11/17/23 Klamath Hall Lab Exhaust Fan Testing and Fume Hood Shutdown

Begin:  Friday, November 17, 2023, at 7:00 am

End:      Friday, November 17, 2023, at 8:00 am

Building(s) or Area(s) Affected:  Klamath Hall – Basement, Ground, First, and Second Floors

Scope:  Lab exhaust fans will be shut off for 5-10 minutes to test alarm activation and notification.

Services Impacted:  Fans will be tested one at a time, reduced exhaust air volume can be expected and some local low flow alarms at fume hoods.

Special Instructions:  Fume hood sashes should be closed and containers within the fume hoods sealed prior to this date.

Work Performed By:  CPFM Facilities, Siemens

ContactKevin Waldrop, CPFM Facilities Engineer, 541-346-2315 or 541-525-4326

Current construction and impacts information can be found on the UO Maps site.

Image of Klamath Hall

11/07/23 Willamette Hall Domestic Hot Water Shutdown

Begin:  Tuesday, November 7, 2023, at 7:30 am

End:      Tuesday, November 7, 2023, at 10:30 am

Building(s) or Area(s) Affected:  Willamette Hall

Scope:  The domestic hot water will be shut down while repairs are made to the sink in the basement room 33.

Services Impacted:

  • This will affect all restrooms, custodial sinks, and any other domestic hot water source within the building.
  • Lab industrial hot water will not be effected by this shut down.

Work Performed By:  CPFM Facilities Services

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Willamette Hall

10/31/23 Johnson Hall Roof Repair Advisory

Begin:  Tuesday, October 31, 2023, at 7:00 am

End:      Tuesday, October 31, 2023, at 3:30 pm

Building(s) or Area(s) Affected:  Johnson Hall

Scope:  Roof repairs will take place on the front portico of Johnson Hall.

Services Impacted:  This will affect the front entry area at the base of the steps.

Work Performed By:  CPFM Facilities Services

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Johnson Hall

11/03/23 Lot 12B (North of Streisinger Hall) Shutdown

Begin:  Friday, November 3, 2023, at 7:00 am

End:      Friday, November 3, 2023, at 10:00 am

Building(s) or Area(s) Affected:  Lot 12B (North of Streisinger Hall)

Scope:  Due to a crane pick, the east side of lot 12B (shown as pictured) will not be available for use during this time.

Services Impacted:

  • The area will be cordoned off, but please be sure to maintain your awareness in the surrounding area and to take alternative paths as needed.
  • This will also affect the adjacent loading dock.

Work Performed By:  Bridgeway Construction & Hermanson

ContactDamon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285

Current construction and impacts information can be found on the UO Maps site.

Image of Lot 12B

 

11/03/23 – 11/06/23 Huestis Hall, Lokey Labs, Streisinger Hall, Klamath Hall, and Willamette Hall Electrical and RO/DI Water Shutdown

UPDATE/CORRECTION:
Network servers will be down on Friday, November 3rd.  Users should power down computers and equipment.

 

Begin:  Friday, November 3, 2023 – see times below

End:      Monday, November 6, 2023 – see times below

Building(s) or Area(s) Affected:  Huestis Hall, Lokey Labs, Streisinger Hall, Klamath Hall, and Willamette Hall

Scope:  As part of the Huestis Renovation project, there will be a series of electrical shutdowns necessary to make the final connections for the project.  These shutdowns will impact Huestis Hall and neighboring science buildings.  The first series of shutdowns will occur on November 3 and November 6.  Affected services and durations are listed by date and building below.

Friday, November 3, 5:00 am – 9:00 am – Electrical to Huestis Hall, Lokey Labs.  RO supply to Klamath Hall, Streisinger Hall, Willamette Hall

Huestis Hall: Electrical shutdown will affect all equipment on normal power during the transfer of normal loads to generator back up.  All services provided by steam, chilled water, HVAC supply and exhaust will be affected during the transitions from normal to backup and again.  Huestis RO faucets will be offline.

Network servers will be supported by local UPS units and battery panels.

Lokey Labs: Electrical shutdown will affect all equipment and systems running on normal power in rooms 76, 87 and 96.  Occupants are advised to power down all equipment in rooms 76, 87 and 96.  Chilled water will be offline.  Standby will also be offline and unavailable for this duration.

Klamath Hall, Streisinger Hall, and Willamette Hall: RO water supply will not be available as booster pump 1 will be offline in Huestis Hall during this outage.

