8/05/24 – 8/09/24 Huestis Hall Siemens Remote Monitoring System Integration Advisory

Begin:  Monday, August 5, 2024

End:      Friday, August 9, 2024

Building(s) or Area(s) Affected:  Huestis Hall

Scope:  Siemens to integrate remote monitoring capabilities on industrial hot water heaters 1 and 2 in Huestis Hall.

Services Impacted:

  • No outages or impacts to production of industrial hot water are anticipated.
  • The industrial heating water system will be observed during this work.

Work Performed By:  Siemens

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of Huestis Hall

5/21/24 – 12/31/24 Knight Library Exterior Restoration Project Advisory

UPDATES for 7/11/24 through 8/16/24:

  • Starting July 11th, the scaffolding on the roof of the library will begin to be dismantled and reinstalled on the ground level.  This activity will be ongoing for two weeks.
  • In addition, the week of July 15th the contractor will start to install seismic reinforcing on the brick veneer of the ground level.  This will create noise from drilling through the veneer to the concrete structure behind.  This activity will be on going for 3-4 weeks.

UPDATE for 7/02/24 through 7/23/24:

  • Starting tomorrow 7/2, window contractor will be reinstalling window sashes that have been restored on the roof areas.  This activity will be on going for the next 2-3 weeks.

UPDATE for 6/20/24 through 10/15/24:
The area between Knight Library and the Cemetery will be closed to all pedestrian access from June 20 until October 15, 2024, for construction crane and roofing – see attached plan

Phase B Crane Location

UPDATE for 6/05/24 through 6/19/24:
For the next two weeks, masonry grinding and tuck pointing will continue.  Painters will be working on painting exterior window frames.

UPDATE 5/23/24:
There will be grinding on the exterior brick, causing noise, for the next five weeks.

UPDATE 5/21/24: (A separate notice was sent for this activity on 5/21)
Pressure washing is taking place on the exterior of Knight Library through Wednesday 5/29.

 

Begin:  Tuesday, May 21, 2024, at 7:30 am

End:      Tuesday, December 31, 2024, at 5:00 pm

Building(s) or Area(s) Affected:  Knight Library and surrounding area

Scope:  Exterior restoration on the brick, windows, and roof will be taking place at Knight Library.  Work is currently scheduled to be completed in December.

Services Impacted:  Related noise is to be expected during this time.

Work Performed By:  Preferred Construction

ContactBruce Budzik, CPFM Small Projects & Cap Imp Manager, 541-346-8834

Current construction and impacts information can be found on the UO Maps site.

Overhead map Image of Knight Library

 

 

5/17/24 Thompson’s University Center Building Inspection Advisory

Begin:  Friday, May 17, 2024, at 10:00 am

End:      Friday, May 17, 2024, at 12:00 noon

Building(s) or Area(s) Affected:  Thompson’s University Center

Scope:  A building inspection will take place on Friday.  The inspector will need to access all areas of the building and take photos.

Services Impacted:  Melinda Seeley from Campus Planning will accompany the inspector during this time.

Work Performed By: Contractor and CPFM Campus Planning

Contact:  Melinda Seeley, CPFM Campus Planning Real Estate Prop Specialist, 541-346-5550

Current construction and impacts information can be found on the UO Maps site.

Image of Thompson University Center

5/14/24 – 5/15/24 Knight Library, Student Rec Center, McArthur Court, Straub Hall, Frohnmayer Music Pressure Washing Noise Advisory

Begin:  Tuesday, May 14, 2024, at 10:00 am

End:      Wednesday, May 15, 2024, at 5:00 pm

Building(s) or Area(s) Affected:  Knight Library, Student Rec Center, McArthur Court, Straub Hall, Frohnmayer Music

Scope:  Pressure washing will be taking place to remove flyers that have been glued to the walls of the buildings listed.

Services Impacted:  Pressure washing noise can be expected from this activity.

Work Performed By:  CPFM Facilities Services

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of buildings affected by pressure washing 5/14/24 - 5/15/24

5/13/24 Parking Lots 10 and 12A Safety Exclusion Zone Closure Advisory

UPDATE:
This work has been completed as of 10:30 am.  The contractor has left, and all areas have been returned to normal service status per EHS and Transportation Services.

 

Begin:  Monday, May 13, 2024, at 7:00 am

End:      Monday, May 13, 2024, at 3:00 pm

Building(s) or Area(s) Affected: Parking Lot 10, West portion of Parking Lot 12A, Adjacent sidewalks, East entrance to Lawrence Hall, North Entrances to Onyx Bridge and Cascade Annex East and West.

