Lawrence and Pacific Connecting Stairway Closure 3/14/22 – 3/25/22

UPDATE:
Work will now begin the week prior to Spring Break on March 14th .  The completion date is still scheduled for March 25th.

 

Begin:  Monday, March 14 21, 2022

End:      Friday, March 25, 2022

Building(s) or Area(s) Impacted:  Lawrence Hall,  H100

Scope:  During the week of Spring Break, plus the week prior, hallway H100 will be closed in order to make repairs caused by a water leak earlier this winter.

Services Impacted: Access to the three step stairway between Lawrence and Pacific, near room 100, will be shut down.

Work Performed By:  CPFM Facilities Services Crew

ContactKevin Wilson, CPFM FS Construction Field Superintendent, 541-968-4024

Updated: Susan Campbell Hall East Stairwell Closure Advisory 2/10/22 – 2/28/22

UPDATE:
The date has been extended to next Monday, February 28th.

 

Begin:  Thursday, February 10th, 2022 – effective immediately

End:      Monday, February 21st, 2022 Monday, February 28th, 2022

Building(s) or Area(s) Impacted:  Susan Campbell Staircase 103

Scope:  Due to a sidewalk replacement, the north facing eastern most staircase exit (Stair 103) will be available for Emergency Exit only. Weather permitting for the work, this will be completed by Friday 2/18 and then re-opened the following Monday 2/21.

Services Impacted:  The staircase is closed except for emergency exiting only.

Special Instructions:  A sign has been placed and an alternate exit map posted on the door.

Work Performed By:  Pacific Excavation

ContactJeff Hanson, CPFM Construction Project Manager, 541-346-7991

Oregon Hall North Lawn Vault Work and Parking Advisory 2/17/22

Begin:  Thursday, February 17th, 2022 at 8:00 am

End:      Thursday, February 17th, 2022 at approximately 2:00 pm

Building(s) or Area(s) Impacted:  North side of Oregon Hall between the building and the underground vault

Scope:  Due to work in the large underground vault in the lawn north of the building, vehicles may be parked on the sidewalk near the vault. The sidewalk will remain open. The work has to do with pump repair. The pumps keep rain water from entering the Oregon Hall basement data center.

Services Impacted:  Short periods of sidewalk parking, near the vault, on the north side of the building.

Work Performed By:  OEG

ContactBruce McCarthy, Information Services Data Center Systems Specialist, 541-346-1019

REVISED: CPFM Warehouse and ZIRC Expansion Staging Advisory 2/23/22 – 3/04/22

DATE REVISED:
This shipment was delayed and is now expected to arrive tomorrow, February 23rd.

 

BeginThursday, February 17th, 2022 Wednesday, February 23rd, 2022

End:      Friday, February 25th, 2022  Friday, March 4th, 2022

Building(s) or Area(s) Impacted:  CPFM Warehouse and Compound

Scope:  A shipment of owner furnished owner installed (OFOI) aquaculture equipment is expected to arrive on 2/17 2/23. Shipment will arrive on a flatbed and be moved into the ZIRC expansion area by Fortis. The move in is expected to take up to 5 days. Components that are vulnerable to cold temps are planned to be staged in the CPFM Warehouse (Bldg. 130).

Services Impacted:  Staging will take place in Bldg. 130 in the breezeway (H109).

Work Performed By:  Colin Brennan and Fortis Construction

ContactColin Brennan, CPFM Owner’s Representative, 541-346-8242 or 541-654-2972

Onyx Bridge/Klamath Loading Dock and Service Vehicle Spots Closure 2/10/22

Begin:  Thursday, February 10th, 2022 at 7:00 am

End:      Thursday, February 10th, 2022 at 12:00 noon

Building(s) or Area(s) Impacted:  Onyx Bridge/Klamath Loading Dock area and Service Vehicle Spots

Scope:  The Loading Dock area and the CPFM Service Spots will be closed to accommodate an EHS vendor (Clean Harbors) so they may access their required work site.

Services Impacted:  Vehicles will not be allowed to park here during this time.

