Begin: Friday, August 22, 2025, at 8:00 am
End: Friday, August 22, 2025, at 3:30 pm
Building(s) or Area(s) Affected: Walkway between Straub and Young Hall on the South end of Straub.
Scope: We will be pulling our boom lift into the egress walkway on the south end of Straub Hall to reach gutter downspouts inside the south courtyard. We will be working above the S196 stairwell exit on the downspout collection boxes.
Services Impacted: There will be no egress in or out of the south Straub courtyard on this walkway.
Work Performed By: CPFM Maintenance Support
Contact: Gabe Hein, CPFM Maintenance Support Supervisor, 541-346-7563
Work Control Center, Campus Planning and Facilities Management, 541-346-2319
Current construction and impacts information can be found on the UO Maps site.