Scope: Clean Harbors, a contractor for Environmental Health and Safety, will be stabilizing a highly reactive material in preparation for disposal. The contractors’ work will occur within a 50-foot radius area in the west portion of Parking Lot 12A. The immediately adjacent area will be controlled as a safety exclusion zone by 7:00 am and is scheduled to be re-opened by 3:00 pm (see scale diagram below). Environmental Health and Safety staff will be on site for the activity, with UOPD staff available on-call. UO staff will control access along the sidewalk between Pacific and Cascade Halls while material is moved to the work site, ~8:00-9:00 am; this includes adjacent building and exterior pathway access points. Emergency egress from adjacent buildings will remain available, as will fire lane access for emergency response vehicles, but entry into the safety exclusion zone by non-emergency vehicles or pedestrians will be prohibited. Temporary vehicle barriers will be positioned across the affected area of Lot 12A and the connecting fire lanes. Temporary pedestrian barriers will be positioned across affected areas adjacent to the safety exclusion zones during the material movement phase.

Services Impacted:

  • Vehicle parking Lot 10 and a portion of Lot 12A will be unavailable, including several ADA spaces. Please contact transportation@uoregon.edu for temporary ADA accommodations.
  • All non-emergency vehicle traffic will be excluded.
  • Traffic signage will be posted on site.
  • Vendor deliveries will be re-directed to the Klamath and Streisinger loading docks.
  • Pedestrian traffic will be directed around the safety exclusion zone. The Stabilization Activity Exclusion Zone will be closed and staffed until Clean Harbors leaves the site. The Transport Activity Exclusion Zone will be closed and staffed ~8:00-9:00 am.
  • North entrance access to Cascade Annex East and West will be escorted.

Special Instructions: Refer to the attached diagram for details visualized.

Work Performed By: Environmental Health and Safety, and waste disposal contractor Clean Harbors.

Contact: Ben Bythell, Chemical Safety Officer/Hazardous Materials Manager, 541-346-0371

Current construction and impacts information can be found on the UO Maps site.

Image of map for Lot 10 and 12A related to the EHS Material Stabilization Operation - May 13 2024

5/03/24 Encampment Activity Update

Facilities Update:

As the encampment begun earlier this week continues, we wanted to update you, as our facilities managers, of what to expect and how to access assistance when needed.

The University of Oregon goes to great lengths to support a safe working and educational environment for its students, faculty, and staff. The University has policies, and best practices for events to create and sustain a safe environment for the campus community.  We are meeting with the students involved in the encampment and have shared the policies and expectations. They have also been notified of the policies that have been violated.

Please note the following relevant information:

  • Safety & Risk Services (SRS) staff will be checking buildings through the weekend for graffiti or other damage. Next week, during normal business hours, please keep an eye out for vandalism, graffiti, or other things that seem out of place and report that as soon as possible to UOPD: 541-346-2919.
  • Building schedules may be changed for campus safety and security. Some are closing early and/or limiting access. If you choose to do so, notify uoem@uoregon.edu of your plans.
  • Should there be a large change to campus operations, class schedules, or other unforeseen event, we will notify the university community via the emergency notification system and through UO Alerts. This information may come as a text message in a true emergency, or email for general notification.

In an emergency, call 9-1-1. To report a criminal concern, contact UO Police Department at 541-346-2919.

Map of Main Campus

5/2/24 CPFM Administration Building (#136) and Facilities Services Miscellaneous Quonset Building #(131) Walk Through

Begin:  Thursday, May 2, 2024, at 2:00 pm

End:      Thursday, May 2, 2024, at 5:00 pm

Building(s) or Area(s) Affected:  Facilities Services Miscellaneous Quonset (#131) and CPFM Administration Quonset (#136)

Scope: The architecture firm will be walking through the buildings for programming and schematic design for the seismic upgrade.

Services Impacted:  No impact is expected.

Work Performed By:  Woofter and Bolch Architects

ContactRenee Benoit, CPFM Owner’s Representative, 541-346-5080

Current construction and impacts information can be found on the UO Maps site.

4/05/24 – 4/12/24 CPFM Compound Truck Traffic Advisory

Begin:  Friday, April 5, 2024

End:      Friday, April 12, 2024

Building(s) or Area(s) Affected:  CPFM Compound & yard west of CPS

Scope:  Hoffman Construction will be staging steel slide-rail components west of CPS and the thermal tank – See map below

Services Impacted:  There will be periodic Hoffman truck & equipment traffic to and from the staging area.

