12/30/22 Lawrence Hall Communications Wire Running Advisory

Begin:  Friday, December 30th, 2022 at 7:30 am

End:      Friday, December 30th, 2022 at 12:00 pm

Building(s) or Area(s) Affected:  Lawrence Hall Rooms 106, 107, 107C, and 205

Scope:  The internal communications team will be running wiring above the ceiling in these spaces

Services Impacted:  No interruption in services will occur however, workers will be working on ladders and removing ceiling panels in these areas

Work Performed By:  UO Information Services

ContactDamon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285

Current construction and impacts information can be found on the UO Maps site.

12/28/22 – 12/30/22 Oregon Hall Rooms 124-133 Furniture Install Advisory

Begin:  Wednesday, December 28th, 2022 at 8:30 am

End:      Friday, December 30th, 2022 at 4:00 pm

Building(s) or Area(s) Affected:  Oregon Hall Rooms 124-133

Scope:  There will be a 3-day furniture install in the CMAE suite.

Services Impacted:  There may be some noise associated with this work and access will be slightly affected.

Work Performed By:  Office World

ContactBrianna Liberty, CPFM D&C Design Associate, 541-346-7612 or 541-556-9618

Current construction and impacts information can be found on the UO Maps site.

12/27/22 – 12/30/22 Knight Library #57, 19, H57 Renovation Advisory

Begin:  Tuesday, December 27th, 2022

End:      Friday, December 30th, 2022

Building(s) or Area(s) Affected:  Knight Library Rooms 19, 57, and Hallway H57

Scope:  Abatement, demolition, and renewal will occur for rooms 19, 57, and hallway H57, while they receive new lighting, flooring, paint, and electrical.

Services Impacted:

  • ADA access will be impacted from the NW lower entrance to the elevator.
  • Construction noise and odor can be expected during this time.

Work Performed By:  PMG Demolition and CPFM Facilities Services

ContactJanell Cottam, CPFM Owner’s Representative, 541-346-7536

Current construction and impacts information can be found on the UO Maps site.

12/27/22 Knight Library Fire Alarm Activation Advisory

Begin:  Tuesday, December 27th, 2022

End:      Tuesday, December 27th, 2022

Building(s) or Area(s) Affected:  Knight Library

Scope:  Due to a water intrusion from the roof, the fire alarm was activated.  Crews are currently working to make repairs.

Services Impacted:  The fire alarm was heard earlier in the day.

Work Performed By:  UO Safety & Risk Services

ContactZach Earl, UO Fire Systems Program Manager, 541-521-0351

Current construction and impacts information can be found on the UO Maps site.

12/27/22 – 1/20/23 PLC Room 23 Demolition and Construction Advisory

Begin:  Tuesday, December 27th, 2022

End:      Friday, January 20th, 2023

Building(s) or Area(s) Affected:  Prince Lucien Campbell Hall Room 23

Scope:  Demolition and construction activities will occur during the renovation of the space

Services Impacted:  While no services will be impacted, adjacent areas should expect some noise and odors associated with these activities

Work Performed By:  PMG Demolition followed by Bridgeway Construction

ContactJanell Cottam, CPFM Owner’s Representative, 541-346-7536

Current construction and impacts information can be found on the UO Maps site.

12/22/23 – 12/23/23 Winter Grease Trap Cleaning Schedule

Begin:  Thursday, December 22nd, 2022 at 9:00 am

End:      Friday, December 23rd, 2022 at 4:00 pm

Scope:  Housing and Dining will have a contractor clean the grease traps in select areas – see schedule below

Buildings and Schedule:

Thursday, December 22nd

  • 9:00 am –         Barnhart – 1500 gallons
  • 10:00 am –       Carson Hall – 1500 gallons
  • 11:00 am  –       Central Kitchen – 3000 gallons
  • 1:00 pm –          Global Scholars – 2500 gallons
  • 3:00 pm –         EMU – 3000 gallons

Friday, December 23rd

  • 9:00 am –        Ford Alumni
  • 10:00 am –      Hamilton
  • 11:00 am –       Knight Library
  • 12:00 pm –       Tykeson Hall
  • 1:00 pm –         Hydro jet upstream and downstream via cleanout
  • 1:30 pm –         Barnhart – jet 2” kitchen line
  • 2:00 pm –         Hamilton – jet via manhole
  • 2:30 pm –         Carson – jet inlet and outlet
  • 3:00 pm –         Carson – jet via manhole

Services Impacted:  Noise can be expected in the area, along with the possibility of encountering unpleasant odors outside the building with potential drift inside via entryways.

