Begin: Monday, January 12, 2026, at 8:00 am
End: Friday, January 16, 2026, at 5:00 pm
Building(s) or Area(s) Affected: 1776 Millrace
Scope: The exterior windows will be cleaned by a contractor next week.
Services Impacted:
- Windows are to remain closed during this time.
- The boom lift will be used throughout the process.
- A slight noise is to be expected when the windows are cleaned.
- There may be a disruption to the northside parking spaces when the northside of the building is being cleaned.
Work Performed By: Cutting Edge Window Cleaning Services LLC
Contact: Nick Grant, CPFM Custodial Operations Supervisor, 541-346-2653
Work Control Center, Campus Planning and Facilities Management, 541-346-2319
Current construction and impacts information can be found on the UO Maps site.