1/29/25 – 1/30/25 Frohnmayer Music Building Emergency AHU-1 Shutdown
Posted on

UPDATE:  The repair has now been completed and all systems in the building are now back online.

UPDATE:  An electrical panel will be shutdown today 1/30/25 at 1:00 pm for 2 hours to replace a breaker for AHU-1.  The panel also serves AHU-2 which will shutdown heating to the following additional spaces for 2 hours. Rooms 105, 109, 118,120, 203, 205, 207, Vestibule V220, and Lobby L120.

Begin:  Wednesday, January 29, 2025

End:      unknown Thursday, January 30, 2025

Building(s) or Area(s) Affected:  Frohnmayer Music Building

Scope:  Due to a yet to be determined cause, a reset on the freeze stat for AHU-1 continues to cause an electrical breaker to trip.  As a result, that Air Handling Unit will be shutdown until the issue can be resolved.

Services Impacted:  All rooms on the first and second floors represented on the maps below are served by AHU-1 and can expect the heat to be affected by this shutdown.  An update will be sent out when the equipment is back online.

Work Performed By:  CPFM Facilities Services

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

2/03/25 – 2/04/25 – 1715 Franklin Rooms 180 – 199 HVAC Work Advisory
Posted on

Begin:  Monday, February 3, 2025, at 7:00 am

End:      Tuesday, February 4, 2025, at end of day

Building(s) or Area(s) Affected:  1715 Franklin

Scope:  Harvey and Price will be onsite Monday at 7:00 am to add remote sensors in rooms 180 to 199.  The work will be minimally invasive and should take about 15 minutes per room.

Additionally, they will be installing a mini split system in room 183C which will take most of the day and probably commissioning on Tuesday 2/4/2025.

Services Impacted:  No impact is expected other than noise during the install and workers in the building.

Work Performed By:  Harvey & Price

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.