Work Performed By:  Hoffman Construction

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

Current construction and impacts information can be found on the UO Maps site.

Image of traffic route for CPFM Compound 4/5/24 - 4/12/24

3/25/24 – 3/29/24 Klamath Hall Air Velocity and Volume Measurements Advisory

Begin:  Monday, March 25, 2024

End:      Friday, March 29, 2024

Building(s) or Area(s) Affected:  Klamath Hall Basement, 1st, and 2nd floors

Scope:  The air balancing contractor will make final adjustments to the lab exhaust air systems. Work will include taking air velocity and volume measurements in ductwork, exhaust grilles, and fume hoods. Room air pressures will also be measured relative to adjacent spaces and/or the corridor.

Services Impacted: The lab exhaust fans will remain active during these activities; the only disruptions will be the contractor taking measurements in rooms.

Work Performed By:  Contractor

ContactKevin Waldrop, CPFM Facilities Engineer, 541-346-2315 or 541-525-4326

Current construction and impacts information can be found on the UO Maps site.

Overhead picture of Klamath

3/18/24 Streisinger Hall 4th Floor Window Replacement Advisory

Begin:  Monday, March 18, 2024, at 8:00 am

End:      Monday, March 18, 2024, at 10:00 am

Building(s) or Area(s) Affected:  Streisinger 4th Floor Hallway

Scope:  Culver Glass will remove and replace a broken window in the 4th floor hallway.

Services Impacted:  Expect congestion in the hallway and noise in surrounding areas.

Work Performed By:  Culver Glass Company

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Overhead map of Streisinger Hall

3/13/24 – 4/05/24 Huestis Hall Exterior Work and Move-In Advisory

Begin:  Wednesday, March 13, 2024

End:      Friday, April 5, 2024

Building(s) or Area(s) Affected:  Huestis Hall and surrounding area

Scope:  The Huestis Hall Deferred Maintenance Project is nearing final completion and the following is a list of upcoming work and impacts around the building:

  • March 13 – Mulching around the south and east
  • March 21 – Construction fencing will be removed on the south and east sides of Huestis Hall.
  • March 22 – April 5 – Construction fencing will remain in place around the Streisinger courtyard to allow for the following site activities:
    • The Coast Redwood tree removal. The growth habit of this tree species in the location poses a risk to infrastructure, property, and life.
    • Replanting, mulching, and landscape repairs in the courtyard and west walkway between Huestis and Willamette Halls.
  • March 25 – Construction trailer will be removed from the site on E. 13th Ave.
  • April 1 – 30 – Occupant move in activities
  • May TBD – Exterior art work installation on the exterior brick of the south stair tower

I appreciate the patience and collaboration from all of our campus partners over the last 2 years! Thank you!!

Services Impacted:  This will affect parking, roadways, and sidewalks in the area.  Noise can also be expected from the activities listed above.

Work Performed By:  Lease Crutcher Lewis and Rexius

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

Image of Huestis Hall and surrounding area

3/07/24 CPFM Warehouse Engineer Inspection

Begin:  Thursday, March 7, 2024, at 10:15 am

End:      Thursday, March 7, 2024, at 12:15 pm

Building(s) or Area(s) Affected:  CPFM Warehouse/Stores (Building 130)

Scope:  MAE Engineers will be walking through the building doing a visual inspection.

Services Impacted:  This will affect the entire building.

Work Performed By:  MAE Engineers

ContactRenee Benoit, CPFM Owner’s Representative, 541-346-5080

Current construction and impacts information can be found on the UO Maps site.

Image of CPFM Warehouse/Stores

2/22/24 – 2/26/24 Tykeson Hall Room 151 Glass Wall Offline

UPDATE:
The glass wall has been repaired and can be used again.  Please remember to contact Work Control Center two weeks in advance (or 72 hours at the very minimum) to schedule the opening and closing of this wall.

 

Begin:  Thursday, February 22, 2024 – effective immediately

End:      Unknown   Monday, February 26, 2024

Building(s) or Area(s) Affected:  Tykeson Hall Room 151 (James Common Room)

Scope:  The glass wall partition is currently inoperable and awaiting repairs.  An update will be sent when work is complete.

Services Impacted:  The glass wall will not be able to close off the room until it has been repaired.

Work Performed By:  CPFM Facilities

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Tykeson Hall's James Common Room 151

2/28/24 – 4/12/24 Thompson University Center Cellular Equipment Upgrade Advisory

Begin:  Wednesday, February 28, 2024, at 11:00 am

End:      Friday, April 12, 2024, at 5:00 pm

Building(s) or Area(s) Affected:  Thompson’s University Center

Scope:  A contractor will be upgrading equipment for Verizon, including all antennas on the roof and equipment in the attic.

