8/12/24 – 9/13/24 Knight Campus 2 Construction Work Odor Advisory

Begin:  Monday, August 12, 2024

End:      Friday, September 13, 2024

Building(s) or Area(s) Affected:  Knight Campus 2 and surrounding area

Scope:  Contractors will be installing hot rubber waterproofing products at the upper levels of the new construction, on the south & west sides.

Services Impacted:  Periodically through the work there could be a strong rubber odor in the adjacent areas – see map below.

Work Performed By:  Hoffman Construction

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

Current construction and impacts information can be found on the UO Maps site.

Overhead map image of area affected by Knight Campus 2's construction activity smell 8/12/24 - 9/13/24

7/22/24 – 8/08/24 Collier House Deck Repair and Refinishing

UPDATE:
The completion date has been extended to August 8th.

 

Begin:  Monday, July 22, 2024, at 6:00 am

End:      Friday, August 2  Thursday, August 8, 2024, at 5:00 pm

Building(s) or Area(s) Affected:  Collier House

Scope:  The deck will be repaired and refinished after the desk has been pressure washed July 18th and 19th.

Services Impacted:

  • No deck access July 18th – August 2nd.
  • Noise and odor can be expected during this time.

Work Performed By:  CPFM Facilities Services

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of Collier House and it's deck

7/20/24, 7/21,24, 7/27/24, 7/28/24, 8/05/24 Summer Parking Lot Painting Closures

UPDATE:
Western Asphalt will be back on Monday morning, August 5th, to paint the EV and ADA spaces.  The three lots listed will be shut down Sunday night and closed throughout the day on Monday.  However, once the paint is dry, the signs will be removed and the lots will be reopened.

  • 7B – NW corner of McKenzie Hall (ADA ramp yellow motorcycle)
  • 12B – N of Streisinger, Klamath, and NE of Onyx Bridge
  • 30 – S and E of McArthur Court and W and N of Student Tennis

 

1st Weekend:  Saturday, July 20, 2024 and Sunday, July 21, 2024

2nd Weekend:  Saturday, July 27, 2024, and Sunday, July 28, 2024

Scope: Summer parking lot maintenance will be performed on the weekends for the locations listed below.

Services Impacted: Lots will be closed the preceding Friday night for both Saturday and Sunday work.

Extra Notes: The lots will be re-opened as soon as the paint is dry.

Parking Lots Impacted Saturday, July 20, 2024:
3A – Strip N of Wilkinson House and Millrace Studios and S of ZIRC
3B – Parking areas N of Lock Shop and buildings N of Zebrafish
7A – W of Computing Center
7B – NW corner of McKenzie Hall (ADA ramp yellow motorcycle)
10 – N side of Lawrence Hall
12A – N of Cascade Annex West and East
47 – W and S of Rainier
57 – N of 1600 Millrace and S of the Millrace Garage
60 – SE of 1900 Millrace
Millrace Riverfront
13th Ave Crosswalk

Parking Lots Impacted Sunday, July 21, 2024:
12B – N of Streisinger, Klamath, and NE of Onyx Bridge
23 – E of Johnson Hall and W of Collier House
25 – E of JSMA and W of Susan Campbell
26 – S of Gerlinger Annex
27 – Horseshoe parking E of Hendricks
28 – Horseshoe parking E of Gerlinger Hall
29A – S of EMU
29B – SW corner of the EMU
29D – Street parking W of Straub
30 – S and E of McArthur Court and W and N of Student Tennis
36A – E of Carson and W of University Health Services
36B – SW corner of University Health Services
Carson Loading Dock
Johnson Fire Lane
University Street
15th Ave Crosswalks

Parking Lots Impacted Saturday, July 27, 2024:
33 – N and W of East Campus Graduate Village West
34B – N of Viv Olum Child Center
34C – E of Many Nations Longhouse/Viv Olum/Oregon Law Clinic
37 – Long lot E of Hamilton and W of Ford Alumni Center
39 – S of Agate Hall and Agate House and E of the Agate Apartments
41 – NE parking by Outdoor Program Barn and SW of Jane Sanders Stadium
43 – S of Knight Law Center
44 – Lot between East Campus Graduate Village East and West
46 –  E of Global Scholars Hall and N of NILI
51 – Long lot W of Black Cultural Center and E of NILI
52 – W of UOPD East Station
53 – UOPD lot between UOPD outbuildings and NE of UOPD Station
54 – UOPD lot E of Lot 53
55 – Long narrow parking strip E of Global Scholars Hall and Kalapuya Ilihi