Work Performed By:  EH & S / Clean Harbors

Contact: Steve Stuckmeyer, UO Environmental Health and Safety Director & RSO, 541-346-3197

Esslinger Hall Electrical Shutdown 2/26/22

Begin:  Saturday, February 26th, 2022 at 7:00 am

End:      Saturday, February 26th, 2022 at 1:00 pm

Building(s) or Area(s) Impacted:  Esslinger Hall – First Floor and Possibly Basement Level

Scope:  Contractors will shut down power to Panels C1 and C2 to terminate 8 circuits and re-feed additional circuits for rooms 112 and 116.

Services Impacted:  Power will be offline on the first floor and possibly affect some circuits in the basement level.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.

Work Performed By:  Mortenson Construction/ EC Power

ContactTim Allenbaugh, CPFM Owner’s Representative, 541-346-8214

Frohnmayer Music Trench Work and Noise Advisory 2/15/22

Begin:  Tuesday, February 15th, 2022

End:      Tuesday, February 15th, 2022

 Building(s) or Area(s) Impacted:  Frohnmayer Music and Parking Lot 20

Scope:  To facilitate wall sealing, a trench will be dug beside the east wall of the Frohnmayer Music building, outside rooms 150 and 178.

Services Impacted:

  • Some equipment noise can be expected around the area of rooms 035, 150, and 178.
  • Half-lane restriction on access road to Parking Lot 20 and the Frohnmayer east loading area.

Work Performed By:  CPFM FS Maintenance Support

ContactPiper Fahrney, CPFM Facilities Services Maintenance Support, 541-346-2319

HEDCO South Elevator Intermittently Working 2/9/22 – Unknown

UPDATE 3/8/22:
Repairs have been completed on the South elevator.

 

UPDATE 2/10/22:
The elevator is running again. There is an intermittent issue with the door closing but it automatically resets itself.

 

Begin: Wednesday, February 9, 2022

End:    Unknown

Building Impacted: HEDCO South Elevator

Scope:  The south elevator is working intermittently. The Otis elevator technician is on-site investigating. An update will be sent when repairs are completed.

Services Impacted: The elevator is working intermittently.

Work Performed By: Otis

Contact:  Work Control Center, Campus Planning and Facilities Management, 541-346-2319

Romania Power Outage 3/21/22

Begin:  March 21st , 2022 at 8:00 am

End:     March 21st, 2022 at 3:00 pm

Building(s) or Area(s) Impacted:  Romania

Scope: :  There will be a power shutdown in order to replace the overhead conductors feeding the building

Services Impacted:  The building will be without power during this time.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.

Work Performed By:   EWEB

ContactRob Berg, CPFM Facilities Electrical Supervisor, 541-346-2313

Onyx Bridge East Elevator Shut-down Tuesday Feb. 8 @ 7am – Unknown

UPDATE:  The elevator is repaired and back in service

 

Begin:  Tuesday February 8, 2022 @ 7:00am

End:  Unknown

Building(s) or Area(s) Impacted:  Onyx Bridge East Elevator is currently shut-down

Services Impacted:  Out of service

Extra Notes:  Otis is dispatched.  Use West Elevator.  Second notification will be sent when services restore.

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

 

Lawrence Hall (West Side) Chilled Water Shutdown 2/16/22

Begin:  Wednesday, February 16th, 2022 at 7:00 am

End:      Wednesday, February 16th, 2022 at 4:00 pm

Building(s) or Area(s) Impacted:  Lawrence Hall

Scope:  Due to a utility flow meter replacement, chilled water will be shutdown to the west side of Lawrence Hall.  Work will take place in Mechanical room 015 and in the utility tunnel.

Services Impacted:  This will only affect building cooling, so there will be little impact to occupants.

Work Performed By:  Contractor

ContactKyle Wilson, CPFM Utilities Maintenance Manager, 541-346-2246

Cascade Hall Chilled Water Shutdown 2/14/22

Begin:  Monday, February 14th, 2022 at 7:00 am

End:      Monday, February 14th, 2022 at 4:00 pm

Building(s) or Area(s) Impacted:  Cascade Hall

Scope:  Due to the replacement of a utility flow meter, the chilled water will be shutdown to the building.