Services Impacted:  Work will take place in Mechanical Room #309, in stairwell S301 access hatch, and on the roof.

Work Performed By:  North Ridge Wireless on behalf of Verizon

ContactMelinda Seeley, CPFM Campus Planning Real Estate Prop Specialist, 541-346-5550

Current construction and impacts information can be found on the UO Maps site.

Image of Thompson University Center

2/15/24 CPFM Warehouse and Shops Building #130 Seismic Upgrade Investigation

Begin:  Thursday, February 15, 2024, at 1:00 pm

End:      Thursday, February 15, 2024, at 2:30 pm

Building(s) or Area(s) Affected:  CPFM Warehouse and Shops Building #130

Scope:  Seismic upgrade project is in the schematic design phase and the design team will be doing some investigation on the building.

Services Impacted:  No services impacted. There might be some need to access occupied spaces.

Work Performed By:  Woofter and Bolch Architects

ContactRenee Benoit, CPFM Owner’s Representative, 541-346-5080

Current construction and impacts information can be found on the UO Maps site.

CPFM Warehouse on map

2/13/24 – 1600 Millrace Annual Site Inspection

Begin:  Tuesday, February 13, 2024, at 800 am

End:      Tuesday, February 13, 2024, at 11:00 am

Building(s) or Area(s) Affected:  1600 Millrace

Scope:  The annual site inspection will take place by a representative from Q10 Capital Servicing.  They will be walking around the exterior and interior spaces taking photos.

Services Impacted:  The contractor will be accompanied by someone from CPFM and may enter interior spaces to take a quick picture and step back out.

Work Performed By:  Q10 Capital Servicing

ContactMelinda Seeley, CPFM Campus Planning Real Estate Prop Specialist, 541-346-5550

Current construction and impacts information can be found on the UO Maps site.

Image of 1600 Millrace

2/07/24 Hamilton Hall Complex Inspection Advisory

Begin:  Wednesday, February 7, 2024, at 7:00 am

End:      Friday, February 9, 2024, at 4:00 pm

Building(s) or Area(s) Affected:  Hamilton Hall Complex

Scope:  As part of a upcoming construction project, contractors will be intermittently walking through the building for investigative and planning purposes.

Services Impacted:  This will take place in electrical rooms and unoccupied spaces between, so disturbances should be very minor.

Work Performed By:  EC Electric

ContactDamon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285

Current construction and impacts information can be found on the UO Maps site.

Image of Hamilton Hall Complex

1/22/24 Huestis Hall, Lokey Labs, Streisinger Hall, Willamette Hall Compressed Air and BAS Alarm Testing Advisory

Begin:  Monday, January 22, 2024, at 8:00 am

End:      Monday, January 22, 2024, at 10:00 am

Building(s) or Area(s) Affected:  Huestis Hall, Lokey Labs, Streisinger Hall, Willamette Hall

Scope:  A contractor will be performing a short verification test of the newly installed compressed air valves and BAS alarms, as part of commissioning and final UO acceptance.

Services Impacted:  It is expected to have no effect on your normal operations.

Work Performed By:  Siemens, JH Kelly

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

Image of Willamette Hall, Streisinger Hall, Huestis Hall and Lokey Labs

 

1/02/24 Cascade Hall Suite 305 Window Blind Replacement Advisory

Begin:  Tuesday, January 2, 2024, at 1:00 pm

End:      Tuesday, January 2, 2024, at 4:00 pm

Building(s) or Area(s) Affected:  Cascade Hall suite 305

Scope:  Window blinds will be replaced in rooms 305A and 305D.  Work has already been coordinated with the occupants.

Services Impacted:  Contractors will be working in 305A and 305D.

Work Performed By:  VSC Window Coverings

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Image of Cascade Hall rooms 305A and 305D

12/25/23 – 1/01/24 Campus Winter Quiet Period Advisory

UO’s winter quiet period, between December 25 and January 1 holidays, is almost here! Many on-campus services will be reduced. Please take a moment to review previous news briefs about planning for building closures, winter break locking schedule, and taking extra safety and security precautions.  If an area you work in or are responsible for is planned to be unoccupied, please also review these “before you leave” reminders below for methods to ensure areas that will be unattended are left in a safe, secure, and environmentally sustainable manner.

