Huestis Hall Lab Cold Water Shutdown 12/10/20
Posted on

Begin:  Thursday, December 10th, 2020 at 8:00 am

End:      Thursday, December 10th, 2020 at 12:00 noon

Building(s) or Area(s) Impacted:  Huestis Hall

Scope:  Installation of a new valve for the lab cold water.

Services Impacted:  This shutdown will affect all lab sink faucets, ice makers, and the cold water for fume hoods.

Work Performed By:  CPFM Facilities Plumbing Shop

ContactOlin Vermillion, CPFM Facilities Plumbing, 541-346-2319

Carson Hall Electrical Shutdown 12/21/20
Posted on

Begin:  Monday, December 21, 2020, at 8:00 am

End:      Monday, December 21, 2020, at 4:00 pm

Building Impacted:  Carson Hall

Scope:  Due to a leaking bushing on the medium voltage side of the transformer, the power will be de-energized for 8 hours while a contractor makes repairs.

Services Impacted:  The entire building will be without 208 volt power.

Special Instructions:  Please shut down all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when power is turned back on, a power surge can corrupt the clone files in the machines, and can change preconfigured settings.

Work Performed By:  CPFM Utilities & Energy and contractor

ContactRick Tabor, CPFM Interim Co-Dir Utilities and Facilities Management, 541-346-7511

Campus Wide Soap Dispenser Installations for 12/2/20
Posted on

Installations for 12/02/20:
Listed below are the buildings expected to be serviced Wednesday, December 2nd, 2020.
Additional notification will be sent if installers are unable to finish on the projected date.

Columbia Hall
Pacific Hall
Volcanology
Cascade Hall
Cascade Annex
Onyx Bridge
Price Science Commons

ORIGINAL NOTICE

Begin: Monday, November 9th, 2020

End: Friday, December 4th, 2020

Building(s) or Area(s) Impacted: Campus Wide Academic Buildings

Scope: The manufacturer is discontinuing our current soap refills, so we are transitioning to a different soap dispenser across the academic campus. Since this transition is manufacturer caused, they are providing the contractor to do the install at no cost to the university.

Services Impacted: Temporary access to soap dispensers in restrooms, labs, teachings spaces, and kitchenettes.

Extra Notes: Each install will only take a few minutes but there are thousands across campus.

Work Performed By: Home Depot Pro

Contact: Tim Winder, CPFM FS Custodial Services Manager, 541-346-5771