Work Performed By:  Roto Rooter

ContactFarrah Meade, University Housing, HCS & Work Control Manager, 541-346-4082

Current construction and impacts information can be found on the UO Maps site.

12/20/22 – 12/21/22 Onyx Bridge East Elevator Not Going to Upper Floors

Begin:  Tuesday, December 20th, 2022 – effective immediately

End:      Wednesday, December 21st, 2022 – unknown

Building(s) or Area(s) Affected:  Onyx Bridge

Scope:  The east elevator will not take passengers up to the upper floors but will still bring them down when called.  It will go to the ground and basement without any problems.  Otis has looked at it and we are waiting for service to be restored tomorrow, 12/21/22.

Services Impacted:  The east elevator is limited.

Special Instructions:  Please use the other nearby elevators or stairs.

Work Performed By:  Otis Elevator

For questions or concerns, please contact Work Control Center at 541-346-2319 or workcontrolcenter@uoregon.edu.

12/20/22 – 12/21/22 1715 Franklin Gutter Work and Noise Advisory

Begin:  Tuesday, December 20th, 2022, at 7:00 am

End:      Wednesday, December 21st, 2022, at 5:00 pm

Building(s) or Area(s) Affected:  1715 Franklin

Scope:  The landlord will be having McKenzie Roofing and Gutter on-site to clean gutters, replace a section of gutters, and to install gutter guards. The contractor will be using a lift on the west side near the motel to access the roof.

Services Impacted:  There may be noise outside of the building and on the roof as work is being completed.

Work Performed By:  McKenzie Roofing and Gutter

ContactMelinda Seeley, CPFM Campus Planning, Real Estate Property Specialist, 541-346-5550

Current construction and impacts information can be found on the UO Maps site.

12/20/22 Campus Planned Power Testing Unexpected Service Interruption

During island mode testing, we operated a seamless transition from the EWEB power grid to Island Mode.  However, at 11:09 am, while transitioning from Island Mode back to the main grid, we experienced an unexpected momentary glitch in the system.  We are now back on stable power and will have no further testing today.  We will continue to troubleshoot the system at a future date.

We apologize for the inconvenience this has caused.  Please verify that your equipment is back up and operating as expected.

Should you need to report any issues, contact Work Control Center at 541-346-2319 or workcontrolcenter@uoregon.edu.

Current construction and impacts information can be found on the UO Maps site.

12/20/22 Campus Planned Power Testing

Begin:  Tuesday, December 20th, 2022, at 7:00 am

End:      Tuesday, December 20th, 2022, at 3:30 pm

Building(s) or Area(s) Affected:  Campus Wide

Scope:  Utilities and Energy (U&E) will start testing Island mode quarterly instead of annually. This emergency power system requires extensive service more often and complies with our service agreement with the turbine manufacturer. These tests will be during Spring break, Summer break, the annual September power testing, and Winter break. The next test will be December 20th, 2022. Most likely we will enter island mode throughout the day for testing with no exact timeframe.

Services Impacted:  This is a seamless power transition and we do not expect any impacts to campus power.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.

Work Performed By:  Utilities & Energy and Contractor

ContactRick Tabor, CPFM Interim Co-Dir Utilities & Energy, 541-346-7511

To view current construction and impacts, visit UO Map.

12/19/22 Frohnmayer Music Beall Hall Fire Alarm System Shutdown Advisory

Begin:  Monday, December 19th, 2022 at 7:00 am

End:      Monday, December 19th, 2022 at 2:00 pm

Building(s) or Area(s) Affected:  Frohnmayer Music Beall Hall

Scope:  The Beall Hall fire suppression system will be shut down temporarily to add additional sprinkler heads.

Details:  Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions:  If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By:  Harvey & Price and IES

ContactDavid Mason, CPFM Owner’s Representative, 541-346-5679 or 541-852-5659

Current construction and impacts information can be found on the UO Maps site.

12/19/21 – 12/21/22 Gallery Way Utility Locating Activity and Access Advisory

Begin:  Monday, December 19th, 2022

End:      Wednesday, December 21st, 2022

Building(s) or Area(s) Affected:  Gallery Way by Fine Arts Buildings

Scope:  Contractor will be doing site investigations to locate underground tunnel and utilities.

  • Monday 12/19 – Sawcut Asphalt
  • Tuesday 12/20 – Vacuum Excavate to uncover utilities
  • Wednesday 12/21 Backfill and Cover

Services Impacted:  Only bicycle and pedestrian traffic will be allowed in this area.  Noise can also be expected with this activity.

Work Performed By:  Hoffman Construction

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

Current construction and impacts information can be found on the UO Maps site.

