9/02/25 – 9/09/25 and 11/18/25 – 1776 Millrace Exterior Window Preventative Maintenance Work Advisory
Posted on

UPDATE 11/17/25:
Culver Glass has rescheduled this for tomorrow, Tuesday, November 18th, starting at 8:00 am.

UPDATE 11/13/25:
Culver Glass just informed us that this has been postponed due to some emergency work and the weather.  The new date is yet to be determined.

UPDATE 11/12/25:
Culver Glass will be performing a second round of work on the exterior windows tomorrow 11/13 and Friday 11/14.

 

Begin: Tuesday, September 2, 2025

End:   Tuesday, September 9, 2025

2nd RoundNovember 13 & November 14     Tuesday, November 18, 2025

TBD

Building(s) or Area(s) Affected: 1776 Millrace

Scope: Culver Glass will be performing preventative maintenance on the exterior windows.

Services Impacted:

  • Occupants can expect to see contractors using ladders, scaffolding or lifts to scrape and caulk the windows around the building exterior.
  • All work will be performed outside the building and no other impacts are anticipated.

Work Performed By: Culver Glass

Contact: Justin Grishkin, CPFM Construction Services Manager, 541-346-5242 or 541-510-0143

Work Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of 1776 Millrace

8/28/25 – 8/29/25 Unthank Hall Emergency Steam Shutdown
Posted on

UPDATE:  The repair has been completed, and steam is now being returned to the building.  It may take several hours before full building heat and hot water are available.

Begin:  Thursday, August 28, 2025 – effective immediately

End:      Friday, August 29, 2025, at 12:00 noon

Building(s) or Area(s) Affected:  Unthank Hall

Scope:  Steam has been turned off for an emergency leak repair.

Services Impacted:

  • No building heat or hot water will be available until the repair is complete.
  • Minimal impact is expected as catering is currently shutdown at this time.

Work Performed By:  CPFM Utilities & Energy

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of Unthank Hall

9/1/25 – 9/26/25 Campus Fire Systems Testing and Maintenance Schedule for Summer 2025
Posted on

UPDATE 9/19/25:
On Wednesday, September 24th, fire systems testing and maintenance will take place at Alder Building instead of 1776 Millrace.

 

Begin:  Monday, September 1, 2025

End:     Friday, September 26, 2025

Scope:   Summer 2025 Fire Systems Testing and Maintenance has been scheduled for the various campus buildings listed below.  Reminders will be sent to each building prior to testing.

Week of 9/01 – 9/05
Monday – 9/01              No testing – Labor Day
Tuesday – 9/02           8:00 am – 3:00 pm – Global Scholars Hall
Tuesday – 9/02           9:00 am – 3:00 pm – Unthank Hall Kitchen
Wednesday – 9/03      6:00 am – 3:00 pm – Global Scholars Hall
Wednesday – 9/03      6:00 am – 3:00 pm – Unthank Hall Kitchen
Thursday – 9/04         6:00 am – 8:00 am – CPFM Warehouse
Thursday – 9/04         7:00 am – 12:00 noon – Kalapuya Ilihi
Thursday – 9/04         8:00 am – 3:00 pm – Global Scholars Hall
Thursday – 9/04         6:00 am – 3:00 pm – Unthank Hall Kitchen
Friday – 9/05              8:00 am – finished – Global Scholars / CPFM Makeup/Repair

Week of 9/8 – 9/12
Monday – 9/08            6:00 am – 8:00 am – TBD
Monday – 9/08            8:00 am – 3:00 pm – Kalapuya Ilihi
Tuesday – 9/09            6:00 am – 9:00 am – Ford Alumni Center
Tuesday – 9/09            8:00 am – 3:00 pm – Kalapuya Ilihi
Wednesday – 9/10       6:00 am – 9:00 am – Erb Memorial Union
Thursday – 9/11            6:00 am – 8:00 am – Kalapuya Ilihi
Friday – 9/12

Week of 9/15 – 9/19
Monday – 9/15
Tuesday – 9/16            6:00 am – 9:00 am – Jordan Schnitzer Museum of Art
Wednesday – 9/17       6:00 am – 9:00 am – Jaqua Academic Center
Thursday – 9/18          6:00 am – 8:00 am – EC Cares (W. 12th Ave.)
Friday – 9/19

Week of 9/22 – 9/26
Monday – 9/22
Tuesday – 9/23           6:00 am – 9:00 am – 1600 Millrace
Wednesday – 9/24     6:00 am – 9:00 am – 1776 Millrace   Alder Building
Thursday – 9/25         6:00 am – 8:00 am – TBD
Friday – 9/26

Details: Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions: If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By: UO Safety & Risk Services

Contact: Zach Earl, UO Fire Protection Manager, 541-521-0351 or 541-346-9295.

Current construction and impacts information can be found on the UO Maps site.