Monday, November 6, 6:00 am – 10:00 pm – Huestis Hall, Lokey Labs, and Streisinger Hall – Standby Power outage

The standby power source will be offline for the duration of this shutdown. Users are not expected to experience any impacts during this outage but should be aware that the redundant power source is not available.

Copier Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.  For questions, please contact Kati Kronholm at 541-346-5370 or katik@uoregon.edu.  For non-copier questions, please reach out to the contact person listed below.

Work Performed By:  EC, JHK, Siemens, Lewis

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

Image of Huestis, Lokey Labs, Streisinger, Willamette, and Klamath

11/02/23 Knight Library Special Collections HVAC Air Supply Shutdown

Begin:  Thursday, November 2, 2023 – 1st inspection around 11:30 am, 2nd inspection around 2:15

End:      Thursday, November 2, 2023 – approximately 2:30 pm

Building(s) or Area(s) Affected:  Knight Library Special Collections

Scope:  Air handling unit serving Knight Library Special collections will be shut down twice for 15 minutes for an inspection of the humidifier with a manufacturer’s representative.

Services Impacted:  This will impact the Special Collections section.

Work Performed By:  Contractor

ContactKevin Waldrop, CPFM Facilities Engineer, 541-346-2315 or 541-525-4326

Current construction and impacts information can be found on the UO Maps site.

Image of Knight Library

10/27/23 – 11/01/23 Lillis Hall Atrium Elevator Out of Order

UPDATE:
The elevator has been repaired and restored to service.

 

Begin:  Friday, October 27, 2023 – Effective Immediately

End:      Monday, October 30, 2023 – with continuing repairs through Wednesday, November 1, 2023

Building Impacted:  Lillis Hall

Scope:  The Atrium elevator is offline and parts have been ordered.  Repairs are expected to take place on Monday.   An update will be sent when services have been restored.

Services Impacted: The elevator is currently out-of-order.  Please use the other elevators in the building.

Special Instructions:  If you have concerns about accessing your workplace when elevator services are impacted, please contact your supervisor to find an appropriate accommodation.

Work Performed By: Otis

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Lillis Hall elevators

10/31/23 – 11/02/23 Huestis Hall Basement and Lokey Labs Fire Suppression System Shutdown

UPDATE:
The audible fire alarm testing will occur sporadically during this event. This will last for 1-2 hours per floor level 1, 2, 3, and penthouse inside Huestis Hall only.

 

Begin:  Tuesday, October 31, 2023, at 7:00 am

End:      Thursday, November 2, 2023, at 3:00 pm

Building(s) or Area(s) Affected:  Huestis Hall Basement and Lokey Labs

Scope:  As part of the Huestis Hall renovation project, the fire suppression system will be offline each day from 7:00 am to 3:00 pm to allow for final fire line connections to the Huestis Hall basement and Lokey Labs.  Contractors will be working in the Huestis Hall basement mechanical room and main hallway. Contractors will provide fire watch throughout Lokey Labs and the Huestis Hall basement during this shutdown.

Details:  Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions:  If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By:  Harvey & Price

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

Image of Huestis Hall and Lokey Labs

10/30/23 – 11/03/23 Johnson Hall Women’s Restroom #006 Shutdown

UPDATE 11/09/23:
The initial ceiling repair took place yesterday by one of our night crew technicians. The remainder of the work will be done with the night crew and not impact occupants.  We will make sure that the restroom is fully accessible today for use including the sinks that were blocked off.

 

Begin:  Monday, October 30, 2023, at 7:30 am

End:      Friday, November 3, 2023, at end of day

Building(s) or Area(s) Affected:  Johnson Hall Restroom 006

Scope:  Due to water intrusion Restroom 006 will be closed for repairs.

Services Impacted:  Restroom will be shut down.  Construction noise and odor can be expected during this time.

Special Instructions:  Please use the all-gender restroom 006A or the Women’s restroom on the 2nd floor.

Work Performed By:  CPFM Facilities Services

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Women's restroom #6 in Johnson Hall

11/28/23 Huestis Hall Basement Heat Exchangers Shutdown

UPDATE 11/09/23:
The heating water system shutdown has been rescheduled for Tuesday, November 28th.   This was due to the upcoming steam shutdown on November 30th, and needing to do this work in sequence.

 

BeginNovember 9, Tuesday, November 28, 2023, at 6:00 am

End:      November 9, Tuesday, November 28, 2023, at 3:30 pm

Building(s) or Area(s) Affected:  Huestis Hall basement

Scope:  Huestis basement heat exchangers will be offline to allow contractors to tie the new heating loop from HX2 and 3 into the existing heating water loop for HX1.