Parking Lots Impacted Sunday, July 28, 2024:
6B – Half-moon N of Miller Theatre and McKenzie Hall, N side of East 11th Ave.
7B – NW corner of McKenzie Hall (ADA Ramp)
16A – NW of PLC and SW of Condon
16B – W of Condon
20 – E of Education Annex and N of Music
42 – W of UO Annex
50 – parking lot for Barnhart Residence Hall
Baker Downtown Center Loading Dock
EC Cares 1500 W. 12th Ave.

Work Performed By: Transportation Services

Contact: James McGladrey, UO Transportation Services Field Operations Manager, 541-346-2676

Overhead map of campus parking lots

7/15/24 – 7/17/24 Lots 45A and 45B (by Transportation Services) Asphalt Work Advisory

Begin:  Monday, July 15, 2024

End:     Wednesday, July 17, 2024

Parking Lot Impacted:

  • 45A and 45B (spaces surrounding and to the south of Transportation Services)

Scope:  Lots 45A and 45B will be closed for asphalt work.

Services Impacted:  The lots will be closed the preceding night.

Special Instructions:  Please use an alternate parking lot during this time.

Work Performed By:  Western Asphalt

ContactJames McGladrey, UO Transportation Services Field Operations Manager, 541-346-2676

https://map.uoregon.edu/transportation-uo
https://transportation.uoregon.edu/

Overhead aerial view of Parking Lots 45A and 45B next to Transportation Services office

7/12/24 and 8/05/24 Lot 1D/CPE (East of Baker Downtown Center) Asphalt and Painting Work Advisory

UPDATE:
Western Asphalt will be back on Monday morning, August 5th, to paint the EV and ADA spaces.  The lot will be shut down Sunday night and closed throughout the day on Monday.  However, once the paint is dry, the signs will be removed and the lot will be reopened.

 

Begin:  Friday, July 12, 2024

End:     Friday, July 12, 2024

Parking Lot Impacted:

  • 1D/CPE  (East of Baker Downtown Center)

Scope:  Lot 1D/CPE will be closed for asphalt work.

Services Impacted:  The lot will be closed the preceding night.

Special Instructions:  Please use an alternate parking lot during this time.

Work Performed By:  Western Asphalt

ContactJames McGladrey, UO Transportation Services Field Operations Manager, 541-346-2676

Overhead map image of Parking Lot 1D/CPD east of Baker Downtown Center

https://map.uoregon.edu/transportation-uo

https://transportation.uoregon.edu/

7/11/24 – 7/12/24 Lot 38 (North of Agate Hall) Asphalt Work Advisory

Begin:  Thursday, July 11, 2024

End:     Friday, July 12, 2024

Parking Lot Impacted:

  • 38 (North of Agate Hall)

Scope:  Lot 38 will be closed for asphalt work.

Services Impacted:  The lot will be closed the preceding night.

Special Instructions:  Please use an alternate parking lot during this time.

Work Performed By:  Western Asphalt

ContactJames McGladrey, UO Transportation Services Field Operations Manager, 541-346-2676

https://map.uoregon.edu/transportation-uo
https://transportation.uoregon.edu/

Overhead map view of Parking Lot 38 north of Agate Hall

 

 

6/18/24 – 6/29/24 Wilkinson House Exterior House Painting and Lot 3A Parking Advisory

UPDATE:

This work will continue through Saturday, June 29th.  The contractor will be painting the decks Friday and Saturday, on both the North and South sides and they will need the weekend to dry.  The building will be accessible on Monday, July 1, 2024.

REMINDER:

This work will begin on Tuesday and run through Friday, June 28th.

UPDATE:
Due to graduation taking place on Monday, the contractor notified us they will start their work on Tuesday, June 18th.

 

BeginMonday, June 17, Tuesday, June 18, 2024, at 6:00 am

End:      Friday, June 28, 2024, at 5:00 pm  Saturday, June 29, 2024

Building(s) or Area(s) Affected:  Wilkinson House and Parking Lot 3A

Scope:  A contractor will be removing the existing exterior paint, then repainting the building.

Services Impacted:  During this time, six parking spaces immediately north of the Wilkinson House will be blocked off.

