8/17/22 – Unknown – University Health Services Basement Emergency AHU-1 Shutdown
Posted on

UPDATE:  We were informed that this was previously restored.

 

Begin:  Wednesday, August 17th, 2022 – effective immediately

End:      Unknown

Building(s) or Area(s) Affected:  University Health Services

Scope:  The chilled water pump for AHU-1 needs to be replaced.  The pump has been ordered and is expected to take approximately two weeks to arrive.

Services Impacted:  The cooling will be offline in the basement only.

Work Performed By:  CPFM FS Mechanical Crew

ContactKyle Harshbarger, CPFM Mechanical and Plumbing Shop Manager, 541-346-5406 or Dan Pennisi, CPFM Mechanical Shop, 541-346-2319

To view current construction and impacts, visit UO Map.

8/17/22 Huestis Hall Heating Water Loop Shutdown
Posted on

Begin:  Wednesday, August, 17th 2022 at 7:00 am

End:      Wednesday, August 17th 2022 at 6:00 pm

Building(s) or Area(s) Impacted:  Huestis Hall

Scope:  Due to Huestis Renovation Project there will be a heating water loop shutdown in the basement

Services Impacted:  HX-1 AHU 1 and 2, steam sterilizers, reheat coils and TUS in Huestis basement

Work Performed By:  Contractor

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880