Services Impacted:  This will require the exhaust fans, AHUs, heat exchanger 1, and heating water pumps 1 & 2 serving the Huestis basement to be shut down.

Work Performed By:  JH Kelly

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

Image of Huestis Hall

10/25/23 Esslinger Hall Rooms 156 and 165 Electrical Outage

Begin:  Wednesday, October 25, 2023, at 8:00 am

End:      Wednesday, October 25, 2023, at 4:00 pm

Building(s) or Area(s) Affected:  Esslinger Hall

Scope:  Electricity will be offline in rooms 156 and 165 while contractors work in these spaces.

Services Impacted:  Circuits to these rooms will be turned off for a short period.

Special Instructions:  Please contact me if other spaces experience power outages.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.  For questions, please contact Kati Kronholm at 541-346-5370 or katik@uoregon.edu.  For non-copier questions, please reach out to the contact person listed below.

Work Performed By:  Sunset Electrics

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Image of Esslinger rooms 156 and 165

10/23/23 – 10/24/23 Lewis Integrative Science Building Main Elevator Shutdown

UPDATE:
The elevator has been restored to service.

 

Begin:  Monday, October 23, 2023 – effective immediately

End:    Tuesday, October 24, 2023

Building Impacted:  Lewis Integrative Science Building

Scope:  The main elevator is currently shut down for repairs and is expected to be operational sometime tomorrow.  A notice will be sent when it has been restored to service.

Services Impacted:  Elevator #1 will be offline during this time.

Special Instructions:  If you have concerns about accessing your workplace when elevator services are impacted, please contact your supervisor to find an appropriate accommodation.

Work Performed By: Otis

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Lewis Integrative Science Building Elevator #1

10/31/23 – 11/14/23 Klamath Hall Air Balancing Testing Advisory

Begin:  Tuesday, October 31, 2023

End:      Tuesday, November 14, 2023

Building(s) or Area(s) Affected:  Klamath Hall – Basement, Ground, 1st, and 2nd Floors

Scope:  Due to the replacement of exhaust fan motors and associated controls, an exhaust air system rebalance is required.

Services Impacted:  An air balancing consultant will need access to all exhaust grilles to measure air volume and adjust dampers, as necessary.

Work Performed By:  Air Inc.

ContactKevin Waldrop, CPFM Facilities Engineer, 541-346-2315 or 541-525-4326

Current construction and impacts information can be found on the UO Maps site.

Image of Klamath Hall

11/01/23 McArthur Court Fire Suppression System Shutdown

Begin:  Wednesday, November 1, 2023, at 6:00 am

End:      Wednesday, November 1, 2023, at 4:00 pm

Building(s) or Area(s) Affected:  McArthur Court

Scope:  Due to the need to add two additional fire sprinkler heads in McArthur Court, the fire suppression system to the north zone of the mezzanine will be shut down. The system will be up and running by the end of the day.

Details:  Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions:  If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By:  GBC Construction/ Harvey & Price / IES

ContactTim Allenbaugh, CPFM Owner’s Representative, 541-346-8214

Current construction and impacts information can be found on the UO Maps site.

Image of McArthur Court

10/23/23 – 10/24/23 13th Avenue Garage Elevator #2 Emergency Shutdown

UPDATE:
The elevator has been restored to service.

 

Begin:  Monday, October 23, 2023 – effective immediately

End:      Tuesday, October 24, 2023 – unknown

Building(s) or Area(s) Affected:  13th Avenue Garage

Scope:  Elevator #2 is currently out of order and will be down overnight.  Repairs are expected to be complete tomorrow.

Services Impacted:  Elevator is offline.  Please use adjacent elevator.

Special Instructions:  If you have concerns about accessing your workplace when elevator services are impacted, please contact your supervisor to find an appropriate accommodation.

Work Performed By:  Otis

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of 13th Ave Garage elevator #2Image of Ford Alumni and Matthew Knight Arena

 

10/20/23 – 10/26/23 Prince Lucien Campbell Elevator Emergency Shutdown

UPDATE:
The part arrived and the elevator has been repaired.

 

Begin:  Friday, October 20, 2023 – effective immediately

End:      Unknown  Thursday, October 26, 2023

Building(s) or Area(s) Affected:  Prince Lucien Campbell

Scope:  The northern most elevator has been shutdown and will remain down at least through the weekend

Services Impacted:  The north elevator is out of service.

