Tykeson Hall and Chapman Hall Lawn Renovation Advisory 3/29/21 – 7/30/21
Posted on

UPDATE 7/28/21:

The fencing will remain in place through August.

 

UPDATE 7/15/21:

The fencing will remain in place until the end of July. Work is expected to be complete by July 30th.

 

UPDATE 7/7/21:

The work is still ongoing and is expected to be complete on July 23rd, 2021.

 

2nd UPDATE 5/25/21:

Concrete Work Advisory extended to 6/07/21

Due to the recent wet weather conditions, the concrete pour was delayed.  Therefore, the west entry to Tykeson will remained blocked until Tuesday, June 1.  The  construction fence will remain in place and block the west entry. This will allow for adequate cure time on the newly poured concrete.

The remainder of the concrete flatwork pavement will be poured on June 6 and 7. The west end of Johnson Lane will be blocked during these days for the concrete trucks.

 

UPDATE 5/5/21:

Concrete Work Advisory 5/17/21 – 5/28/21 6/7/21 7/23/21 7/30/21 8/31/21

Scope:  As part of the Tykeson Lawn Renovation Project, Delta Construction will be removing and pouring concrete panels outside Tykeson Hall’s west entry.

Services Impacted:  The construction fence will be moved to block access to the west entry/exit of Tykeson Hall and close the seating area under the west canopy.

Special Instructions:  See diagram below for the area involved.

Work Performed By:  Delta Construction

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

 

 

Original Notice

Begin:  Monday, March 29th, 2021

End:      Wednesday, June 30th, 2021

Building(s) or Area(s) Impacted:  Lawn between Tykeson Hall and Chapman Hall

Scope:  Fortis Construction will begin work on site next week for the renovation of the lawn area between Tykeson Hall and Chapman Hall. This exterior project will close access to the lawn until completion at the end of June. The project includes new hardscape pathways and landscape mounds with seat walls.

Services Impacted:

  • Building entries and access to Chapman and Tykeson Halls will be maintained and not impacted.
  • Typical construction activities and noises, including the sound of beeping from vehicles backing up, is to be expected in and around the landscape and hardscape areas.

Work Performed By:  Fortis Construction

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Lillis AMAG Panel Maintenance Advisory 3/24/21 – 3/25/21
Posted on

UPDATE 3/24/21:

AMAG Maintenance/Panel Upgrades will continue at Lillis Complex on Thursday, 03/25/2021, from 7:45 am – 5:oo pm. Restricted access permissions continue and we will again have UOPD staff in the building to assist if any access needs arise. Please contact the SOC at 541.346.2919 ext. #2 via phone if you are experiencing any issues.

 

Original –

Lillis Hall will be undergoing AMAG panel maintenance as well as hardware upgrades Wednesday, 03/24/2021 (tomorrow), from 7:45 am to 5:00 pm. Regular authorized building access should not be impacted (Spring Break Restricted Access Only), but if issues arise, UOPD will provide building access requests via the SOC at 541.346.2919 ext. #2. We will have a Community Service Officer on site in the Lillis atrium/building during the panel maintenance to support your needs.

ContactBenjamin McNulty, UOPD Dir Security & Support Service, 541-285-5904