December 2022_Gallery Way_Utility Locate Map (1)

12/19/22 Huestis Hall Basement Fire System Shutdown

Begin:  Monday, December 19th, 2022, at 6:00 am

End:      Monday, December 19th, 2022, at 10:00 am

Building(s) or Area(s) Affected:  Huestis H001 basement lobby and hallway around the elevator

Scope:  The fire suppression system will be shut down to remove heads out of the demo zone.

Details:  Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions:  If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By:  Harvey & Price

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

12/19/22 Feeder 1 Electrical Shutdown

Begin:  Monday, December 19th, 2022, at 7:00 am

End:    Monday, December 19th, 2022, at 8:00 am

Buildings:  Unthank Hall, Bean Hall, Global Scholars, Kalapuya Ilihi, Ford Alumni, Matt Knight Arena.

Scope:  Feeder 1 will be shut down to connect the HWTP Phase 2 Project to campus power.

Services Impacted:

  • This will affect main power and elevators, however these buildings will be on standby power during this time.
  • This will not impact Hayward Field.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.

Work Performed By:  Oregon Electric Group and CPFM U&E

ContactGeorge Bleekman, CPFM Owner’s Representative, 541-346-2625

Current construction and impacts can be found on the UO Maps site.

12/16/22 Johnson Hall North Stairs Pressure Washing Advisory

UPDATE:
This work has been rescheduled for Friday, 12/16, at the same time.

 

BeginThursday, December 15th, 2022, Friday, December 16th, 2022, at 12:00 noon

End:      Thursday, December 15th, 2022, Friday, December 16th, 2022, at 3:30 pm

Building(s) or Area(s) Affected:  Johnson Hall

Scope:  CPFM Facilities will be pressure washing the north stairs.

Services Impacted:  Access to the north stairs will be limited.

Special Instructions:  Please use the south entrance.

Work Performed By:  CPFM Facilities Crews

ContactGabe Hein, CPFM Facilities Services, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

12/14/22 – 12/16/22 Streisinger Hall Heating System Shutdown

UPDATE 12/15/22: 
Crews are continuing to work on the lines.  They expect to have the heating water restored to the building by noon on Friday, 12/16/22.  An update will be sent when the water has been restored.

 

UPDATE 12/9/22:
The start date for this shutdown has been moved to 12/14/22 and will finish 12/15/22.

 

BeginMonday, December 12th, 2022 at 7:00 am Wednesday, December 14th, 2022 at 7:00 am

End:      Tuesday, December 13th, 2022 at 3:00 pm, Thursday, December 15th, 2022 at 3:00 pm, Friday, December 16th, 2022 at 12:00 noon

Building(s) or Area(s) Affected:  Streisinger Hall

Scope:  The heating system for the 3rd floor of Streisinger Hall will be shutdown for the installation of valve replacements

Services Impacted:  This will shut down the heating service to the 3rd floor and may affect the heating throughout the building.  The heat will be restored end of day on Wednesday, December 14th at 3:00 pm to mitigate the impact overnight if the work is not finished that day, then shutdown again Thursday, December 15th at 7:00 am if needed.

Work Performed By:  CPFM FS Plumbing Crew

ContactJim Cody, CPFM Associate Dir. of Facilities Services, 541-346-2302

To view current construction and impacts, visit UO Map.

12/14/22 Fenton and Ford Alumni Elevator Shutdown

Begin:  Wednesday, December 14, 2022, at 8:00 am

End:   Wednesday, December 14, 2022 at 5:00 pm

Building(s): Fenton Hall (first) and Ford Alumni (second)

Scope:  The elevators will be shut down to finish year end code requirements.

Services Impacted:  The elevators will be out of service.

Work Performed By:  Otis Elevator

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

To view current construction and impacts, please see the UO Map.

 

12/13/22 – 12/15/22 Student Rec Center Steam and Hot Water Shutdown

Begin:  Tuesday, December 13th, 2022, at 10:00 pm

End:      Thursday, December 15th, 2022, at 4:00 pm

Building(s) or Area(s) Affected:  Student Rec Center (SRC)

Scope:  Due to a failing steam flow meter and damaged steam expansion joint, the steam heat and hot water to the Student Recreation Center will be shutdown to affect repairs. The meter, expansion joint, and associated piping will be re-insulated after repairs. All work will take place in the tunnel and mechanical room 004.

Services Impacted:  This will affect the building heating systems and the domestic hot water.

Work Performed By:  S2 Industrial

ContactKyle Wilson, CPFM Utilities Maintenance Manager, 541-346-2246

Current construction and impacts information can be found on the UO Maps site.

12/12/22 – 12/13/22 Lewis Integrative Science Building NW Elevator Currently Offline

UPDATE:
The elevator was restored to service this morning.