  • Make sure windows and doors are closed and locked.  Close window coverings if applicable.
  • Turn down heating thermostats to “away mode” if locally controlled.
  • Turn off lights.
  • Turn off computers.
  • Unplug electrical appliances including but not limited to coffee pots, space heaters, holiday lights.
  • Eliminate pest attractants by disposing of all food and garbage.
  • In laboratories, ensure that fume hood sashes are fully closed and that plumbing fixtures (gas and water) have valves closed.

Thank you.

University of Oregon
Safety and Risk Services  |  1260 University of Oregon
1715 Franklin Blvd. Suite 2A, Eugene OR 97403-1260
safety.uoregon.edu

1/09/24 – 1/10/24 Millrace Canal Inspection and Water Level Advisory

UPDATE:
This City of Eugene just informed us that they have cancelled this work, and it will not be rescheduled.

 

BeginTuesday, January 9, 2024, at 7:00 am

End:      Wednesday, January 10, 2024, at 3:00 pm  CANCELLED

Building(s) or Area(s) Affected:  Millrace Canal

Scope:  Millrace pumps will be turned off for the City of Eugene to inspect and survey the storm sewer system under Mill Street.

Services Impacted:  The water level in the Millrace will be lower than normal.

Work Performed By:  City of Eugene

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Millrace Canal

12/12/23 – 1/07/24 Campus Academic Buildings Unlock/Access Advisory for Winter 2023

Begin:  December 12, 2023

End:       January 7, 2024

Building(s) or Area(s) Impacted:  Academic Buildings

Services Impacted:  Buildings that CPFM Custodial Services is responsible for manually locking and unlocking will remain locked for the remainder of the year. Crews will resume unlocking exterior manual doors starting January 8, 2024.  For questions regarding Academic manual building unlocks, contact Campus Planning and Facilities Management Work Control Center, 541-346-2319

This will not impact proxy access to buildings.

For questions regarding AMAG schedules, please contact FASS at 541-346-2455.

Current construction and impacts information can be found on the UO Maps site.

Image of Eugene Campus

12/14/23 – 12/15/23 Tykeson Hall Art Sculpture Repair and Access Advisory

Begin:  Thursday, December 14, 2023

End:      Friday, December 15, 2023

Building(s) or Area(s) Affected:  Tykeson Hall

Scope:  Repairs will be made to the Percent for Art sculpture in open stair 001 at the north end of Tykeson Hall.  Contractors will be actively working on all levels but predominately on the basement level.

Services Impacted:  Stairs may be temporarily blocked and inaccessible as repairs are made on floors 1-4.

Special Instructions:  Occupants are encouraged to use the south stair 002 or the elevator.

Work Performed By:  Fortis Construction

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

Image of Tykeson Hall

12/18/23 – 01/02/24 Erb Memorial Union ID Services Office Holiday Closure

The EMU and the ID Services Office will be closed from December 18th – January 1st and reopening January 2nd. Vanessa Abbott, Access Control Program Specialist, will also be out during this time.

Key orders/dispersals/returns will not be processed during this time. You may still submit the requests but note that keys won’t be available for pick up until after January 2nd.

Prox access and Locknetic code requests will be processed by Angee from the Lock & Key Shop. You can contact her through the access request forms here: https://emu.uoregon.edu/key-and-access-office or at keyaccess@uoregon.edu.

Please plan accordingly as some requests might need to wait until the office reopens.

Feel free to forward this email to other relevant parties.

Thank you for your patience and understanding.

Vanessa Abbott
Access Control Program Specialist
University of Oregon Campus Planning & Facilities Management
ID Card Services Office, Ground Level, Room 002
Erb Memorial Union
(541) 346-5446

Image of the EMU

12/20/23 New Walton (B&C) and Hayward Field Standby Electrical Power Shutdown

Begin:  Wednesday, December 20, 2023, at 7:30 am

End:      Wednesday, December 20, 2023, at 12:00 noon

Building(s) or Area(s) Affected:  New Walton (B&C) and Hayward Field.

Scope:  To upgrade the electrical service to the new Walton, all standby power (only) will be down to the new residence hall buildings B&C and Hayward Field.

Services Impacted:  Regular power will not be affected during this shutdown.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.  For questions, please contact Kati Kronholm at 541-346-5370 or katik@uoregon.edu.  For non-copier questions, please reach out to the contact person listed below.

Work Performed By:  OEG

ContactDavid Mason, CPFM Owner’s Representative, 541-346-5679

Current construction and impacts information can be found on the UO Maps site.

Image of New Walton Building B and C and Hayward Field