drops in Willamette may be disrupted for a few minutes if there is a manual balancing valve already installed in the bypass piping. Any interruptions in Willamette will be short and no other buildings have this condition, so they will not be impacted.
This will impact:
- Willamette: Rooms 36, 39, 41C, 42, 154, 242, 255, 272, 273
- LISB: 003, 004A, 004B, 004C, 004D, 018
- Lokey Labs: 053A, 063, 073, 073A, 080, 083A, 083A, 087A, 096A, 097A
Work Performed By: S2 Industrial, Air Inc.
Contact: Kevin Waldrop, CPFM Facilities Engineer, 541-346-2315