3/28/23 – 3/29/23 Lewis Integrative, Lokey Labs, and Willamette Process Chilled Water Shutdown

Begin:  Tuesday, March 28, 2023

End:      Wednesday, March 29, 2023

Building(s) or Area(s) Affected:  Lewis Integrative Science Building, Lokey Labs, and Willamette Hall

Scope:  CPFM Design and Construction will temporarily isolate individual process chilled water equipment drops in Lewis Integrative Science Building and Lokey Labs.  The process chilled water system needs a few final adjustments to complete the project to improve system operation, water quality, and redundancy.

3/28-3/29: Installation of additional ball valves on equipment drops in LISB and Lokey Labs will allow for bypass water flow when equipment is not connected. This will require equipment to be disconnected during installation.  Immediately following valve installation, the equipment can be reconnected.  The process chilled water system will remain active during this work and the only interruption will occur at individual equipment drops.

3/29-3/31: Water flow adjusting and balancing for the system will occur during this time.  A contractor will need to access each equipment drop and will make adjustments to the manual balance valves. Flow to individual equipment drops in Willamette may be disrupted for a few minutes if there is a manual balancing valve already installed in the bypass piping. Any interruptions in Willamette will be short and no other buildings have this condition, so they will not be impacted.

This will impact:

  • Willamette: Rooms 36, 39, 41C, 42, 154, 242, 255, 272, 273
  • LISB: 003, 004A, 004B, 004C, 004D, 018
  • Lokey Labs: 053A, 063, 073, 073A, 080, 083A, 083A, 087A, 096A, 097A

Work Performed By:  S2 Industrial, Air Inc.

ContactKevin Waldrop, CPFM Facilities Engineer, 541-346-2315

Current construction and impacts information can be found on the UO Maps site.

5/9/22 – 5/10/22 Willamette Hall Chilled Water Shutdown

Begin:  Monday, May 9th, 2022 at 2:00 pm

End:      Tuesday, May 10th, 2022 at 2:00 pm

Building:   Willamette Hall

Scope:    The chilled water has been shut down in order to install a new flow meter and valves.

Services Impacted:  Any process cooling fed from Willamette Hall.

Work Performed By:  CPFM Utilities & Energy and S2 Industrial

ContactKyle Wilson, CPFM Utilities Maintenance Manager, 541-346-2246

5/4/22 Willamette Hall, Lokey Labs, LISB Process Cooling Water System Testing Advisory

Begin:  Wednesday, May 4th, 2022 at 8:00 am

End:      Wednesday, May 4th, 2022 at 10:00 am

Building(s) or Area(s) Impacted:  Willamette, Lokey Labs, Laser Cooling, LISB (partial but not the MRI Cooling Water).

Scope:  We will be testing the industrial city water back up to the process cooling water system in Willamette Hall.  Building users of the process cooling may see a slight impact to process cooling water during the test.  Please notify CPFM Work Control of any major process cooling water temperature issues during the test.

Services Impacted:  This will affect the process cooling heat exchangers

Extra Notes:  This test will not impact MRI Cooling water in LISB.

Work Performed By:  CPFM FS Building Automation Systems Crew

ContactKyle Wilson, CPFM Utilities Maintenance Manager, 541-346-2246 or Stacy Breaux, CPFM FS Building Automation Systems Field Supervisor, 541-346-2304

CPFM Compound Back 40 Access Advisory 2/7/22 – 2/18/22

Begin:   Monday, February 7th, 2022

End:      Friday, February 18th, 2022

Building(s) or Area(s) Impacted:  CPFM Compound by Utilities & Energy Chilled Water Plant

Scope:  Due to cooling tower fill media replacement, contractors and a crane will be accessing the CPFM compound.  Contractors will be working in, around the plant, and on the roof between the 7th and 18th and the crane is expected between the 10th and 15th.

Services Impacted:  There will be little to no impact when accessing CPFM’s Back 40.

Work Performed By:  Contractor

ContactKyle Wilson, CPFM Utilities Maintenance Manager, 541-346-2246

LISB and Lokey Labs Process Cooling Water Shutdown 12/23/19

Begin:  Monday, December 23rd, 2019 at 6:00 am

End:     Monday, December 23rd, 2019 at 9:00 am

Building(s) or Area(s) Impacted:  LISB and Lokey Labs

Scope:  Need to modify the piping of the Process Cooling Water (PCW) system in the Willamette basement to benefit two renovation projects.

Services Impacted:  The Process Cooling Water will be offline to the Lokey Labs and Lewis Integrative Science Building (LISB) for the three hour duration. This will also impact CT rooms on the 3rd floor of LISB.

Special Instructions:  Please shutdown critical equipment connected to the system prior to 12/23 at 6:00 am.

ContactDenise Stewart, Owner’s Representative, 541-346-2280 or 541-335-1258

 

Willamette and Klamath Basements Process Cooling Water Shutdown 12/23/19

Begin:  Monday, December 23rd, 2019 at 6:00 am

End:     Monday, December 23rd, 2019 at 3:00 pm

Building(s) or Area(s) Impacted:  Willamette Hall Basement and Klamath Hall Basement

Scope:  Renovation work in the basement requires connecting to the Process Cooling Water (PCW) system.

Services Impacted:  The Process Cooling Water will be offline in both basements.

Special Instructions:  Please shutdown critical equipment connected to the system prior to 12/23/19 at 6:00 am.

ContactDenise Stewart, Owner’s Representative, 541-346-2280 or 541-335-1258