6/16/22 – 6/17/22 Frohnmayer Music Courtyard Pressure Washing
Posted on

Begin:  Thursday, June 16th, 2022 at 8:30 am

End:      Friday, June 17th, 2022 at 4:30 pm

Building(s) or Area(s) Affected:  Frohnmayer Music Courtyard

Scope:  CPFM staff will be pressure washing the Music Building Courtyard this Thursday and Friday.

Services Impacted:  Access to the ADA ramps to the building will be open, but there will be hoses and equipment that may need to be moved in order to access the ramps.

Special Instructions:  Please use an alternative entrance if possible.

Work Performed By:  CPFM Facilities

ContactDonny Addison, CPFM Zero Waste Solid Waste Manager, 541-346-0961

To view current construction and impacts, visit UO Map.

6/16/22 Huestis Hall Basement HVAC Shutdown
Posted on

Begin:  Thursday, June 16th, 2022 at 11:00 am

End:      Thursday, June 16th, 2022 at 2:00 pm

Building(s) or Area(s) Affected:  Huestis basement rooms 17, 20, 20B, 21, 21A, and 31

Scope:  As part of the Huestis Renovation Project, supply fan 2-B will be shutoff for 3 hours.

Services Impacted:  This work will affect heating and cooling air supply to the Huestis basement rooms.

Work Performed By:  Mortenson Construction

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

To view current construction and impacts. visit UO Map.

6/15/22 Volcanology Drinking Water Notification
Posted on

Hi All:

This notification is provided as an update to the water issues that have been reported in the Volcanology Building during the Spring of 2022. The issues reported have been centered around discoloration in the water. The discoloration is due to rust in the piping. The following actions have been taken or are planned to remedy the situation:

  1. The building fixtures were inventoried. It was determined that dedicated drinking water fixtures are present in the first and second floor hallways as drinking fountains. All of the other fixtures in the building are lab fixtures and are not intended for drinking water use. They will not be managed as drinking water fixtures.
  2. In early May, the piping to the first floor drinking fountain was flushed and the filter in the first floor drinking fountain was changed. This did not remove the noted discoloration.
  3. Last week, then entire building plumbing system was flushed and the filter in the first floor drinking fountain was upgraded to a charcoal filter. This appears to have helped, but we’ll see how long it lasts.
  4. A charcoal filter will be added to the second floor drinking fountain.
  5. The water from the first and second floor drinking fountains will be tested for corrosion byproducts after the second floor fixture has been addressed.

If you identify discoloration in the drinking fountains, please notify me ASAP at asjones@uoregon.edu. We will coordinate with CPFM and try additional mitigation steps to work towards solving the problem.

Thanks,

Adam S. Jones, CIEC | Environmental Services Manager
Safety and Risk Services
Environmental Health & Safety
1260 University of Oregon | Eugene, OR 97403-1260
(541) 346-8397 | asjones@uoregon.edu
(541) 852-5685

6/15/22 Huestis Hall Clean Steam Shutdown
Posted on

Begin:  June 15, 2022 at 7:30 am

End:      June 15, 2022 at 3:30 pm

Building(s) or Area(s) Affected:  Huestis Hall

Scope:  As part of the Huestis Renovation Project, building clean steam will be shutdown and unavailable.

Services Impacted:  Autoclave Steam, Steam Condensate

Work Performed By:  Mortenson Construction and JH Kelly

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880