Special Instructions:  If you have concerns about accessing your workplace when elevator services are impacted, please contact your supervisor to find an appropriate accommodation.

Work Performed By:  Otis

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

map showing PLC

10/23/23 – 11/01/23 CPFM Administration Quonset Overhang Work Advisory

UPDATE:
Work is almost complete and the main entry to the CPFM Administrative Quonset building is now accessible.
The bike rack will be returned to the west side of the Quonset on Wednesday.

 

Begin:  Monday, October 23, 2023, at 7:00 am

End:      October 27, November 1, 2023, at 3:30 pm

Building(s) or Area(s) Affected:  CPFM Administration Quonset

Scope:  The main entry will be closed for several days during repair work to the west overhang.  The entry at the southwest corner will be programmed to stay open during regularly scheduled work hours.

Services Impacted:

  • The main entrance will be temporarily closed.
  • The bike rack will be relocated to the front of Stores (CPFM Warehouse), on the north side, during this time.

Work Performed By:  CPFM Facilities Services

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of CPFM Admin Quonset and the location for the bike rack for overhang work 10/23 through 10/27

10/25/23 – 10/31/23 Columbia Hall 144, 144A, and 144B Construction Work and Noise Advisory

Begin:  Wednesday, October 25, 2023, at 7:30 am

End:      Tuesday, October 31, 2023, at 4:00 pm

Building(s) or Area(s) Affected:  Columbia Hall

Scope:  Demolition of a wall and abatement of flooring will take place in rooms 144, 144A and 144B. There may be noise associated with the demolition and abatement.

Services Impacted:  The rooms most likely impacted by the noise are: 246, 247, 248, 249, 143, and 142. We are working with the contractor to limit most noise to early morning prior to classes in 143.

Work Performed By:  Asbestos Abatement Contractor, Gilberto Martinez

ContactJanell Cottam, CPFM Owner’s Representative, 541-346-7536

Current construction and impacts information can be found on the UO Maps site

Image of Columbia Hall rooms 144, 144A, 144B

11/01/23 – 11/02/23 Lewis Integrative Science Building Steam Heat Shutdown

UPDATE 11/2/23:
The steam has been restored.  Building temperatures are expected to rise slowly as they return to normal levels.

 

UPDATE 11/2/23:
Due to the complexity of the pipeline repair, the contractors will be working later than anticipated. The steam service will be restored this evening, as soon as possible.

 

Begin:  Wednesday, November 1, 2023, at 1:00 pm

End:      Thursday, November 2, 2023, at 5:00 pm  till complete

Building(s) or Area(s) Affected:  Lewis Integrative Science Building

Scope:  Due to urgent repairs needed to the utility steam piping system, the steam heat will be shut down.

Services Impacted:

  • Expect temperatures to drop in the building.
  • Work will take place in the tunnel.

Work Performed By:  Hydro-Temp Mechanical

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Lewis Integrative Science Building

10/16/23 – 10/17/23 Esslinger Hall Rooms 190, 190A, 190B, 199 Emergency Air Conditioning Shutdown

Begin:  Monday, October 16, 2023 – effective immediately

End:      Tuesday, October 17, 2023 – around 12:00 noon

Building(s) or Area(s) Affected:  Esslinger Hall Rooms 190, 190A, 190B, and 199

Scope:  An emergency shut down of the air conditioning has occurred in the rooms listed.  Repairs are being made and the system is expected to be back online around noon tomorrow.  An update will be sent when services have been restored.

Services Impacted:  Cooling will be offline.

Work Performed By:  CPFM Facilities Services

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Esslinger 190, 190A, 190B, 199

10/16/23 Condon Hall Cardboard Dumpster Removal Notification

Begin:  Monday, October 16, 2023 – effective immediately

Building(s) or Area(s) Affected:  Condon Hall

Scope:  The cardboard recycling dumpster located at the northwest entrance to Condon Hall has been permanently removed.

Services Impacted:  Building occupants in Condon Hall can now recycle their cardboard at Lillis Business Building or Prince Lucien Campbell.

Special Instructions:  Please see the map below detailing where these two cardboard recycling dumpsters are located.

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Map of cardboard locations at PLC and Lillis 10-16-23

10/23/23, 10/26/23, 10/30/23, 11/03/23 Willamette Hall, Huestis Hall, Streisinger Hall, and Lokey Labs Compressed Air Shutdown

UPDATE 10/30/23:
The shutdown today was not successful.  The shutdown of compressed air will be rescheduled for Friday, November 3rd from 9:00 am – 1:00 pm.

