5/23/25 – 5/24/25 Millrace Waterway Pump Intake Annual Screen Cleaning Advisory
Posted on

Begin:  Friday, May 23, 2025, at 7:00 am

End:      Saturday, May 24, 2025, at 5:00 pm

Building(s) or Area(s) Affected:  Millrace Waterway Intake Pump Station and Canal

Scope:  The intake pumps will be shut down for the annual cleaning of the Millrace pump intake screens.

Services Impacted:  Minimal to no impact. Contractors will be working in the Willamette River at the intake pump station. Millrace water levels may be lower depending on the amount of rain and storm sewer run off.

Work Performed By:  Big Fish Scuba

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319