UPDATE 6/15/23:
The week of June 20th electrical work will be occurring in the ceiling of hallway H037, the west hallway of the basement level. During this above head work, the hallway will be closed to regular foot traffic. Access to the southern portions of the basement will be directed through hallway 30 and hallway 57.
UPDATE 6/01/23:
Abatement of ductwork and two older mechanical units in rooms 56 and 50A is scheduled to start on Monday, June 5th and finish on Friday, June 16th. Noise can be expected during this time.
UPDATE 5/02/23:
Abatement has been completed and general demolition work should be finished by next week. We will then begin the construction phase with an expected end date in early September.
This Wednesday morning, May 3rd, Preferred Construction will be saw cutting concrete in the basement. The extra noise associated with this will occur between 7:00 am – 10:00 am.
UPDATE 4/6/23:
General demolition in preparation for construction will start April 17th. Signage will be in the halls directing use of the temporary location for the Testing Center in rooms 41 & 42. Hallway H30 will remain open, though may have temporary closures as work is occurring in the area. Please watch for signage in this area. Construction is expected to continue through the summer with completion in early September. There also will be material removal and delivery occurring through the double doors to the exterior on the basement level northwest corner at times.
CPFMnoticePlan (1)
UPDATE: The completion date for the abatement portion of this project has been extended out to Friday, April 14, 2023. An update will be provided when a timeline for the demolition and construction portion has been finalized.
Begin: Tuesday, March 28, 2023
End: Thursday, April 6, 2023 Friday, April 14, 2023 (abatement), Friday, September 15, 2023 (project completed)
Building(s) or Area(s) Affected: Knight Library
Scope: Abatement and demolition will be underway in the basement as part of the Consolidated Testing Center Renovation. The lower northwest entrance and hall H30 will be blocked temporarily, but not for the entire work period. Hallway H30 and the entrance will be addressed first during the week of Spring Break to minimize ADA disruption.
Services Impacted: Lower northwest entrance hall, H30, and a small corner in hall H57. The following rooms have been vacated and are part of the renovation: 19, 19A, 30, 30A, 32, 33, 34, H31, 31, 31A, 31B, and 58
Special Instructions: If you need an accessible entrance during this time period, please plan to use the accessible entrance on the NE main floor.
Work Performed By: Rose City Contracting
Contact: Janell Cottam, CPFM Owner’s Representative, 541-346-7536