Lokey Labs Emergency Heating Water Shutdown 3/8/22
Posted on

UPDATE:
The heating water has been restored.

 

Begin:  Tuesday, March 8th, 2022 at 7:00 am

End:      Tuesday, March 8th, 2022 at 2:00 pm

Building(s) or Area(s) Impacted:  Lokey Labs (CAMCOR)

Scope:  An emergency repair needs to be made on a 2” copper 180° heating supply line and will require the heating water to be shut down.

Services Impacted:  Heating water will be offline during this time.

Work Performed By:  CPFM FS Plumbing Shop

ContactRon Warren, CPFM Facilities Plumbing, 541-346-2319

Klamath Hall Ground Floor Electrical Shutdown 3/12/22
Posted on

Begin:  Saturday, March 12, 2022 at 7:00 am

End:  Saturday, March 12, 2022 at 3:00 pm

Building(s) or Area(s) Impacted:   Klamath Hall Ground Floor – see specific rooms affected below

 Scope:   Power will be shut down to electrical panel serving portions of the Ground floor while contractors connect additional circuits for room 019.

Services Impacted:  Electrical power will be shut down to rooms 018, 019, 019A, 019B, 019C, 019D, 021, 023, 024, 030, 032, 033, 065, 065A-065C, 053, 073A, 075, 075A and the corridor lights will be off in hallways H002, H004, H005, and H006.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.

Work Performed By: Mortenson Construction, EC Electric

ContactTim Allenbaugh, CPFM Owner’s Representative, 541-346-8214

 

Campus AHU Preventative Maintenance Schedule for March 2022
Posted on

Begin:  March 1st, 2022

End:     March 31st, 2022

Building(s) or Area(s) Impacted:

  • Music
  • HEDCO
  • Clinical Services
  • Lokey Ed A&B
  • Lokey Ed C
  • Education Annex
  • Berwick Hall
  • 510 Oak Street
  • UOPD East Station

Scope:  Preventative Maintenance work will be performed, over the course of the month, for the buildings listed above.

Services Impacted:  No services are expected to be impacted.

Work Performed By:  CPFM Preventative Maintenance Crew or Contractor

ContactJim Cody, CPFM Associate Dir. of Facilities Services, 541-346-2302

Huestis Hall Elevator Shutdown Monday 3/7/2022 at 08:15 am – Unknown – UPDATE
Posted on

UPDATE: elevator service is restored

Begin:  March 7, 2022 at 08:15 am

End:      Unknown

Building(s) or Area(s) Impacted:  Huestis Hall Elevator

Services Impacted:  No elevator service.  Please use stairs.

Extra Notes: Elevator Service Technician dispatched and will arrive at 9:30 am

Work Performed By:  Otis

Contact: Work Control Center, Campus Planning and Facilities Management, 541-346-2319