Services Impacted:

  • This will only affect building cooling, so there will be little impact to building occupants.
  • There may be noise and odor associated with welding in the area of Mechanical room 005.

Work Performed By:  Contractor

ContactKyle Wilson, CPFM Utilities Maintenance Manager, 541-346-2246

1600 Millrace Fire Systems Test/Maintenance Advisory 2/9/22

Begin:  Wednesday, February 9th, 2022 at 6:30 am

End:      Wednesday, February 9th, 2022 at 7:00 am

Building(s) or Area(s) Impacted:  1600 Millrace

Scope:  A fire systems test/maintenance will be performed.

Details:  Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions:  If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By:  UO Safety & Risk Services

ContactSimon Ditton, UO SRS University Fire Marshal, 541-346-2958

1600 Millrace Building Inspection Advisory 2/15/22

Begin:  Tuesday, February 15th, 2022 at 9:00 am

End:      Tuesday, February 15th, 2022 at 11:00 am

Building(s) or Area(s) Impacted:  1600 Millrace

Scope:  A representative from Capital Servicing, LLC will be on-site for the annual review of the building, and will be taking pictures of the exterior and interior, including departmental office space. The representative will be escorted by a member of Campus Planning.

Services Impacted:  No impact is expected.

Work Performed By:  Capital Servicing, LLC – on behalf of the landlord

ContactMelinda Seeley, CPFM Campus Planning, Real Estate Property Specialist, 541-346-5550

Tunnel Evacuation Alarm Test on Tuesday Feb. 8, 2022

Begin: Tuesday, February 8, 2022 at 10:00 am

End: Tuesday, February 8, 2022 at 10:15 am

Building or Area Impacted: Campus Tunnel System

Scope: Tunnel Evacuation Alarm test – Short Burst

Services Impacted: Should not affect building occupants

Work Performed By: CPFM Utilities & Energy

Contact: Rick Tabor, Interim Co-Director of U& E, 541-346-7511

CPFM Lot 2 Storm Water Basin Service Advisory 2/09/22

Begin:  Wednesday, February 9th, 2022 at 10:00 am

End:      Wednesday, February 9th, 2022 at 12:00 noon

Building(s) or Area(s) Impacted:  Lot 2 (East of the Central Power Station)

Scope:  Storm water basin service will be performed in the area shown in red below. (The blue line shows the traffic route.)

Services Impacted:  The driving route will not be blocked but will be constricted slightly.  If needed, we will be able to open it up further should emergency vehicles need access.

Work Performed By:  CPFM Facilities Crews

ContactRod Madison, CPFM Landscape Coordinator, 541-346-8626

Campus AHU Preventative Maintenance Schedule for February 2022

Begin:  February 1st, 2022

End:     February 28th, 2022

Building(s) or Area(s) Impacted:

  • 1900 Millrace
  • Student Rec Center
  • Cascade Hall
  • Cascade Annex West
  • Cascade Annex East
  • McMorran
  • Esslinger
  • Straub

Scope:  Preventative Maintenance work will be performed, over the course of February, for the buildings listed above.

Services Impacted:  No services are expected to be impacted.

Work Performed By:  CPFM Preventative Maintenance Crew or Contractor

ContactJim Cody, CPFM Associate Dir. of Facilities Services, 541-346-2302

CPFM Warehouse Room 237 Renovation Advisory 2/14/22 – Unknown

UPDATE:
On Wednesday, March 9th, contractor H&P is scheduled to do minor HVAC modifications in conference room #237.
There is also ongoing work by Facilities Services to finish this room.

 

Begin: Monday, February 14th, 2022

End: Unknown

Building(s) or Area(s) Impacted: CPFM Warehouse (Bldg. 130) Room 237

Scope: Starting February 14, work will be performed in Conference Room 237. Initial work will focus on minor modifications to North and East wall furnishings (whiteboard, monitor, and sound panel), as well as electrical outlet and data jack installation. Installation of a door and modification of HVAC will occur at a later date. Additional notifications will be provided.

Services Impacted:

  • Occupants can expect to hear light construction noises such as drilling and cutting.
  • The first phase is expected to be done by 2/22/22.