 

Begin:  Monday, December 12th, 2022 – effective immediately

End:      Monday, December 12th, 2022 – this evening

Building(s) or Area(s) Affected:  Lewis Integrative Science Building NW Elevator

Scope:  The NW elevator is currently offline and an Otis technician is on his way.  Repairs are expected to be completed this evening.

Services Impacted:  Elevator to the basement is not working.

Work Performed By:  Otis

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

12/12/22 Huestis Hall Basement Fire Suppression System Shutdown

Begin:  Monday, December 12th, 2022 at 6:00 am

End:      Monday, December 12th, 2022 at 9:00 am

Building(s) or Area(s) Affected:  Huestis Hall Basement

Scope:  The fire suppression system will be offline to accommodate construction activities for the Huestis Hall renovation project.

Details:  Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

Special Instructions:  If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

Work Performed By:  Harvey & Price

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

12/12/22 – 12/21/22 Hayward Field NW Mechanical Room Construction Advisory

Begin:  Monday, December 12th, 2022

End:      Wednesday, December 21st, 2022

Building(s) or Area(s) Affected:  Hayward Field

Scope:  Contractors will be installing a platform to support equipment in the foyer into the NW mechanical room.

Services Impacted:  No services will be affected.

Work Performed By:  Clay’s Refrigeration and GBC Construction

ContactGene Mowery, CPFM Owner’s Representative, 541-346-5593 or 541-799-4016

Current construction and impacts information can be found on the UO Maps site.

12/12/22 – 12/23/22 University Hall and Villard Hall Heritage Project Exploratory Tasks Advisory

Begin:  Monday, December 12th, 2022, at 8:00 am

End:      Friday, December 23rd, 2022, at 4:00 pm

Building(s) or Area(s) Affected:  University Hall and Villard Hall

Scope:  For the Heritage Renovation project, our contractor and architect have several small exploratory tasks to complete within and around the two buildings.

Services Impacted:  The bulk of the work will be measuring and possibly drilling some small holes in walls, along with accessing attic spaces. None of the work will be particularly noisy or dusty.

Work Performed By:  Hennebery Eddy Architects and Fortis Construction

ContactTim Allenbaugh, CPFM Owner’s Representative, 541-346-8214

Current construction and impacts information can be found on the UO Maps site.

 

12/12/22 – 1/31/23 PLC Classroom Construction Noise Advisory

Begin:  Monday, December 12th, 2022

End:      Tuesday, January 31st, 2023

Building(s) or Area(s) Affected:  Prince Lucien Campbell Hall Rooms 348, 353, and adjacent rooms

Scope:  PLC 348 and 353 will be renovated into a single classroom

Services Impacted:  Most construction activity will be restricted to the interior of the two rooms however, some construction related noise can be expected in adjacent areas.  The bulk of the work will take place over the winter break, with less intrusive work continuing into the first weeks of winter term.

Work Performed By:  GBC Construction

ContactTim Allenbaugh, CPFM Owner’s Representative, 541-346-8214

Current construction and impacts information can be found on the UO Maps site.

12/12/22 – 01/06/23 Knight Library 2nd Floor Paint Odor Advisory

Begin:  Monday, December 12th, 2022 at 6:00 am

End:      Friday, January 6th, 2023 at 3:00 pm

Building(s) or Area(s) Affected:  Knight Library 2nd Floor

Scope:  Painting will be occurring in the South Reading Room on the 2nd floor. Portions of the space will be taped off to contain areas of active work.

Services Impacted:  Paint odor may be experienced.

Work Performed By:  Bridgeway

ContactBrianna Liberty, CPFM D&C Design Associate, 541-346-7612 or 541-556-9618

Current construction and impacts information can be found on the UO Maps site.

 

12/12/22 -1/6/23 Lokey Education Elevator and Restrooms Shutdown Advisory

UPDATE 12/29/22:  Due to unexpected delays the completion date for this work is now scheduled for 1/6/23

Begin:  Monday, December 12, 2022

EndFriday, December 30, 2022 Friday, January 6th, 2023

Building Affected:  Lokey Education Restrooms #172, #173, #272, #273

Scope:  Due to the elevator modernization project, and associated ongoing construction, the first and second floor restrooms immediately adjacent to the elevator will be closed for the duration of Winter Break. In addition, the elevator will be out of service during this time.

Services Impacted:

  • Restrooms #172, #173, #272, #273 will be shut down.  Please see map below for nearby facilities in HEDCO.
  • The elevator will be offline.  Please use the stairs to the north of the elevator or by classroom 176.

Work Performed By:  Ryan Thomas construction

ContactDamon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285

Current construction and impacts information can be found on the UO Maps site.