Work Performed By:  Third Generation Paint Company

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Ariel view of Wilkinson House and the six parking spots immediately to the north

6/17/24 – 11/01/24 Klamath Hall Re-Roofing Project Advisory – Updated

UPDATE for Thursday, July 18, 2024, from 7:00 am to 7:15 am:
Lease Crutcher Lewis will shut down one roof top exhaust fan for 15 minutes.  The EF3-1 affects restrooms and service rooms on the third floor: All Gender Restroom 311, Service 312B, Women’s Restroom 312, Electrical 354, Men’s Restroom 353

Small map of Klamath rooms affected by AF3-1

UPDATE for Tuesday, June 18, 2024, from 7:00 am – 4:00 pm:
As part of the re-roofing project the contractor will be pressure washing during this time, noise associated with this can be expected in the building and surrounding areas.

UPDATE 6/14/24:

  • Interior stairs will only be used during the project’s first week 6/17 through 6/21. (There is no elevator in Klamath.)
  • The contractor will begin prep work on the roof from 6/17 through 6/21.
  • Construction for the reroofing project will begin on 6/24 and last 4-5 months.
  • Scaffolding will be placed on the northeast corner of the building for the duration of the project.
  • An indoor air quality management plan will be implemented to manage and monitor air quality in and around the site.

 

BeginMonday, June 3, 2024   Monday, June 17, 2024, at 7:00 am

End:      Friday, November 1, 2024, at 4:00 pm

Building(s) or Area(s) Affected:  Klamath Hall, Lokey Laboratories, Price Science Commons, Streisinger Hall, Willamette Hall, Huestis Hall, Onyx Bridge, Cascade Hall, Lewis Integrative Science Building

Scope:  A contractor will be re-roofing Klamath Hall.

Services Impacted:

  • Elevator and  The loading dock will be used temporarily throughout the project when needed.  Further notice will be provided during those times.
  • The project will have minimal noise and disruption.
  • Some materials used may cause a harmless odor.

Work Performed By:  Lease Crutcher Lewis

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impact information can be found on the UO Maps site.

Overhead view of Klamath Hall

6/03/24 – 11/01/24 Klamath Hall Reroofing Project Advisory

RESCHEDULED:
The dates for the roofing project were changed due to an updated schedule from the contractor.

 

BeginFriday, May 17, Monday, June 3, 2024, at 7:00 am

End:      Friday, June 28, Friday, November 1, 2024, at 4:00 pm

Building(s) or Area(s) Affected:  Klamath Hall

Scope:  A contractor will be reroofing Klamath Hall.

Services Impacted:

  • Elevator and loading dock will be used temporary throughout the project when needed.  Further notice will be provided during those times.
  • Project will have minimal noise and disruption.
  • Some material used may cause a harmless odor.

Work Performed By:  Lease Crutcher Lewis

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Image of Klamath Hall

4/12/24 – 9/27/24 Pacific Hall Room #013 Room Construction Activity

UPDATE #1:
Monday, June 24, 2024, 7:30 am – 4:00 pm
Due to the remodel, compressed air and lab vacuum lines will be temporarily shut down in rooms 9 and 10.

UPDATE #2:
Monday, June 24, 2024, 7:30 am – 4:00 pm
Due to the remodel, the tempered water and reverse osmosis water will be temporarily shut down in rooms 1 – 30 in the basement.

UPDATE #3:
Wednesday, June 26, 2024, 7:00 am – Friday, June 28, 2024, 4:00 pm
As part of the remodel, a contractor will be painting room 13.  A low VOC paint will be used but paint odor can be expected throughout the basement during this time.

 

Begin:  Friday, April 12, 2024, at 7:00 am

End:      Friday, September 27, 2024, at 4:00 pm

Building(s) or Area(s) Affected:  Pacific Hall room #013

Scope:  A conference room will be converted into a research lab.

Services Impacted:  Construction activity and noise can be expected during this time.  This will also affect parking and the loading dock.

Work Performed By:  Luna Design and Construction

ContactDavid Mason, CPFM Owner’s Representative, 541-346-5679

Current construction and impacts information can be found on the UO Maps site.

Image of Pacific Hall Room #013

4/17/24 – 4/23/24 Chapman Hall West Entry Closure Advisory

UPDATE 4/12/24:
This work has been rescheduled for Wednesday, April 17th, through Tuesday, April 23rd, from 8:30 am to 4:00 pm.