Work Performed By: CPFM Facilities Services

Contact: Justin Grishkin, CPFM Construction Services Manager, 541-346-5242

Huestis Hall Construction Noise Advisory 2/04/22

Begin:  Friday, February 4th, 2022 at 6:00 am

End:      Friday, February 4th, 2022 at 9:00 am

Building(s) or Area(s) Impacted:  Huestis Hall

Scope:  Contractor will be sawcutting tile and drilling concrete in the level 1, north lobby of Huestis Hall.

Services Impacted:

  • Occupants can expect noise and vibration during this time.
  • Access through the lobby will not be impacted during this work.

Work Performed By:  Mortenson and Stanton

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Huestis Hall Basement Fire Sprinkler System Shutdown 2-21-22

Begin: Monday, February 21, 2022 at 7:30 am

End:   Monday, February 21, 2022 at 5:00 pm

Building(s) or Area(s) Impacted:  Huestis Hall

Scope:   Sprinklers lines will be rerouted in the construction zone.

Services Impacted:   Fire Sprinkler system will be shut down basement wide.

Details:  Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions:  If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By:  Mortenson Construction/ Harvey & Price

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Klamath Hall First Floor Fire Sprinkler System Shutdown 2-22-22

Begin:  Tuesday, February 22, 2022 at 7:00 am

End:    Tuesday, February 22, 2022 at 2:00 pm

Building(s) or Area(s) Impacted:  Klamath

Scope:   Replace and reroute sprinkler heads in room 019.

Services Impacted: . All the 1st floor sprinkler system will be down.

Details:  Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions:  If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By:  Mortenson Construction/ Harvey & Price

ContactTim Allenbaugh, CPFM Owner’s Representative, 541-346-8214

Esslinger Hall First Floor Fire Sprinkler System Shutdown 2-24-22

UPDATE:

The fire sprinkler system testing has been rescheduled for Thursday, February 24.

 

BeginFebruary 25, 2022 at 7:00 am – Thursday, February 24 at 7:00 am

End:     February 25, 2022 at 2:00 pm –  Thursday, February 24 at 2:00 pm

Building(s) or Area(s) Impacted:  Esslinger

Scope:  Re-routing fire Sprinklers in rooms 112 & 116

Services Impacted:  All the 1st floor sprinkler system will be down.

Details:  Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur      after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions:  If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By:  Mortenson Construction/ Harvey & Price

ContactTim Allenbaugh, CPFM Owner’s Representative, 541-346-8214

HEDCO South Elevator Shut-Down Wednesday Feb. 2nd @ 7:00am – Unknown

Update The elevator has been repaired, service is restored

 

Begin: Wednesday, February 2, 2022 @ 7:00am

End:    Unknown

Building Impacted: HEDCO South Elevator

Scope:  The south elevator is nonresponsive. The Otis elevator technician is on-site making repairs. An update will be sent when repairs are completed.

Services Impacted: The elevator is currently shut down.

Extra Notes: An update will be sent when services are restored.

Work Performed By: Otis

Contact:  Work Control Center, Campus Planning and Facilities Management, 541-346-2319

Streisinger Hall Drilling Noise Advisory 2/02/22

Begin:  Wednesday, February 2, 2022 at 1:00 pm

End:      Wednesday, February 2, 2022 at 4:00 pm

Building(s) or Area(s) Impacted:  Streisinger Hall Rooms 275A and B

Scope:  Contractor will be drilling concrete in the 2nd floor renovation area.

Services Impacted:  Nearby occupants can expect noise and construction activity during this time.

Work Performed By:  Mortenson Construction

ContactColin Brennan, CPFM Owner’s Representative, 541-346-8242 or 541-654-2972

Frohnmayer Music Hall Heating System Repair 2-1-2022 – Unknown

UPDATE:  We were informed that this was previously restored.

 

Begin:  Tuesday February 1, 2022

End:      As Soon As Possible

Building(s) or Area(s) Impacted:  Frohnmayer Music Hall

Scope:  Building Heating System Repair in Progress

Services Impacted:  Heating Impact – The building will be cold

Work Performed By:  CPFM Utilities & Energy

ContactJim Cody, CPFM Assoc. Dir of Facilities Services, 541-346-2302