  • Lokey Labs will not have compressed air during this shutdown. Please shut down affected equipment.

 

UPDATE 10/23/23:
Today’s test at Willamette Hall and Streisinger Hall was unsuccessful.  CPFM Facilities has ordered additional parts and rescheduled the test for Thursday, October 26th, from 7:00 am to 12:00 noon.

 

1st Test:   Monday, October 23, 2023, at 7:00 am – 12:00 noon

2nd Test:   Thursday, October 26, 2023, at 7:00 am – 12:00 noon

Final Day:  Monday, October 30, 2023, at 7:00 am – 1:00 pm  Friday, November 3, 2023, at 9:00 am – 1:00 pm

Building(s) or Area(s) Affected:  Willamette Hall, Huestis Hall, Streisinger Hall, and Lokey Labs

Scope:  As part of the Huestis Renovation project, the campus supplied compressed air system will be offline as follows:

Monday, October 23, 2023, 7:00 am – 12:00 noon: Outage in Streisinger and Willamette Halls.

  • Streisinger and Willamette Halls – Building supplied compressed air will go offline to allow adequate testing of the emergency backup compressor units. Users will experience limited to no availability of compressed air which is likely to affect air turrets at lab benches and possibly affect building heating and cooling supply. Users should plan to limit their use of the emergency supplied compressed air during this period.
  • Huestis Hall – No impact to compressed air service anticipated during this test period.
  • Lokey Labs – No impact to compressed air service anticipated during this test period.

Monday, October 30, 2023, 7:00 am – 1:00 pm: Outage in Huestis, Lokey Labs, Willamette and Streisinger.

  • At Streisinger and Willamette Halls, following the test results of the emergency backup air supply, users will experience a lower flow of available compressed air via lab turrets. Users should plan to limit use during this period. Heating and cooling supply may be affected during this period.
  • Lokey Labs will be supplied by a temporary air compressor. Users should plan to limit use during this period.
  • Huestis Hall will not have compressed air during the shutdown. Please shut down affected equipment.

Work Performed By:  JH Kelly

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

Image of Willamette Hall, Huestis Hall, Streisinger Hall, and Lokey Labs

 

10/23/23 Student Recreation Center/Esslinger Hall Room 40 Domestic Cold and Hot Water Shutdown

Begin:  Friday, October 20, 2023, at 8:00 am

End:      Friday, October 20, 2023, at 4:00 pm   Monday, October 23, 2023

Building(s) or Area(s) Affected:  Student Recreation Center and Esslinger Hall

Scope:  Renovation work will take place with the existing plumbing that services some fixtures in the building.

Services Impacted:  This will shut down the domestic hot and cold water, affecting only room #40 in the SRC.

Work Performed By:  Bridgeway Contracting and Twin Rivers Plumbing

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Image of SRC room 40

10/25/23 Huestis Hall Basement Exhaust, HVAC, and Steam Shutdown

Begin:  Wednesday, October 25, 2023, at 5:00 am

End:      Wednesday, October 25, 2023, at 4:30 pm

Building(s) or Area(s) Affected:  Huestis Hall basement

Scope:  Remove existing Steam Flow Meter and add spool / Tie New Steam PRV station in to house MPS. Tie Fish housing MPS into new POC before the new PRV station. Open new LPS to the Fish housing Area.

Services Impacted:  This will affect the exhaust, HVAC air supply, and steam condensate.

Work Performed By:  JH Kelly

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

map of Huestis Hall

11/01/23 Huestis Hall Basement Steam Shutdown

UPDATE:
This work has been rescheduled for Wednesday, November 1st as additional coordination was required to complete the piping installation for the new steam supply.

 

BeginOctober 25, Wednesday, November 1, 2023, at 5:00 am

End:      October 25, Wednesday, November 1, 2023, at 4:30 pm

Building(s) or Area(s) Affected:  Huestis Hall basement

Scope:  As part of the Huestis Renovation project, temporary steam source will be refed from the new permanent steam source.  This shutdown will remove the existing steam flow meter and tie into the new PRV station for the permanent steam supply.

Services Impacted:  This steam supply shutdown will take the following equipment offline in Huestis serving the Zebrafish facility and quarantine:

  • Exhaust Fans 1&2
  • AHU 1&2
  • Heat Exchange 1
  • Heating Water pump 1&2

Work Performed By:  JH Kelly

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.