 

UPDATE 3/26/24:
The installation of the doors has been postponed due to a shortage of staff.  An update will be sent when it has been rescheduled.

 

BeginMarch 25, 2024, at 8:30 am   Postponed   Wednesday, April 17, 2024, at 8:30 am

End:      March 29, 2024, at 4:00 pm   Postponed   Tuesday, April 23, 2024, at 4:00 pm

Building(s) or Area(s) Affected:  Chapman Hall

Scope:  Refurbished doors will be installed, and the door frame and trim will be refinished.

Services Impacted:  West entry will be closed.

Special Instructions:  Use an alternative entrance.

Work Performed By:  CPFM Lock and Door Shop and Contractor

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Overhead view of Chapman

3/16/24 – 3/28/24 Huestis Hall AHU Shutdown

Begin:  Saturday, March 16, 2024

End:      Thursday, March 28, 2024

Building(s) or Area(s) Affected:  Huestis Hall

Scope:  Huestis Hall AHU will be shut down for final modifications and resurfacing of the penthouse traffic coating.

Services Impacted:

  • This will affect the exhaust and HVAC air supply.
  • The application of the traffic coating material may cause an odor.

Work Performed By:  Lease Crutcher Lewis

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

Image of Huestis Hall

3/13/24 – 4/05/24 Huestis Hall Exterior Work and Move-In Advisory

Begin:  Wednesday, March 13, 2024

End:      Friday, April 5, 2024

Building(s) or Area(s) Affected:  Huestis Hall and surrounding area

Scope:  The Huestis Hall Deferred Maintenance Project is nearing final completion and the following is a list of upcoming work and impacts around the building:

  • March 13 – Mulching around the south and east
  • March 21 – Construction fencing will be removed on the south and east sides of Huestis Hall.
  • March 22 – April 5 – Construction fencing will remain in place around the Streisinger courtyard to allow for the following site activities:
    • The Coast Redwood tree removal. The growth habit of this tree species in the location poses a risk to infrastructure, property, and life.
    • Replanting, mulching, and landscape repairs in the courtyard and west walkway between Huestis and Willamette Halls.
  • March 25 – Construction trailer will be removed from the site on E. 13th Ave.
  • April 1 – 30 – Occupant move in activities
  • May TBD – Exterior art work installation on the exterior brick of the south stair tower

I appreciate the patience and collaboration from all of our campus partners over the last 2 years! Thank you!!

Services Impacted:  This will affect parking, roadways, and sidewalks in the area.  Noise can also be expected from the activities listed above.

Work Performed By:  Lease Crutcher Lewis and Rexius

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

Image of Huestis Hall and surrounding area

2/23/24 Huestis Hall Sealant Application, Odor Advisory, and Exhaust Fan Shutdown

UPDATE:
The time has been extended an additional two hours, from 6:00 am to 11:00 am.

 

Begin:  Friday, February 23, 2024, at 6:00 am

End:      Friday, February 23, 2024, at 9:00 11:00 am

Building(s) or Area(s) Affected:  Huestis Hall, Willamette Hall, Lokey Labs

Scope:  Graffiti proof sealant will be applied to the exterior brick on Level 1/ground floor of Huestis Hall. The early morning hours were selected to decrease the amount of disruption to occupants during a typical work day. This notice is subject to rescheduling if weather conditions are unfavorable for installation.

Outage affecting Huestis basement: AHU 1 and 2 and lab exhaust fans will be offline during this work activity.

Advisory to Lokey Labs and Willamette Hall: Neighbors of Huestis Hall may experience odors due the sealant material.

Work Performed By:  Milne, Lease Crutcher Lewis

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

Map showing Huestis Hall

1/19/24 – 1/26/24 Prince Lucien Campbell Building Heat Advisory

UPDATE 1/26/24:
The repairs are complete and steam has been restored.

 

UPDATE 1/26/24:
The contractors will be cutting and welding the pipes during the steam outage today.  Occupants may experience a slight smoke smell during this activity.

 

UPDATE 1/25/24:
The needed part has been received and repair work will take place tomorrow, January 26th, from 7:00 am until the end of the day.  Steam will be shut down and heat will be offline during this time. A notice will be sent when the work has been completed.

