12/30/24 Unthank Hall and Knight Law Center Steam Shutdown
Posted on

Begin:  Monday, December 30, 2024, at 7:00 am

End:      Monday, December 30, 2024, at 5:00 pm

Building(s) or Area(s) Affected:  Unthank Hall and Knight Law Center

Scope:  Due to a steam pipe leak in the utility tunnel, steam will be shut down to replace a section of piping.

Services Impacted:  This will affect the building heat and the domestic hot water.

Special Instructions:  Please dress accordingly for the cooler temperatures.

Work Performed By:  CPFM Utilities & Energy and S2 Industrial

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of Unthank Hall and Knight Law Center

12/26/24 Streisinger Hall Heating Water Shutdown
Posted on

Begin:  Thursday, December 26, 2024, at 7:00 am

End:      Thursday, December 26, 2024, at 4:00 pm

Building(s) or Area(s) Affected:  Streisinger Hall

Scope:  The 3rd floor heating will be shut down to change out a failed heating water valve.

Services Impacted:  This will only affect the 3rd floor building heat.

Special Instructions:  Please dress accordingly for the cooler temperatures.

Work Performed By:  CPFM Crews

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of Streisinger Hall