 

Begin:  Friday, January 19, 2024 – effective immediately

End:      Unknown  Friday, January 26, 2024, at 1:00 pm

Building(s) or Area(s) Affected:  Prince Lucien Campbell

Scope:  Two steams valves for the heating system have failed.  A smaller valve was found to use temporarily until the new part arrives.  The contractor will install the new valves once received and they’ve been told to expect it on Friday.  An update will be sent when repairs have been completed.

Services Impacted:  Temperatures in the building are low.  The system is currently operating at approximately 30% to 40%.

Work Performed By:  CPFM Facilities and S2

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Prince Lucien Campbell

1/09/24 – 2/09/24 Oregon Hall Suite 380 Construction Activity Advisory

Begin:  Tuesday, January 9, 2024

End:      Friday, February 9, 2024

Building(s) or Area(s) Affected:  Oregon Hall

Scope:  Work to level the office and hall floors in Oregon Hall Suite 380 is underway. The contractor will be removing doors and prepping the space for the floor leveling compound to be poured.

Services Impacted:  There may be some light construction noise associated with the process.  This will affect Suites 380, 360, and 287.

Work Performed By:  Bridgeway Construction

ContactJanell Cottam, CPFM Owner’s Representative, 541-346-7536

Current construction and impacts information can be found on the UO Maps site.

Image of Oregon Hall L380

 

 

1/12/24 – 5/17/24 Willamette Hall Room 154 Renovation Work Advisory

UPDATE:
Renovations and remodeling are still in process and the end date has been extended into the middle of May.

 

Begin:  Friday, January 12, 2024, at 8:00 am

End:      March 31   Friday, May 17, 2024, at 4:00 pm

Building(s) or Area(s) Affected:  Willamette Hall room 154

Scope:  Room 154 will undergo renovation and remodeling.

Services Impacted:  Contractors will be present in the building and lobby plus noise and odor can be expected with this type of work.

Work Performed By:  Bridgeway Contracting

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Image of Willamette 154

12/18/23 – 1/12/24 Knight Library Hallways H116 and H148 Construction and Access Advisory

Begin:  Monday, December 18, 2023, at 7:30 am

End:      Friday, January 12, 2024, at 4:00 pm

Building(s) or Area(s) Affected:  Knight Library hallways H116 and H148

Scope:  A contractor will be doing demolition and construction in hallways H116 and H148. They are replacing the four display cabinets in these halls. These are the two main North South passageways from the entrance to the body of the library.

Services Impacted:  There may be a temporary re-route from one hallway to the other during the demolition process.

Special Instructions:  Please watch for signage.

Work Performed By:  Richards Remodeling

ContactJanell Cottam, CPFM Owner’s Representative, 541-346-7536

Current construction and impacts information can be found on the UO Maps site.

Image of Knight Library Hallways H116 and H148

12/26/23 – 12/27/23 Campus Winter Grease Trap Cleaning Advisory

Begin:  Tuesday, December 26, 2023, at 9:00 am

End:      Wednesday, December 27, 2023, at 4:00 pm

Scope:  Housing and Dining will have a contractor clean the grease traps in select areas of campus – see schedule below

Buildings and Schedule:

Tuesday, December 26th

  • 9:00 am – Central Kitchen (plus jetting)
  • 10:00 am – Living Learning Center
  • 11:00 am – Global Scholars (plus jetting)
  • 11:30 am – Ford Alumni
  • 12:00 noon – Carson Hall (plus jetting)
  • 1:00 pm – Barnhart Hall (plus jetting)
  • 1:00 pm – Spencer View
  • 2:00 pm – Unthank Hall (plus jetting)

Wednesday, December 27th

  • 9:00 am – Tykeson Hall
  • 10:00 am – EMU (plus jetting)
  • 10:30 am – Knight Library
  • 12:00 noon – HEDCO
  • 1:00 pm – Lillis Café
  • 2:00 pm – Unthank Hall (plus jetting)
  • 2:30 pm – Lawrence Hall

Services Impacted:  Noise can be expected in the area, along with the possibility of encountering unpleasant odors outside the building with potential drift inside via entryways.

Work Performed By:  Roto Rooter

ContactFarrah Meade, University Housing, HCS & Work Control Manager, 541-346-4082

Current construction and impacts information can be found on the UO Maps site.

Image of buildings affected by the Winter 2023 grease trap cleaning

 

 

10/30/23 – 11/03/23 Johnson Hall Women’s Restroom #006 Shutdown

UPDATE 11/09/23:
The initial ceiling repair took place yesterday by one of our night crew technicians. The remainder of the work will be done with the night crew and not impact occupants.  We will make sure that the restroom is fully accessible today for use including the sinks that were blocked off.

 

Begin:  Monday, October 30, 2023, at 7:30 am

End:      Friday, November 3, 2023, at end of day

Building(s) or Area(s) Affected:  Johnson Hall Restroom 006

Scope:  Due to water intrusion Restroom 006 will be closed for repairs.

Services Impacted:  Restroom will be shut down.  Construction noise and odor can be expected during this time.

Special Instructions:  Please use the all-gender restroom 006A or the Women’s restroom on the 2nd floor.

Work Performed By:  CPFM Facilities Services

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Women's restroom #6 in Johnson Hall

10/11/23 – 10/13/23 Knight Library H035 Painting Advisory

Begin:  Wednesday, October 11, 2023

End:      Friday, October 13, 2023

Building(s) or Area(s) Affected:  Knight Library

Scope:  Hallway H035 is being painted today through Friday.

Services Impacted:    Ultra-low VOC paint will be used, but some odor can be expected.

Work Performed By:  CPFM Facilities Services

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Knight Library Hallway H035

 

10/11/23 – 10/12/23 Cascade Hall 305D Painting Advisory

Begin:  Wednesday, October 11, 2023

End:      Thursday, October 12, 2023

Building(s) or Area(s) Affected:  Cascade Hall

Scope:  Room 305D is being painted today and tomorrow.

Services Impacted:    Ultra-low VOC paint will be used, but some odor can be expected.

Work Performed By:  CPFM Facilities Services

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Cascade Hall Room 305D

 

9/27/23 – 10/05/23 Oregon Hall 3rd and 4th Floors Painting Advisory 9/27/23 – 10/05/23

Begin:  Wednesday, September 27, 2023, at 8:00 am

End:      Thursday, October 5, 2023, at 3:30 pm

Building(s) or Area(s) Affected:  Oregon Hall V351, V353, H450

Scope:  Paint repair work will be taking place outside the restrooms in the east wing on the 3rd and 4th floors.

Services Impacted:  Ultra-low VOC paint will be used, but some odor can be expected.

Work Performed By:  CPFM Facilities Services

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Oregon Hall V351 and V353
Image of Oregon Hall H450

 

9/25/23 – 3/01/24 Huestis Hall East Side Planter Excavation Work Advisory

UPDATE 2/01/24:
Odorous work is complete for this week.  However, there will be more waterproofing material installation next week, currently anticipated for Tuesday and Wednesday, February 13 and 14, as weather permits.

 

UPDATE 1/26/24:

  • Waterproofing work continues next week at the east side planter. Occupants and neighbors may experience construction related noise, vibration and odors due to the waterproofing material installation.
  • The landscaping portion of work, including sidewalk work, backfilling with soil, and plantings, is anticipated to be complete by March 1.

 

UPDATE 10/27/23:
Work has been extended through the end of November.  This extension will include the final put back of soils and landscaping repair.

 

Begin:  Monday, September 25, 2023

End:      October 31, November 30, 2023,  March 1, 2024

Building(s) or Area(s) Affected:  Huestis Hall and Lokey Labs

Scope:  As part of the Huestis Renovation Project, the east side planters will be excavated out to repair waterproofing connections between Huestis Hall and Lokey Labs.

Services Impacted:  Occupants and neighbors may experience construction related noise, vibration and odors due to the waterproofing material installation.

Work Performed By:  Weitman and Lease Crutcher Lewis

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

Image of Huestis Hall and Lokey Labs

10/02/23 – 11/10/23 CPFM Warehouse 116, 116B, 116C, and 116D Construction Activity Advisory

Begin:  Monday, October 2, 2023

End:      Friday, November 10, 2023

Building(s) or Area(s) Affected:  CPFM Warehouse rooms 116, 116B, 116C, and 116D

Scope:  The portion of room 116, adjacent to the Mechanical and Plumbing offices, will be under construction.

Services Impacted:  Typical light construction noises, including cutting and drilling, are expected.

Work Performed By:  CPFM Facilities Services

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of construction area in CPFM Warehouse